Preliminary Design Review (a.k.a. DR1)
November 12, 2023
Slides:
Critical Design Review (a.k.a. DR2)
December 10, 2023
This design review was intended to be the final design review for Prometheus but ended up being not as complete as is required for a true Critical Design Review. Propulsion had recently figured out that the propellant characterizations were incorrect and large changes would need to be made. Problems also existed with Payload and Airbrakes especially, and more testing and development would need to be done for all systems before settling on the final design.
Slides:
Recording:
Design Review 3
January 21, 2024
Slides:
Design Review 4
February 18, 2024
This design review was hosted only to review the airbrakes design.
Slides:
Prometheus DR4 (Air Brakes Only).pptx
Recording: