You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 35 Next »

The General Contract Change Order process combines previously approved Change Order Requests, generated using the 06.01 Letter or Release/ Change Order Request process, into a Contract Change Order for final approval.

3/27/2018 - Both the process and the instructions here are being updated.

    • This process is usually started by the project manager, however it can be started by the contractor.
    • The process routes the GCCO for approval and signature by the appropriate parties based on dollar amount and program.

    1. Start

    2. PM Review

    3. Initiator Revise

    4. Project Budget Change

    5. $0 Change?

    6. Spawn $0 Budget Change

    7. Spawn Additional Funding

    8. Time Only? (Decisional Step)

    9. Fin. Analyst Holds for Completion

    10. GC Change Order M.M

    11. Sum of Attached CORs

    12. Success (Decisional Step)

    13. Initiator Resubmit

    14. PM Review Mail Merge

    15. Vendor Signature

    16. Vendor Signature St

    17. A/E Review Required? (Decisional)

    18. A/E Signature

    19. PM Review

    20. Program Manager Review

    21. Program Director Review

    22. CC Director Executes

    23. CC DIrector Signs

    24. <$100 (Decisional Step)

    25. Deputy EVPT Review

    26. EVPT Executes

    27. CO Signature Finalize

    28. Compl CORs on Hold

    29. Success? (Decisional Step)

    30. eB Admin Resubmit

    31. Finish

    • No labels