Result or Product of this Process

The 06.01 Letter of Release - Change Order Request process is used:

  • To request a Letter of Release
  • Either by the contractor or the project manager to initiate a change to an e-Builder commitment. (Purchase Order)
  • CORs (one or multiple) must be processed using the 06.02 - General Contract Change Order process.

    This process can be used to generate the Change Order Request (COR). One or more CORs must be included in a General Conract Change Order process in order for commitments (POs) to be changed.

    When you change a commitment (PO) you must also ensure that there is sufficient budget to cover the total of the changes.

    Start/Initiation

    NAICS 1 = A/E?

    NAICS 2 - NOT A/E?

    NAICS 3 - NOT A/E?

    Improper Change Order Type

    PStatus Valid for $

    PM FIXES Project Status w/a PMUa

    $0 Change?

    LOR?

    Is this a LOR?

    Is $ 0?

    Data Entry Error?

    PO CO ONLY?

    Pm Enters Data

    Conditional Questions

    Contract Required

    Hold For Contract Execution

    Program Manager Review

    CC Director Approval

    Initiator Revise

    eB Admin Review

    COR Hold for GC-CO

    SAP Hold Step

    COR AMT <0>?

    Comm Chng Items Mssng / Zero

    Zero Dollar Tot COR?

    Ready for Owner?

    Initiator Hold

    A/E on Project?

    A/E Review

    Initiator Revise & Resubmit

    PM Approves/Rejects & Verifies Funding

    Budget Change Req'd

    Program Manager Review and Approval

    Finish


    • No labels