Project sponsor identified?
Key Stakeholders identified/stakeholder analysis completed?
Have features in scope been identified?
Have features 'out of scope' been identified?
Project Steering Committee members identified, if applicable?
Define project goals and objectives
Have project success criteria been identified?
Have risks been identified?
Determine if there any conflicts with existing projects
Are there any compliance issues to be considered?
Are there any audit (internal or external) findings that should be addressed by the project?
Will the existing technical infrastructure support this project?
Has scope statement been written?
Has project approach been determined?
Has project been added to RT queue?
Have resource requests been made to functional managers
Has preliminary budget been reviewed by finance
Has preliminary monthly forecast been submitted to finance
Has preliminary project schedule been developed?
Has project wiki been created?
Have project processes been documented
Have project processes been communicated to the team?
Document risk and escalation procedure
Research-Scope: audit file; requires full file from MITSIS, adds 4-8 weeks to project schedule
Research - Scope: EECS file of new appts (impact to schedule unknown, analysis needed)
Research-Scope:Improvements to Phase I functionality
Schedule: Vacations/time off through next May
# grad admins, # grad students - Leslie
Stakeholders: AAIIC - determine involvement
Stakeholders: Grad Admins; reach out to Angelita Mireles