Project Timelines and Milestones:
- Goal is to roll out HR Staffing Services web site by early fall
Revised timeline and major milestones for the NEO web site project:
- 4/11 RFP distributed
- 4/23 Vendors Selected
- 5/1 Kickoff Meeting
- 9/3 Target Release Date
Consolidated Design and Writing Calendar (updated 5/21/08)
Date |
Description |
Contact |
Comments |
5/16/08 |
Photography comments to Wing |
Ken |
To confirm choice of photography direction |
5/16/08 |
1st writing deliverable |
Kath T-L |
To Janet and Julienne |
5/23/08 |
Feedback on 1st writing deliverable |
Janet |
To Kath T-L |
5/27/08 |
1st design review |
Wing |
In person presentation |
5/27/08 |
Identify next pages to be written |
Janet and Julienne |
To Kath T-L |
5/30/08 |
2nd writing deliverable |
Kath T-L |
To Janet and Julienne |
6/2/08 |
Design direction decision |
Ken |
To Wing |
6/6/08 |
Feedback on 2nd writing deliverable |
Janet |
To Kath T-L |
6/12/08 |
2nd design review |
Wing |
Via internet |
6/12/08 |
Identify next pages to be written |
Janet and Julienne |
To Kath T-L |
6/12/08 |
Usability review begins |
Ranjani |
|
6/13/08 |
3rd writing deliverable |
Kath T-L |
To Janet and Julienne |
6/17/08 |
Usability review results |
Ranjani |
To Ken |
6/20/08 |
Feedback on 3rd writing deliverable; confirm final writing deliverables |
Janet |
To Kath T-L |
6/18/08 |
Design feedback |
Ken |
To Wing |
6/26/08 |
3rd design review |
Wing |
Via internet; final design presentation |
6/27/08 |
Sign-off on design |
Ken |
To Wing |
6/27/08 |
4th writing deliverable |
Kath T-L |
To Janet and Julienne, final pages |
7/1/08 |
Final design delivered |
Wing |
Photoshop files delivered to Bob |