Jan 29, Feb. 5, 12, 19: requirement gathering meeting (Craig, Mike, Qing, Robin). Summary notes from the meetings will be sent to Derek and Catherine
By End of March
--------------------
Thalia Deliverables:
- API skeleton and content model for the ECM will be complete
- We will have unit tests for the APIs
Stellar Deliverables:
- Stellar has completed their data export script
During April
-----------------
- Thalia will import the data from Stellar's export, to confirm that the model is correct, and adjust as needed
- Thalia team will build out the API, implementing all functionality
During May
-----------------
- Thalia will perform load testing, do quality assurance and bug fixing
By End of May
------------------
- Thalia delivers functionally complete, well tested API