The General Contract Change Order process combines previously approved Change Order Requests, generated using the 06.01 Letter or Release/ Change Order Request process, into a Contract Change Order for final approval.
    • This process is usually started by the project manager, however it can be started by the contractor.
    • The process routes the GCCO for approval and signature by the appropriate parties based on dollar amount and program.

    Start

    PM Review

    Initiator Revise

    Project Budget Change (Decicional Step)

    $0 Change? (Decisional Step)

    Spawn $0 Budget Change

    Spawn Additional Funding

    Time Only? (Decisional Step)

    Fin. Analyst Holds for Completion

    GC Change Order M.M

    Sum of Attached CORs

    Success? (Decisional Step)

    Commitment Value CO

    Success?

    GC Change Order M.M. (Mail Merge)

    Initiator Resubmit

    PM Review Mail Merge

    Vendor Signature

    Vendor Signature St

    A/E Review Required? (Decisional)

    A/E Signature

    PM Review

    Program Manager Review

    Program Director Review

    <10m? (Decisional Step)

    CC Director Executes

    CC DIrector Signs

    <$100 (Decisional Step)

    Deputy EVPT Review

    EVPT Executes

    CO Signature Finalize

    Compl CORs on Hold

    Success? (Decisional Step)

    eB Admin Resubmit

    35. Finish




    Date Change eB Admin
    4/3/2018 Process updated to enable signaure step for CC Director when value of GCCO is <10 milion. (Workflow v4.1) RB/SA
    4/3/2018 WIKI documention (Step Descriptions and Process map updated) RB
    12/4/2020 Process Map updated. JM