IS&T Milestones:
- Now - Template Development
- Held up because current release is unworkable per Malc & Harry
- Now - Server Ops
- State: we have one server, to be used as dev server for Content Authoring
- 12/15 - FC Release, install on Dev Server (ISDA-CS1), combines web tier & db tier initially on one machine
- 12/15 - template development begins
- 12/15 - script development for porting begins
- 1/15 - GA Release,
- 1/15 - Information Architecture due from DCAD
- Need to know most frequently accessed pages
- Where users leave IS&T locker for dynamic servers that must be coordinated
- 1/15 - Redesign of ItInfo content/schema (DCAD)
- 1/15 - site re-org scripts begin
- 1/19- GA Installed per arch diagram for dev environment (dev content server, web server, db server, web app server for J2EE components, 4 servers)
- Requires 3 more machines from Server Ops
- Need someone to set up Oracle 10g
- Need focal point for server admin issues
- 2/2 - IS&T Content (AFS Locker) Ported (first pass)
- Scripts convert to new IA
- Pull out basic parts (header, footer) as includes
- 2/9 - 1+ Working Templates with Living Content
- Estimate Grunt Code for porting
- 2/9-3/9 - Workflow Development / Implementation
- 3/9 - New Look and Feel
- Define CSS classes
- 4/15 - Content Freeze
- Templates done
- Basic templates (6-7 at most)
- Scripting done
- Convert IA
- Pull out included elements
- Pull out CSS classes
- Convert to XHTML content
- Workflow done
- Link module ready to use
- Templates done
- 4/28 - Content ported
- 4/30 - CSS begins using/testing
ITInfo Milestones: - 12/15 - FC
- Template Development begins
- Coord w/DCAD re: what parts of schema are likely to be stable
- 1/15 - GA
- 1/15 - new IA, affects schema of ItInfo
- 1/26 - FinalDataPort / Scripts
- 2/9 - Templates Created
- 3/9 - Workflow implemented
- 3/12 - formal testing begins
- 3/16 - Cutover?
Link Management Piece: - GA Dependent
- FC + 2 weeks - Tech Requirements
- GA + 2 weeks -Working Agreement w/Alfresco
- Basic design
- Agreement on components, architecture
- Detailed Dev plan
- ? - Issues / Risks
- 4/15 - Live for final content port