Result or Product of this Process

This process is used to request a Journal Voucher.

    Project Managers should use this process to:

    • Move costs from one GL to another within a project
    • Move costs from one project to another project

    DoF Accounting will use this process to:

    • Convert the project from a Capital to an Expense project
    • Move asbestos/moving to a separate cost object
    • Convert non-billable time to billable
    • Split the project into multiple projects after project completion

    1. Initiation

    2. Final Invoice?

    3. Acct Change eB Info and Create JV

    4. Correct Project GL? (Decisional Step)

    5. PM Creates Budget Change Process

    6. POs on Project? (Decisional Step)

    7. PM Creates Commitment Change Process

    8. Account Creates GL Change JV

    9 Asbestos Move? (Decisional Field)

    10. Acct Updates eB & Creates Asbestos JV

    11. Billable/Non-Billable (Decisional Step)

    12. eB Admin Changes Project Number

    13. Previous Time Bill? (Decisional Step)

    14. Accounting Creates Billable Time JV

    15. Wrong Project Cost? (Decisional Step)

    16. Acct Creates Transfer JV

    17. eB Admin Creates/Joins Projects

    18. Acct Creates Cost Object IO

    19. PM Determines/Triggers Reallocation

    20. Finance Reallocates Cost

    21. Accounting Creates Reallocation JV

    22. Finish

     

     


     

     

     

    Instructions for Project Managers

    1. Complete Section A

    2. To move costs from one GL to another on this project complete Sections B and C

    3. To move costs from this project to another project (or vice versa) complete Sections B and C.
      If you are not the PM on the other project you should attach documentation (email) indicating that the PM of the other project accepts the charges.
    4. If "other" provide as much information as possible.

    Note: By using this process you are requesting a JV. The request is reviewed by accounting resources prior to any processing. If you do not have complete information fill in only the required fields and the information you have and accounting will guide you on any other information that is needed.

    DoF Accounting Instructions

    1. Complete Section A
    2. To convert this project from a Capital to Expense project (or vice versa) complete Section E.
    3. To move Asbestos/Moving to a separate cost object , complete Section E.
    4. To convert non-billable time to billable, complete Section F.
    5. To split this project into multiple projects after completion, complete Sections D and E.