This process is usually initiated by the CC planner or the project manager. Other roles with the ability to being the process are:
CC Planning Manager
R&M Manager
UTLITIES-Program Manager
e-B Admin
When not started by the CC planner the process routes to the CC planner as the second step.
After the PD form is completed this process spawns the 03.01 Milestone Project Budget Estimate process.
Card
label
Process Map
PDF
name
PD Form Workflow March 2018.pdf
Card
label
Step Descriptions
Toggle Cloak
1. Start
Cloak
If the process was initiated by CC Planner, the next step is Project Manager Review.
If not initiated by CC Planner, the next step is CC Planner Completes PD Form.
Toggle Cloak
2.CC Planner Created?
Cloak
If the initiator is the CC Planner the next step is Project Manager Review.
If the initiator is not the CC Planner then the next step is CC Planner Completes PD Form.
Toggle Cloak
3. CC Planner Completes PD Form
Cloak
CC Planner reviews the process, completes the required fields and selects one of the following actions: Submit, Revise or Void.
If Submit is chosen the next step is Project Manager Review.
If Revise is chosen the next step is Initiator Review.
If Void is chosen the next step is Finish.
Toggle Cloak
4. Project Manager Review
Cloak
The Project Manager reviews the process with the option to approve and Submit or to Revise.
To approve and submit the project manager must complete the required fields including section 9.1 on the process form by choosing the date.
If Submit is chosen the next step is Planning Manager and Prog. Manager Review.
If Revise is chosen the next step is CC Planner Revise.
Toggle Cloak
5. Initiator Review
Cloak
The process Initiator reviews the process, completes the required fields and clicks Reply.
The next step is CC Planner Completes PD Form
Toggle Cloak
6. CC Planner Revise
Cloak
The CC Planner reviews the process, completes the required fields, and clicks Resubmit.
The next step is Project Manager Review
Toggle Cloak
7. Planning Manager and Prog. Manager Review
Cloak
Project Manager and Program Manager review the process, complete the required fields and choose to Submit or Revise.
If Submit is chosen the next step is Working Committee Review
IfRevise is chosen the next step is CC Planner Revise
Toggle Cloak
8. Working Committee Review
Cloak
CC Planning Manager reviews the process with the working committee outside of e-Builder, completes the required fields and chooses to Submit or Put On Hold.
Included in the required fields is the question "Expected number of funding sources". Later in the process this field is used to determine whether or not to spawn the process.
If Submit is chosen theNext Step is Utilities, O&M and SEG Review
If Put On Hold is chosen the next step is Finish
Toggle Cloak
9.Utilities, O&M and SEG Review
Cloak
Utilities Director, O&M Director, and SEG Assignor review the process, add their comments and click Submit.
The next step is Create PD Form
Toggle Cloak
10.Create PD Form (Mail Merge Step)
Cloak
The PD form is created and stored in the Documents folder.
Next Step: One Funding Source? (Conditional)
Toggle Cloak
11. One Funding Source? (Conditional)
Cloak
Used to identify whether or not 03.01 Milestone Project Estimate should be spawned. It is assumed that if there is only one funding source, 03.01 Milestone Project Estimate has not been previously started; therefore, it will be spawned from this process. (The information about a single funding source was gathered in step 8 of the process)
If there is one funding source the “03.01 Milestone Project Estimate” is spawned.
If there is more than one funding source, the next step is Finish.
Process 03.01 needs to be either (1) started manually or (2) a pre-existing instance of 03.01 should be updated with the Infrastructure cost data as documented in the PD Form process.
When “One Funding Source?” is “True”, the process will proceed to this spawn step. In the spawn step the 03.01 – Milestone Project Estimate process will be started and moved to the first step of that workflow.