The General Contract Change Order process combines previously approved Change Order Requests, generated using the 06.01 Letter or Release/ Change Order Request process, into a Contract Change Order for final approval.

3/27/2018 - Both the process and the instructions here are being updated.

    • This process is usually started by the project manager, however it can be started by the contractor.
    • The process routes the GCCO for approval and signature by the appropriate parties based on dollar amount and program.

    1. Start

    2. PM Review

    3. Initiator Revise

    4. Project Budget Change

    5. $0 Change?

    6. Spawn $0 Budget Change

    7. Spawn Additional Funding

    8. Time Only? (Decisional Step)

    9. Fin. Analyst Holds for Completion

    10. Change Order M.M

    11. Sum of Attached PCOs

    12. Success (Decisional Step)

    13. Initiator Resubmit

    14. PM Review Mail Merge

    15. A/E Signatures

    16. Vendor Signature

    17. PM Signature

    18. Program Manager Review

    19. Program Director Review

    20. Campus Construction Review

    21. >=$1M (Decisional Step)

    22. EVPT Review

    23. SAP C.O. Hold Step

    24. Compl PCOs on Hold

    25. Success? (Decisional Step)

    26. Initiator Resubmit

    27. Finish

     