 Result or Product of this Process

This process merges information stored in e-Builder with a document template to create a Memorandum of Understanding (MOU) and initial budget that can be shared with project sponsors or other parties.

 

Process Details

    • This process starts automatically when the 02.01 Team Assignment (TA) process is complete or can be initiated by the e-B admin.
    • The primary actor for this process is the Project Manager.
    • Secondary actors include the Provost Office,
    • The process does not spawn other processes

    1. Process Started by Spawn or by eB Admin

    2. PIT Meeting Required? Conditional Step

    3. PIT Meeting Occurs

    4. PM Verifies Team Assignments

    5. Provost Office Draft MOU

    6. Team Review

    7. Provost Office Review MOU Comments

    8. Program Manager MOU Review

    9. PM Checks Benchmark Data

    10. Draft MOU

    11. Provost Distributes to DLC for Review

    12. PM Enters Benchmark and S1 Estimate

    13. Program Manager Review

    14. CC Dir and Dir of Projects Review

    15. PM Revises Benchmark or S1 Estimate

    16. Provost Office Distributes to DLC

    17. Start Milestone Project Estimate (Spawned)

    18. Finish

    e-Builder generates a Word document for editing by the project manager. Copies of the MOU that are distributed for comment will be in PDF format and not be editable by the reviewers.

     

     

     

     