Scope:
This page details large tests. This does not include incremental assemblies & practice for each subsystem, which people will need to do before the launch rehearsal.
Test 1: Ground Test + CRIMP, 4/6
Required:
- Assembly checklists for guidance (should not be too rigorous, rely on training)
- Verification checklists for rigorous checking of proper assembly (should be very simple and clear and have photos)
- Flight team assignments
...
- Completed Avionics + Recovery Ground Test without cameras
- Refined packing lists
Test 2: Launch Rehearsal, 4/13
Required:
- Verification checklists for rigorous checking of proper assembly (should be very simple and clear and have photos)
- Flight team assignments
...
- Log single point failure locations
- Refine packing lists
- Add missing tools & materials
- Add missing flight parts
- Log Assembly times
- Overall start/finish
- By subsystem
- Final integration
- "Wish List" for additional GSE
- Practice rocket integration in hangar
Test 3: Launch Rehearsal, 4/20, 4/27 and/or 5/4
Scope:
- Pack tools & GSE listed in assembly checklists
- Pre-charge cameras, payload, and ALL altimeter batteries
- Transport only those tools to the hangar
- Set up tables & test stand as "launch tower" on Briggs prior to transport (simulate "FAR")
- Assemble Hermes II in the hangar
- Log & acquire any missing tools/GSE
- Put in "Final Integration" state
- Transport to Briggs Field A with GSE, including test stand as "launch tower"
- Perform Integration & Prelaunch procedures (except igniter, incl. raising to vertical)
- Verify telemetry in launch ready configuration
- Perform "rocket take down" procedures
- "Launch" with telemetry and video during a ground test
- Use recovery procedures to pick up & safe the rocket
- Transport back to lab
- Log all data
...
- Loosely simulate launch environment
- Allow extra tools to be obtained easily as long as they are logged
- Determine GSE needed for successful launch/recovery
- Train flight team
Test 4: Launch Simulation, 5/12-13 (stretch goal)
Required:
- GSE for packed configuration
- Refined checklists from above tests
- Pre-set, reasonable adverse conditions
...