The General Contract Change Order process combines previously approved Change Order Requests, generated using the 06.01 Letter or Release/ Change Order Request process, into a Contract Change Order for final approval.
    • This process is usually started by the project manager, however it can be started by the contractor.
    • The process routes the GCCO for approval and signature by the appropriate parties based on dollar amount and program.

    1. Start

    2. Time Only? (Decisional Step)

    3. Change Order M.M

    4. Sum of Attached PCOs

    5. Success (Decisional Step)

    6. Initiator Resubmit

    7. Initiator Review

    8. A/E Signatures

    9. Vendor Signature

    10. PM Signature

    11. Program Manager Review

    12. Program Director Review

    13. Campus Construction Review

    14. >=$1M (Decisional Step)

    15. EVPT Review

    16. SAP C.O. Hold Step

    17. Compl PCOs on Hold

    18. Success? (Decisional Step)

    19. Initiator Resubmit

    20. Finish

     