This process allows the project manager to change the project budget at any time following approval of the Stage 1 budget.
Process Start (By Project Manager)
The project manager fills out the required fields and takes the following action:
Submit
- Status of Process: Submitted
- Causes Field Validation: No
- Makes data field assignments
- Next Step: Return Funds?
Return Funds?
Decisional: Return funds to program?
- True
- Status of Process: Leave Status Unchanged
- Causes Field Validation: No
- Next Step: Program Manager Review A
- False
- Status of Process: Leave Status Unchanged
- Causes Field Validation: No
- Next Step: Program Manager Review B
Program Manager Review A
The program manager reviews the process and adds comments if necessary. When finished one of the following actions are taken:
- Submit
- Status of Process: Leave Status Unchanged
- Causes Field Validation: Yes
- Next Step: Financial Analyst Adjusts Funding
- Revise
- Status of Process: Leave Status Unchanged
- Causes Field Validation: No
- Add Comments: Yes
- Require Comments: Yes
- Data Field Assignments: N/A
- Next Step: Initiator Revise and Submit
Initiator Revise and Submit
The project manager reads the comments, reviews process fields and updates as necessary. When finished takes one of the following actions:
- Resubmit
- Status of Process: Leave Status Unchanged
- Causes Field Validation: Yes
- Data Field Assignments are made
- Next Step: Return Funds
- Void
- Status of Process: Void
- Causes Field Validation: No
- Add Comments: Yes
- Comments Required: Yes
- Data Field Assignments: N/A
- Next Step: Finish
Financial Analyst Adjusts Funding
The Financial Analyst reads the comments, adjusts the funding and then takes the following action:
Submit
- Status of Process: Leave Status Unchanged
- Causes Field Validation: Yes
- Data Field Assignments: N/A
- Next Step: Finish
Program Manager B Review
The program manager reads the comments and reviews the process fields and takes one of the below actions:
- Submit
- Status of Process: Leave Status Unchanged
- Causes Field Validation: Yes
- Data Field Assignments: N/A
- Next Step: CC Project?
- Revise
- Status of Process: Leave Process Unchanged
- Causes Field Validation: No
- Add Comments: Yes
- Require Comments: Yes
- Data Field Assignments: N/A
- Next Step: PM Reviews Com Initiator Revise and Resubmit
CC Project
This step is decisional. e-Builder evaluates the Project Type to determine if the project is Capital Renewal
- True
- Status of Process: Leave Status Unchanged
- Causes Field Validation: No
- Next Step: Project Director Review
- False
- Status of Process: Leave Status Unchanged
- Causes Field Validation: No
- Next Step: M&U Project?