The General Contract Change Order process combines previously approved Change Order Requests, generated using the 06.01 Letter or Release/ Change Order Request process, into a Contract Change Order for final approval.

3/27/2018 - Both the process and the instructions here are being updated.

    • This process is usually started by the project manager, however it can be started by the contractor.
    • The process routes the GCCO for approval and signature by the appropriate parties based on dollar amount and program.

    1. Start

    2. PM Review

    3. Initiator Revise

    4. Project Budget Change (Decicional Step)

    5. $0 Change? (Decisional Step)

    6. Spawn $0 Budget Change

    7. Spawn Additional Funding

    8. Time Only? (Decisional Step)

    9. Fin. Analyst Holds for Completion

    10. GC Change Order M.M

    11. Sum of Attached CORs

    12. Success? (Decisional Step)

    13. Commitment Value CO

    14. Success?

    15. GC Change Order M.M. (Mail Merge)

    16. Initiator Resubmit

    17. PM Review Mail Merge

    18. Vendor Signature

    19. Vendor Signature St

    20. A/E Review Required? (Decisional)

    21. A/E Signature

    19. PM Review

    20. Program Manager Review

    21. Program Director Review

    22. <10m? (Decisional Step)

    22. CC Director Executes

    23. CC DIrector Signs

    24. <$100 (Decisional Step)

    25. Deputy EVPT Review

    26. EVPT Executes

    27. CO Signature Finalize

    28. Compl CORs on Hold

    29. Success? (Decisional Step)

    30. eB Admin Resubmit

    31. Finish

    • No labels