Result or Product of this Process
Limited Scope of Work/ Exhibit A (LSW) process ensures that for all contracts the Limited Statement of Work or Exhibit A is received before work commences.
When this process is completed for a GMP, the Original Commitment amount is changed in the Cost module. The changed amount will be used in the Change Summary section of the GCCO process, when the GCCO process uses the original value of the commitment/contract to provide change details.
- This process is usually initiated internally by the project manager, though it can be initiated by the contractor.
Start
PRJCT Status CHK
PM Fixes Project Status
Initiator Revise
Contract Admin Compiles Documents
Project Manager Review
Program Manager Review
Contract Manager Review
OGC Review
Contracts Send to Vendor for Signature
Contract Admin Hold for Vendor Signature
SPT Director Review
CC Director Execute
CC Director Review
OCP Director Execute
OCP Director Review
Facilities Operations Execute
Facilities Operations Review
Utilities Director Execute
Utilities Director Review
FEG Director Review
Dir of Finance Execute
VP Finance Executes
VP Finance Reviews
EVPT Execute
Amendment e-Signatu
Contract Admin Review / Distribute
SAP Hold Step
Campus Construction?
SPT?
Con>$10m?
OCP?
Con>$500k?
CSM?
ConFO>$10m?
Utilities?
Con>$1m?
FEG?
Con>$1m?
>$10m<+$100m?
Finish