Result or Product of this Process

 This process allows the Project Manager to change the project budget if funds are needed for non-PO Cost or for PO Only (no contract).

Process Details

    • The primary actor for this process is the Project Manager.
    • This process does not spawn other processes.

    Process Start (Project Manager)

    Return Funds? (Decision Step)

    Program Manager Review A

    Initiator Revise and Submit

    Financial Analyst Adjusts Funding

    True Up Form

    Program Manager Review B

    CC Project? (Decision Step)

    M&U Project? (Decision Step)

    OCP? (Decision Step)

    Project Director Review

    CC Director Review

    M&U Director Review

    OCP Director Review

    Director of Housing Review

    Department Funding? (Decision Step)

    DoF Contingency (Decision Step)

    EVPT Contingency (Decision Step)

    Deputy EVPT Review

    Governance Review

    True Up Form (Automatic Step to Generate Document)

    Financial Analyst Adds Funding

    Finish