The proposed timeline for pyxida 6.1 is as follows:
- Make changes to pyxida by the end of this week, as soon as the ECR #8 gets approved.
- Have an internal design review around 8/25 and order the boards right after
- Have the external design review around 9/5 and order new boards if any critical mistake is discovered
- Assemble the first boards to verify they work by mid September
- Put pyxidas on the September launch of NEU
- Assemble the rest of the boards by mid October
- Target the October and November NEU launches.