Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Comment: Migrated to Confluence 4.0

Revised task list, after consulting with Qing:

F5 not a short-term concern
Using Thalia 1 as a dev environment

Now - API Test Plan and timeline - Andrew

May 4 - Thalia 2,3,4 as layers - Hunter
Thalia 2 - Front end / business layer
Thalia 3 - Alfresco
Thalia 4 - Database

May 8 - Test Environment Ready
Internal testing - Qing, Robin, Hunter

May 9 - API Test Writing beings - Andrew
May 9 - Communicate with Questcom, UI test plan and writing begins - Qing

May 15 - Back End code complete - Qing
May 25 - UI code complete - Robin

June - Test execution begins - Questcom, Andrew

June - User documentation - Tech Writer?

Date? - Production Cluster ready - Catherine (machine acquisition), Hunter?

Date? - Deployment Strategy
Engage Ops - backup, disaster recovery, machine support
Engage Helpdesk - first line support
ISDA software support plan - ?

Date? - User communications (before July Beta release)
Advertisement/marketing
Feedback/bug reporting channel established

...

Individual, dynamic task lists. Tasks should be of the form "Due date: description"

...