Result or Product of this Process

The 04.01 Bidding process is used for Bid List Approval, Release to Bid and Bid Award Recommendation including these specific steps.

  • Obtain an approved bidder list
  • Prepare and gain approval of the bid package documents including the proposed sample contract
  • Indicate that the bid has been released
  • Recommend an award supported by the bid results/bid tab.
  • Indicate notifications have been made to the bidders
  • Ensure that the awarded bidder is properly set up in e-Builder and SAP

Note that the Bidding process is used to inform and indicate pending or past actions internally about the bid. The Bid module is used to construct and publish the bid to the Bidders portal.

As of October 21, support for Pre-priced agreements has been added to the Bidding process. The process allows the initiator to select a Pre-priced agreement as the contract type, enter information that supports the agreement, forward it for internal approvals and generated the Pre-Priced Selection of Source document.

Process Details

    The Initiator, usually the Project Manager, uses the bidding process and the bidding module to:

    • Compose a list of potential bidders and receive approval on the bidder list (There is an option to bypass Bid List Approval)
    • Prepare the bid documents and assemble the bid package.
    • Release the bid package through the e-Builder Bidder Portal.
    • Answer and respond to questions about the bid from the bidders.
    • Tabulate and analyze the submitted bids.
    • Make an award recommendation.
    • Gain approval of the award recommendation.
    • Award the bid and notify the winning bidder.
    • Notify bidders not selected.

    To make the Step descriptions for Bidding easier to read they have been separated into the three parts (tabs). 

    Start Process

    Furniture or AV Bid? (Conditional)

    Vendor Mgr Reviews Prop Bid List

    Pre-priced Agreement

    Initiator Revise

    Program Manager Review

    Campus Construction? (Conditional)

    SP&T Program? (Conditional)

    SPT Director Review

    CC Director Review

    OCP? (Conditional)

    OCP Director Review

    M&U? (Conditional)

    Utilities Program? (Conditional)

    Utilities Director Review

    SEG Program? (Conditional)

    SEG Director Review

    O&M Director Review

    M&U Director Review

    Campus Services? (Conditional)

    CS Director Review

    IBO Director Review

    Initiator Revise

    Approved Bid List (Automation)

    CA Apprv Contract Type

    Approved Pre-Price Agreement

     

    Pre-Priced SOS Code/Merge Creation

    Bid Document Preparation

    Contract Admin Assembles Bid Package

    Hold for Bids/Proposals Received

    Program Manager Reviews Package

    nitiator Releases Bid

    Vendor Recommendation

    Selection of Source (Automatic Step)

    Vendor Manager Review of SoS

    Program Manager Review

    Initiator Revise Recommendation

    Campus Construction (Decisional Step)

    SP&T Program? (Decisional Step)

    SPT Director Review

    M&U (Decisional Step)

    Utilities Program (Decisional Step)

    Utilities Director Review

    SEG Program

    SEG Director Review

    O&M Director Review

    Vendor Manager Review of SoS

    Campus Construction (Decisional Step)

    CC Director Review

    OCP? (Decisional Step)

    OCP Director Review

    M&U? (Decisional Step)

    M&U Director Review

    Campus Services? (Decisional Field)

    CS Director Review

    IBO Director Review

    Initiator Award Bid

    Vendor Manager Checks Company Info

    Vendor Exists in SAP (Decisional)

    AA Adds New Company

    Finish

     

     