Working Group: Chris Gresham. Patrick McNeal, Garry Zacheiss, Oliver Thomas, Steve Landry and Patricia Sheppard
- Introduction
- much of the leg work was done this past winter and spring - hence Releaseball!
- Steve Buckley has charged Patrick with working on solving software release problems, hence this team/working group!
- Marilyn would like to see a proposal by mid August, we are working around vacation schedules and aiming for the week of the 16th
- Project Sponsor
- the team agrees that this work would benefit from an external sponsor
- sponsor would have a vested interest in IS&T software release, act as consultant, provide feedback and hopefully be able to get behind the processes we propose
- Steve Gass from Libraries is our top candidate - Oliver and Pat will discuss this with him
- Scope of Work for this Phase
- What is in scope: RELEASE - the process by which IS&T introduces products and services to the MIT community
- we have short term goals for this team (see #4 below)
- there are improvements as well as new work to achieve the long term vision ("the big picture")
- portfolio management
- process for finding a home for orphaned products (and making recommendations)
- escalation paths
- change communication and management
- we can sequence the types of products and services that will follow the proposed release processes (desktop, Athena software, enterprise services)
- this will allow for iterative approach, make improvements as we go
- What is NOT in scope: how IS&T makes decisions on what products and services it offers, prioritization of work and resource allocation ("the pipeline")
- this can be addressed by a different team or as part of the long term goals of the larger effort
- What is in scope: RELEASE - the process by which IS&T introduces products and services to the MIT community
- Goals for this team (what we want to present to Marilyn)
- 4-5 release process templates
- decision making guide as to whether you have a release and if so, what size
- definition of the various roles in the release processes
- Approach
- we have drafts of some release processes in progress, which can be found here: Releaseball
- we will walk various products through the draft processes to test our theories
- proposed products:
- Ksplice (S)
- Outlook 2010 (L)
- VPN Client (M)
- Mac OS X 10.6 (L)
- Student Matlab (L)
- CertAid Update (XS)
- Exchange (XL)
- Web Moira (M) if time allows (try a service as opposed to a product)
- proposed products:
- we will capture decision making criteria and role definitions as we go through product walk throughs
- we can research criteria other institutions and companies have used
- Time line
- meet every week for an hour (7/22, 7/27, 8/3, 8/10)
- have final run through of presentation at end of those sessions (8/12)
- present to Marilyn (8/17)
- Reporting on Progress
- Patrick will update Steve Buckley
- Pat will report out to senior staff
- Members can update managers as desired
- Next Steps
- members prep for next weeks meeting on 7/27
- draft processes for extra-small, small and medium releases (current drafts can be found here: Releaseball)
- members can comment directly on the Releaseball wiki
- Steve will research project criteria referenced in #5ci
- Oliver and Pat meet with Steve Gass to discuss sponsorship (8/2)
- members prep for next weeks meeting on 7/27
Our next meeting is scheduled for Tuesday the 27th from 3:30-4:30pm in W92-212 (Aquarium). The proposed agenda is as follows:
1. Walk the following products through the proposed processes
Cert Aid Update (extra-small)
Ksplice (small)
VPN Client (medium)