Result or Product of this Process

The 04.00 Bidding process produces:

  • An Approved Bidder List
  • The Bid Package containing Bid Documents
  • A released bid
  • Tabulation of bidder submissions
  • An approved award recommendation
  • An Awarded Bidder who has been notified of the Award
  • Bidders notified that they have not been selected for the Award

Process Details

    The Project Manager uses the bidding process and the bidding module to:

    • Compose a list of potential bidders and receive approval on the bidder list (There is an option to bypass Bid List Approval)
    • Prepare the bid documents and assemble the bid package.
    • Release the bid package through the e-Builder Bidder Portal.
    • Answer and respond to questions about the bid from the bidders.
    • Tabulate and analyze the submitted bids.
    • Make an award recommendation.
    • Gain approval of the award recommendation.
    • Award the bid and notify the winning bidder.
    • Notify bidders not selected.

    Until all cost processes are released we will not kick off the commitment/purchase order process.

    Step descriptions for Bidding have been separated into the three discrete parts below. While Bidding is one process, the supporting documentation is made easier to read by making this division..

    1. Start

    2. Furniture or AV Bid? (Decisional Step)

    3. A133 Been Signed? (Decisional Step)

    4. Vendor Manager Review

    5. Initiator Revise

    6. Program Manager Review

    7. Sole Source? (Decisional Step)

    8. Campus Construction? (Decisional Step)

    9. SP&T Program? (Decisional Step)

    10. SPT Director Review

    11. Projects Director Review

    12. CC Director Review

    13. OCP? (Decisional Step)

    14. OCP Director Review

    15. M&U? (Decisional Step)

    16. Utilities Program? (Decisional Step)

    17. Utilities Director Review

    18. SEG Program? (Decisional Step)

    19. SEG Director Review

    20. O&M Director Review

    21. M&U Director Review

    22. Campus Services? (Decisional Step)

    23. CS Director Review

    24. IBO Director Review

    25. Initiator Revise

    26. VPF Procurement Reviews Bid Package

    27. Approved Bid List (Automatic Step)

    28. Initiator Prepares Bid Documents

    29. Has A133 Been Signed? (Decisional Step)

    30. DoF Procurement Assembles Bid Package

    31. Program Manager Reviews Package

    32. Projects Director Reviews Package

    33. Initiator Releases Bid (The initiator works in the Bidding Module prior to Submitting this step)

    34. Initiator Recommend Vendor

    35. Selection of Source (Automatic Step)

    36. DoF Procurement Reviews Selection

    37. Program Manager Review

    38. Initiator Revise

    39. Campus Construction (Decisional Step)

    40. SP&T Program? (Decisional Step)

    41. SPT Director Review

    42. Projects Director Review

    43. M&U (Decisional Step)

    44. Utilities Program (Decisional Step)

    45. Utilities Director Review

    46. SEG Program

    47. SEG Director Review

    48. O&M Director Review

    49. DoF Procurement Review

    50. A133 Been Signed? (Decisional Step}

    51. >10M (Decisional Step)

    52. One Bid? (Decisional Step)

    53. Lowest Bid? (Decisional Step)

    54. VPF Procurement Review

    55. Campus Construction (Decisional Step)

    56. CC Director Review

    57. OCP? (Decisional Step)

    58. OCP Director Review

    59. M&U? (Decisional Step)

    60. M&U Director Review

    61. Campus Services? (Decisional Field)

    62. CS Director Review

    63. IBO Director Review

    64. Initiator Award Bid

    65. Finish

     

    Contract Management

    Potential Bidders

    Use the Lookup link to display a menu that allows potential bidders to be added.

    Sole Source

    Indicate if this is a Sole Source procurement. If it is Sole Source, provide a reason.