Process Lookup
I want to ... | Use this Process |
---|---|
Initiate a project (Program Managers Only) | 00.00 - Project Initiation (NEWPJ) |
Add a company or contact to e-Builder for the purpose or responding to a bid | 01.01 - Add New Contact to Existing Company (NWCON) |
Add new users (i.e., people who are not currently in e-Builder) to the system with option of assigning them to a project | 01.02 -Add New User Request (NUSER) |
Request that an existing user be added to a project in e-Builder. | 01.03 - Add Existing User to a Project (ADDRE) |
Assign team members to project roles (Project Coordinator, Construction Safety Officer, SEG Lead) | 02.01 - Team Assignment (TA) |
Create a PD (project definition) form (CC Planners) | 02.02 - Project Definition Form Creation (PD) |
Route a CRSP project through an approval system | 02.03 - CRSP Screening Kickoff - CRSPS (with PM Assignment) (CRSPS) |
Create an MOU and Stage 1 Budget (CRSP) | 02.05 - MOU & Stage 1 Budget - CRSP (Non-Cost) (MUS1) |
Prepare a Milestone Project Estimate and Budget Request | 03.01.a - Budget Approval Process (PBAP) |
Adjust a Budget with a 0$ Change | 03.02 - $0 Budget Change (Cost) (ZBCHG) |
Request Contingent Funds/True Up/Request Additional Funding | 03.03 - Contingency Request / True-Up Form / Additional Funding Request (BCHNG) |
Update information about a project | 10.01.a - Project Manager's Project Update (PMUa) |