Result or Product of this Process
The Bidding process allows the Project Manager to manage the bid for the entire bid process including:
- Bid List approval
- Release to bid
- Bid award recommendation.
Process Details
This process includes Bid List Approval, Release to Bid and Bid Award Recommendation.
Step descriptions for Bidding have been separated into the three discrete parts below. While Bidding is one process, the supporting documentation is made easier to read by making this division.
This is a draft. Once the process is finalized I will add step numbers. I also plan to add links to Bidding Module documentation and instruction where necessary.
- 1, Start
2. Furniture or AV Bid? (Decisional Step)
3. A133 Been Signed? (Decisional Step)
4. Vendor Manager Review
5. Initiator Revise
6. Program Manager Review
7. Sole Source? (Decisional Step)
8. Campus Construction? (Decisional Step)
9. SP&T Program? (Decisional Step)
10. SPT Director Review
11. Projects Director Review
12. CC Director Review
13. OCP? (Decisional Step)
14. OCP Director Review
15. M&U? (Decisional Step)
16. Utilities Program? (Decisional Step)
17. Utilities Director Review
18. SEG Program? (Decisional Step)
19. SEG Director Review
20. O&M Director Review
21. M&U Director Review
22. Campus Services? (Decisional Step)
23. CS Director Review
24. IBO Director Review
25. Initiator Revise
26. VPF Procurement Reviews Bid Package
27. Approved Bid List (Automatic Step)
28. Initiator Prepares Bid Documents
29. Has A133 Been Signed? (Decisional Step)
30. DoF Procurement Assembles Bid Package
31. Program Manager Reviews Package
32. Projects Director Reviews Package
33. Initiator Releases Bid
34. Initiator Recommend Vendor
35. Selection of Source (Automatic Step)
36. DoF Procurement Reviews Selection
37. Program Manager Review
38. Initiator Revise
39. Campus Construction (Decisional Step)
40. SP&T Program? (Decisional Step)
41. SPT Director Review
42. Projects Director Review
43. M&U (Decisional Step)
44. Utilities Program (Decisional Step)
45. Utilities Director Review
46. SEG Program
47. SEG Director Review
48. O&M Director Review
49. DoF Procurement Review
50. A133 Been Signed? (Decisional Step}
51. >10M (Decisional Step)
52. One Bid? (Decisional Step)
53. Lowest Bid? (Decisional Step)
54. VPF Procurement Review
55. Campus Construction (Decisional Step)
56. CC Director Review
57. OCP? (Decisional Step)
58. OCP Director Review
59. M&U? (Decisional Step)
60. M&U Director Review
61. Campus Services? (Decisional Field)
62. CS Director Review
63. IBO Director Review
64. Initiator Award Bid
65. Finish