1. Timing Calibrations of X-ray missions
1.1 Summary of Timing Requirement and Calibrations
Mission/Instruments | Science Requirement Absolute Time | Timing System Design | Timing Calibration Status | In-orbit Timing Calibration Targets | Reported Issues | Reference | ||||
---|---|---|---|---|---|---|---|---|---|---|
Requirement | Goal | GPS Receiver | Clock Stability | Offset | Deviation, sigma | Notes | ||||
RXTE/PCA | 10μsec | none | No | Calibrated: (Absolute, not relative to radio) | Calibrated: 3.4 μsec Uncalibrated: ~50 usec | Calibration: Spline-based calibration against ground timing standards, including ground time assignment error. Uncalibrated: Mission operations maintained on-board clock to within 100 usec of UTC using clock frequency steering | PSR B1821-24 60 μsec | Before 1997-04-29, increased timing jitter 8 μsec | Timing Budget PSR B1821 Crab | |
RXTE/HEXTE | 10 μsec | none | See above | See above | Event by event has 7.6 μsec resolution. "the HEXTE absolute time reference is accurate within a fraction of a millisecond.(10.1086/305377)" | delay 0-1 μsec (corrected?) | None | HXTE Timing (10.1086/305377) | ||
Chandra/ACIS | 0.25625 s (one minor frame start time) | 0.001 s (synchronize minor frame starts) | No (sync DSN) | 3.2 μsec | 285 ± 6 μsec | None at present | Davis et al. 2003 (davis.pdf) | |||
Chandra/HRC | 16 μsec | 4 ± 4 μsec | Crab PSR B1821-24 | Note: Precision relative to RXTE. Due to a wiring problem, photon time tag gets attached | Davis et al. 2003 Rots 2006 | |||||
XMM-Newtion/EPIC-PN | 1 ms | none | No | - | -354±11 μsec | 108 μsec ( 1 sigma) | Note: Timing = -306 +/- 16 μsec, Burst = -387+/-13 μsec. Note: XMM-Newton EPIC-MOS was deleted from the table. | Crab pulsar (bi-annual) | None currently | Kirsch et al, SPIE, 5165, 85 Martin-Carrillo et al, A&A, 545, A126 (2012) |
INTEGRAL/SPI | L.Kuiper 2003 L.Kuiper 2019 | |||||||||
INTEGRAL/IBIS | -248±2 μsec | 61 μsec | Offset is w.r.t. radio main-pulse using ISGRI 20-100 keV data collected during INTEGRAL Revolutions 47 - 1877 (last date Oct. 23, 2017); Jodrell Bank radio eph. folding | same above | ||||||
Swift/BAT | 100 ms | 100 usec | No | ~ 6.572 x 10^-8 s/s | Uncalibrated: tens of seconds | Uncalibrated: N/A Calibrated: ~ 50 μs | BAT instrument has 100 usec time-stamping quantization, which is dominant term in uncertainty. Clock measurements made by mission operations & ground station, and applied as calibration when barycentering. | Crab pulsar (annual) | None at present | G. Cusumano et al 2012 (10.1051/0004-6361/201219968) BAT team wiki page; private communication with Michael Tripicco see BAT Wiki: Pre-launch Timing, BAT Wiki (410.4-SPEC-0005F.pdf) (Limited Access) |
Swift/XRT | ~ 10 ms | No | ~ 270 μs | Clock measurements made by mission operations & ground station, and applied as calibration when barycentering. | Crab pulsar | None at present | G. Cusumano et al 2012 D. Burrows et al. 2005 | |||
Suzaku/XIS | No science requirement defined. | No (sync. ground) | 1.9 x 10^-9 s/s | Not confirmed. | N/A | A0535+262, Her X-1, etc | N/A | Y.Terada et al 2008 (10.1093/pasj/60.sp1.S25) | ||
Suzaku/HXD | ~ 70 μsec
| 360±150 μsec (90%) (270±130 μsec | “offset” is defined from the difference from the average arrival time of Crab among X-ray missions and the HXD in the simultaneous observation of Crab. | Crab for coordinated PSR1509-58 | Timing shift by a failure in time stamp at the ground station during 2012-2014 (Shu Koyama, Fixed) | |||||
NuSTAR/FPM | Should be 100 ms | none | No | Freely drifting by ~3 ms/day. | 65 μs (1-sigma) | Crab | ~5ms offset using Corrected through | Bachetti+ in prep (can distribute early copy) | ||
