Result or Product of this Process

Limited Scope of Work/ Exhibit A (LSW) process ensures that for all contracts the Limited Statement of Work or Exhibit A is received before work commences.

When this process is completed for a GMP, the Original Commitment amount is changed in the Cost module. The changed amount will be used in the Change Summary section of the GCCO process, when the GCCO process uses the original value of the commitment/contract to provide change details.

    • This process is usually initiated internally by the project manager, though it can be initiated by the contractor.

    Start

    Initiator Revise

    Contract Admin Compiles Documents

    Project Manager Review

    Program Manager Review

    Contract Manager Review

    OGC Review

    Contracts Send to Vendor for Signature

    Contract Admin Hold for Vendor Signature

    SPT Director Review

    CC Director Execute

    CC Director Review

    OCP Director Execute

    OCP Director Review

    CSM Director Execute

    CSM Director Review

    Utilities Director Execute

    Utilities Director Review

    FEG Director Review

    Dir of Finance Execute

    VP Finance Executes

    VP Finance Reviews

    EVPT Execute

    Amendment Signature

    SAP Hold Step

    Campus Construction?

    SPT?

    Con>$10m?

    OCP?

    Con>$500k?

    CSM?

    Con>$10m?

    Utilities?

    Con>$1m?

    FEG?

    Con>$1m?

    >$10m<+$100m?