This process allows the Project Manager to change the project budget if funds are needed for non-PO Cost or for PO Only (no contract).
This process is started by the project manager

1. Process Start (Project Manager)
- The Project Manager fills out the required fields and clicks Submit.
- The next step is Return Funds?
2. Return Funds? (Decision Step)
- Return funds is a decision step.
- If funds are being returned to the program the next step is Program Manager Review A
- If funds are not being returned to the program the next step is Program Manager Review B
3. Program Manager Review A
- The Program Manager reviews the process, adds comments if necessary and when finished chooses to Submit or to Revise.
- If Submit is chosen the next step is Financial Analyst Adjusts Funding
- If Revise is chosen the next step is Initiator Revise and Submit.
4. Initiator Revise and Submit
- The Project Manager reads the comments, reviews process fields and updates as necessary and when finished chooses to Resubmit or to Void.
- Resubmit is chosen the next step is Return Funds
- If Void is chosen the next step is Finish
5. Financial Analyst Adjusts Funding
- The Financial Analyst reads the comments, adjusts the funding and then clicks Submit.
- The next step is Finish
6. True Up Form (Automatic Step)
- Automatic Step to generate the True Up form document
- The next step is Finish
7. Program Manager Review B
- The Program Manager reads the comments, reviews the process fields and chooses to Submit or Revise.
- If Submit is chosen the next step is CC Project?
- If Revise is chosen the next step is PM Reviews Com Initiator Revise and Resubmit
8. CC Project? (Decision Step)
- This is a decision step. e-Builder evaluates the Project Type to determine if the value is "Capital Renewal"
- If True the next step is Project Director Review
- If False the next step is M&U Project?
9. M&U Project? (Decision Step)
- This is a decision step. e-Builder evaluates the Project Type to determine if the value is "Utilities".
- If True the next step is M&U Director Review
- If False the next step is OCP Project?
10. OCP? (Decision Step)
- This step is a decision step. e-Builder evaluates the Project Type to determine if the value is "OCP"
- If True the next step is OCP Director Review
- If False the next step is Director of Housing Review
11. Projects Director Review
- The Projects Director reads the comments and review the process fields and has the option to Submit or Revise.
- If Submit is chosen the next step is CC Director Review
- If Revise is chosen the next step is Initiator Revise and Resubmit
12. CC Director Review
- The CC Director reads the comments and reviews the process fields and clicks Submit.
- The next step is Department Funding?
13. M&U Director Review
- The M&U Director reads the comments and reviews the process fields and clicks Submit.
- The next step is Department Funding?
14. OCP Director Review
- The OCP Director reads the the comments and reviews the process fields and clicks Submit.
- The next step is Department Funding?
15. Director of Housing Review
- The Director of Housing reads the the comments and reviews the process fields and clicks Submit.
- The next step is Department Funding?
16. Department Funding? (Decision Step)
- This is a decision step. e-Builder evaluates the value of the Department Funding field.
- If True the next step is Financial Analyst Adds Funding
- If False the next step is DoF Contingency?
17. DoF Contingency (Decision Step)
- This is a decision step. e-Builder evaluates the value of the Funding Source field.
- If True the next step is Financial Analyst Adds Funding
- If False the next step is EVPT Contingency?
18. EVPT Contingency (Decision Step)
- This is a decision step. e-Builder evaluates the value of the Funding Source field.
- If True the next step is Deputy EVPT Review
- If False the next step is CRSP/R-CRSP Committee Review
19. Deputy EVPT Review
The EVPT Office reads the comments and reviews the process fields and then clicks Submit.
The next step is Financial Analyst Adds Funding
20. Governance Review
- The CRSP Admin reads the comments and reviews the process fields and clicks Approve.
- The next step is True Up Form / Addi
21. True Up Form (Automatic Step to Generate Document)
- Automatic step to generate the true up form document
- The Next Step is Financial Analyst Adds Funding
22. Financial Analyst Adds Funding
The financial analyst adds the funding to the project and will compete the required process fields clicks to add funds.
The next step is Finish
23. Finish