Sprint 7 release:
1. th-1446: communicate the manage domain changes to the user. Put it in the release notes
2. set up touchstone on the ime servers (isda-thalia5 and 8): please see the touchstone setup instruction in https://wikis-mit-edu.ezproxyberklee.flo.org/confluence/display/ZEST/configuring+touchstone
3. set up group support on the alfresco server (isda-thalia6): please see the group setup in https://wikis-mit-edu.ezproxyberklee.flo.org/confluence/display/ZEST/Thalia+Setup+and+Configuration+%28Simplified%29
4. get rid of all the mod-rewrites rules on 5 and 8
5. check out the website\about directory and put on isda-build1
I will be online that night to assit and verify the release.
Things AMIT needs do a few days before the release:
1. check the server certificate on isda-thalia5 and 8 to make sure that they are enabled for both client and server
2. ask Bob to add the thalia related touchstone configuration to the touchstone production server
Here is a list of current thalia production domains that touchstone has to recognize:
ap.thalia.mit.edu
css.thalia.mit.edu
demo.thalia.mit.edu
edgerton.thalia.mit.edu
energyclub.thalia.mit.edu
helpdesk.thalia.mit.edu
hst.thalia.mit.edu
misti.thalia.mit.edu
music.thalia.mit.edu
nse.thalia.mit.edu
ocw.thalia.mit.edu
psb.thalia.mit.edu
rd.thalia.mit.edu
swrt.thalia.mit.edu
test.thalia.mit.edu