Members will meet monthly or as needed to review outstanding issues / requests for changes to the Daptiv environment.
Change requests must be presented to the Steering Committee by the requestor or sponsor and should be supported by a completed Change Request form.
The Steering Committee will review and discuss each change, identify possible issues and decide on a recommended action. In all cases, any proposed or recommended change will be brought back to the Directors for approval.
Possible recommendations include:
- Approved, pending Director's final approval
- Referred to VP Staff for additional discussion
- Declined
Once a decision has been made to make an adjustment to the Daptiv system or processes around project & portfolio management with regard to Daptiv, the Steering Committee will establish a priority for that adjustment with regard to any currently outstanding adjustments.
Please direct all questions and comments to the IS&T Daptiv Steering Committee or the IS&T Project Services Office.