Result or Product of this Process
- An Approved Bidder List
- The Bid Package containing Bid Documents
- An Awarded Bidder who has been notified of the Award
- Bidders notified that they have not been selected for the Award
Process Details
The Project Manager uses the bidding process and the bidding module to:
- Compose a list of potential bidders and receive approval on the bidder list
- Prepare the bid documents and assemble the bid package
- Release the bid package through the e-Builder Bidder Portal
- Answer and respond to questions about the bid from the bidders
- Tabulate and analyze the submitted bids
- Make an award recommendation
- Gain approval of the award recommendation
- Award the bid and notify the winning bidder
- Notify bidders not selected
Awarding the bid in e-Builder kicks off the commitment/purchase order process
Step descriptions for Bidding have been separated into the three discrete parts below. While Bidding is one process, the supporting documentation is made easier to read by making this division..
1. Start
2. Furniture or AV Bid? (Decisional Step)
3. A133 Been Signed? (Decisional Step)
4. Vendor Manager Review
5. Initiator Revise
6. Program Manager Review
7. Sole Source? (Decisional Step)
8. Campus Construction? (Decisional Step)
9. SP&T Program? (Decisional Step)
10. SPT Director Review
11. Projects Director Review
12. CC Director Review
13. OCP? (Decisional Step)
14. OCP Director Review
15. M&U? (Decisional Step)
16. Utilities Program? (Decisional Step)
17. Utilities Director Review
18. SEG Program? (Decisional Step)
19. SEG Director Review
20. O&M Director Review
21. M&U Director Review
22. Campus Services? (Decisional Step)
23. CS Director Review
24. IBO Director Review
25. Initiator Revise
26. VPF Procurement Reviews Bid Package
27. Approved Bid List (Automatic Step)
28. Initiator Prepares Bid Documents
29. Has A133 Been Signed? (Decisional Step)
30. DoF Procurement Assembles Bid Package
31. Program Manager Reviews Package
32. Projects Director Reviews Package
33. Initiator Releases Bid
34. Initiator Recommend Vendor
35. Selection of Source (Automatic Step)
36. DoF Procurement Reviews Selection
37. Program Manager Review
38. Initiator Revise
39. Campus Construction (Decisional Step)
40. SP&T Program? (Decisional Step)
41. SPT Director Review
42. Projects Director Review
43. M&U (Decisional Step)
44. Utilities Program (Decisional Step)
45. Utilities Director Review
46. SEG Program
47. SEG Director Review
48. O&M Director Review
49. DoF Procurement Review
50. A133 Been Signed? (Decisional Step}
51. >10M (Decisional Step)
52. One Bid? (Decisional Step)
53. Lowest Bid? (Decisional Step)
54. VPF Procurement Review
55. Campus Construction (Decisional Step)
56. CC Director Review
57. OCP? (Decisional Step)
58. OCP Director Review
59. M&U? (Decisional Step)
60. M&U Director Review
61. Campus Services? (Decisional Field)
62. CS Director Review
63. IBO Director Review
64. Initiator Award Bid
65. Finish