Result or Product of this Process

The 04.01 Bidding process is used for the entire process of Bid List Approval, Release to Bid and Bid Award Recommendation including these specific steps.

  • Obtain an approved bidder list
  • Assemble and gain approval of the bid package
  • Indicate that the bid has been released
  • Submit the Bid Tab for review
  • Recommend an award
  • Indicate that the awarded bidder will be/has been notified

Note that the Bidding process is used to inform, indicate that actions have been or will be taken, and to gain approvals.

The Bid Package is assembled and released in the Bid module, which is also where analysis of the bid responses and accompanying documents take place.

Process Details

    The Initiator, usually the Project Manager, uses the bidding process and the bidding module to:

    • Compose a list of potential bidders and receive approval on the bidder list (There is an option to bypass Bid List Approval)
    • Prepare the bid documents and assemble the bid package.
    • Release the bid package through the e-Builder Bidder Portal.
    • Answer and respond to questions about the bid from the bidders.
    • Tabulate and analyze the submitted bids.
    • Make an award recommendation.
    • Gain approval of the award recommendation.
    • Award the bid and notify the winning bidder.
    • Notify bidders not selected.

    To make the Step descriptions for Bidding easier to read they have been separated into the three parts (tabs). 

    1. Start Process (Complete Initial Bidding Form)

    2. Furniture or AV Bid? (Conditional)

    3. Skip Bid List Approval (Conditional)

    4. Vendor Manager Reviews Bid List

    5. Initiator Revise

    6. Program Manager Review

    7. Campus Construction? (Conditional)

    8. SP&T Program? (Conditional)

    9. SPT Director Review

    10. CC Director Review

    11. OCP? (Conditional)

    12. OCP Director Review

    13. M&U? (Conditional)

    14. Utilities Program? (Conditional)

    15. Utilities Director Review

    16. SEG Program? (Conditional)

    17. SEG Director Review

    18. O&M Director Review

    19. M&U Director Review

    20. Campus Services? (Conditional)

    21. CS Director Review

    22. IBO Director Review

    23. Initiator Revise

    24. Approved Bid List (Automation)

    25. Initiator Prepares Bid Documents

    26. GC Previously Approved? (Decisional Step)

    27. Assemble Bid Package

    28. Program Manager Reviews Package

    29. Initiator Releases Bid

    30. Initiator Recommend Vendor

    31. Selection of Source (Automatic Step)

    32. Vendor Manager Review of SoS

    33. Program Manager Review

    34. Initiator Revise

    35. Campus Construction (Decisional Step)

    36. SP&T Program? (Decisional Step)

    37. SPT Director Review

    38. M&U (Decisional Step)

    39. Utilities Program (Decisional Step)

    40. Utilities Director Review

    41. SEG Program

    42. SEG Director Review

    43. O&M Director Review

    44. Vendor Manager Review of SoS

    45. Campus Construction (Decisional Step)

    46. CC Director Review

    47. OCP? (Decisional Step)

    48. OCP Director Review

    49. M&U? (Decisional Step)

    50. M&U Director Review

    51. Campus Services? (Decisional Field)

    52. CS Director Review

    53. IBO Director Review

    54. Initiator Award Bid

    64. Finish

    Potential Bidders

    Use the Lookup link to display a menu that allows potential bidders to be added.

    Sole Source

    Indicate if this is a Sole Source procurement. If it is Sole Source, provide a reason.