Fermi/LAT | -111 ±4µs | 57 µs | 9 years of LAT data; see also Sci. 334, 69 (2011) for 9 months after launch value of -138 us +/- 12 us +/- 21 us; Jodrell Bank radio eph. folding | |||||||
Fermi/GBM (BGO) | -222 ±4µs | 56 µs | 100-300 keV band; data from Nov-2012 | |||||||
Fermi/GBM (NaI) | ||||||||||
AstroSat/LAXPC | None defined | Yes (offline referral) | 4 μsec rms after GPS synchronization | 316 ±70µs | 118 µs (rms) | The offset is with respect to Fermi-LAT ephemeris | Crab Pulsar (with Radio) | None at present | D. Bhattacharya 2017 (10.1007/s12036-017-9461-x) Basu et al (in prep) | |
AstroSat/CZTI | None defined | Yes (offline referral) | 3 μsec rms after GPS synchronization | -650 ±70µs | 83 µs (rms) | The offset is with respect to Fermi-LAT ephemeris | Crab Pulsar GRBs | None at present | D. Bhattacharya 2017 (10.1007/s12036-017-9461-x) Basu et al 2018 Basu et al (in prep) | |
Insight-HXMT/HE | Yes | 3 x 10^-8 s/s | 24.7 µs | 12.1 µs | The offset is with respect to NICER | Crab (with NICER) |
| |||
Insight-HXMT/ME | 10.1 µs | 8.6 µs | The offset is with respect to NICER | |||||||
Insight-HXMT/LE | 864.7 µs | 15.8 µs | The offset is with respect to NICER | |||||||
Hitomi/SXS, SXI, HXI, SGD | 350 μsec | 35 μsec | Yes | 0.01μsec(GPSR) | ~ 120-230 μsec | <3.0 usec (3 sigma) | Crab (with radio) note: using out-of-time event for SXI | absolute timing accuracy is much larger than expected on ground (3 μsec) | Y.Terada et al 2018 (10.1117/1.JATIS.4.1.011206) | |
NICER/XTI | 100 ns (RMS) | none | Yes | N/A | Uncalibrated: Calibrated: (Absolute, not relative to radio) | 100 ns (RMS) [requirement] | The NICER XTI timing system was calibrated on ground using an end-to-end system, with GPS simulator and precision X-ray pulse generator. Detector + system time delays of ~400 ns are included in the calibration. Combined error / noise terms designed to be < 100 ns (including GPS, X-ray detection, barycentering) | Crab Pulsar PSR B1821-24A PSR B1937+21 | Precise 1-second offset in on-board timestamps due to flight software bug; corrected using TIMEZERO keyword in pipeline-processed FITS data files. (see HEASARC page for detail) | Markwardt et al. (in prep.) |
eROSITA | ||||||||||
XRISM/Resolve | 1 msec | none | Yes | same as Hitomi | <1 ms | <1 ms | the values (1 msec) are the requirement including both offset and deviation. | (under discussion) | See In-flight Calibration Plan in IACHEC 2021 virtual meeting; xrism_ifcp_iachec_20210416.pdf | |
XRISM/Xtend | 10 msec | none | Yes | < 10 ms | < 10 ms | the mission requirement values. | (under discussion) |
Mission completed.
Future Mission
1.2 Point of Contacts
Mission | PoC (last updated 30 June 2021) |
---|---|
RXTE | Craig Markwardt, Arnold Rots |
Chandra | Vinay Kashyap, Arnold Rots |
XMM-Newton | Felix Fuerst, Simon Rosen |
Swift | Amy Lien, Giancarlo Cusumano |
INTEGRAL | Guillaume Belanger, Volodymyr SAVCHENKO,Lucien Kuiper |
NuSTAR | Matteo Bachetti, Katja Pottschmidt |
Astrosat | Gulab Dewangan, Dipankar Bhattacharya |
HXMT | Xiaobo LI |
NICER | Craig Markwardt, Teruaki Enoto |
eROSITA | Michael Freyberg |
Suzaku | Yukikatsu Terada |
Hitomomi | Yukikatsu Terada |
XRISM | Yukikatsu Terada |
2. In-orbit Timing Calibration Plan/Observations
2.1 Archive Data
2.1.1 List of Coordinated Observations useful for Timing
2.1.2 Reports
2.2 New Coordinated Observations
3. Studies on Timing
3.1 effects on timing products (power spec, light curve etc) by the detector’s behavior (dead time, grade selection of calorimeter etc)
4. Timing Tools, (with Statistic Group)
5. Working Group Meeting Notes
(after 14th IACHEC meeting in Japan)
- 28 April 2020
- 15 Sep 2020
- 20 April 2021
- 12 May 2020
- 15 Oct 2021