1.Start Step
- The Start step allows the user, typically the project manager, to enter information about the budget as well as budget line items.
- Also also entered on this screen is information and details for infrastructure funding and alternates.
- On the Submit action the next step is Started by Spawn?.
2. Started by Spawn
- The Started by Spawn? conditional determines if the process was started by spawn (instead of started by a user).
- If the conditional is False the next step is Stage 1?.
- If the conditional is True the next step is PM Enters Stage 1
3. Stage 1?
If this Stage 1 is evaluated False the next step is Program Manager/Planning Manager Review.
If True the next step is PM Enters Stage 1.
4. Stage 1?
If this State 1 is True the next step is PM Enters Stage 1.
If false the next step is Project Manager Enters Budget.
5. PM Enters Stage 1
In this step the PM enters the Stage 1 budget.
If not needed the PM takes the Void Action which voids the process and moves it to Finish.
If a Stage 1 is entered the Submit action is taken. The next step is Program Mgr/Planning Mgr Review
6. Project Manager Enters Budget
- The project manager enters both information about the budget and the Budget Line Items.
- Budget Line Items are are entered by using the Budget Change Items section of the process form. (Because the project manager is editing the template loaded when the project was created)
- When the process form is completed and ready to be reviewed the project manager clicks Submit.
- Next Step: Program Manager Review
- The project manager may also Void the process from this step.
7. Program Manager/Planning Manager Review
- The Program Manager and/or Planning Manager reviews the budget.
- The Program Manager and/or Planning Manager has the option of taking either the Submit or Revise action.
- If Submit is selected the next step is Campus Construction.
- If Revise is selected the next step is Initiator Revise and Resubmit.
8. Initiator Revise and Resubmit
- The process initiator reads the comments and fills out the required fields and has the option to Resubmit or Void.
- If the initiator chooses Resubmit the next step is Program Manager/Planning Mgr Review
- If the initiator chooses Void the next step is Finish
9. Campus Construction Decisional Step
If True Capital Renewal Decisionsl
If False M&U Decisional Decisional is Next
10. M&U Decisional
If True M&U Director Approval
If False OCP Decisional
M&U Director Approval
Submit to Capital Project Decisional
Revise to Initiator Revise 2
OCP Decisional
If True OCP Director Approval
If Revise Initiator Revise 2
Campus Services Decsional
If True Campus Services Director approval
If False IBO Director approval
IBO Director Approval
If Approved the next step is Capital Project
If Revise the next step is Initiator Revise 2
10. Capital Renewal Only
If True CC Director Approval
If False Hold for Team Estimate Review Mtg
11. CC Director Approval
Can revise to Initiator Revise
Submits to Capital Project Decisional
10. Funding Request? (Conditional)
- The funding request step is a conditional that determines if additional funding is needed with the budget request by evaluating the "Does this review include a request for funding" field.
- If True (Yes) the next step is Capital Project? (F)
- If False (No) the next step is Capital Project?
11. Capital Project? (F) (Conditional)
The capital project (F) conditional determines if the Program type equals Capital Group based on the Project Custom Field "Program Type" entry being Capital Group.
- If True the next step is Governance Review
- If False the next step is Provost Review.
12. Capital Project? (Conditional)
- The Capital Project? Conditional determines if the program type equals Capital Group based on the Project Custom Field "Program Type".
- If True the next step is Cost Object Assigned.
- If False the next step is CRSP Admin Distributes
13. CRSP Admin Distributes
- The CRSP Admin reviews the process and distributes to Associate Provost, DLC & School and has the option of sending to RCRSP or Put on Hold.
- If RCRSP is chosen the next step is R-CRSP Committee Review / Approval
- If Put on Hold is chosen the next step is Project on Hold
14. R-CRSP Committee Review Approval
- The CRSP Admin reviews the process, completes the required fields and has the option to Approve, Revise or Reject
- If Approve is selected the next step is Financial Officeer Office Obtain Cost Objects.
- If Revise is selected the next step is CRSP Admin Distributes.
- If Reject is selected the next step is Finish.
15. Governance Review
- The CRSP Admin reviews the process, completes the required fields and has the option to Approve, Put On Hold, or Revise.
- If Approve is selected the next step is Cost Object Assigned?
- If Put On Hold is selected the next step is Project On Hold
- If Revise is selected the next step is Initiator Revise and Resubmit
16. Project On Hold
- The e-B Admin reviews the process, completes the required fields and clicks Submit
- The next step is Governance Review
17. Cost Object Assigned?
- This step determines if a cost object is assigned to the process
- If True (no) the next step is Financial Officer Obtain Cost Object
- If False (yes) the next step is Financial Analyst Imports Data
18. Financial Officer Obtain Cost Object
- The Financial Officer obtains the cost object number, updates the process and takes the Received action.
- The next step is Financial Office Updates PICs and takes the Submit action.
19. Financial Officer Updates PICS
The Financial Officer updates PICS and takes the Submit action.
The next step is Finish.
20. Finish