Result or Product of this Process

The Bidding process allows the Project Manager to manage the bid for the entire bid process including:

  • Bid List approval
  • Release to bid
  • Bid award recommendation.

Process Details

    This process includes Bid List Approval, Release to Bid and Bid Award Recommendation.

    Step descriptions for Bidding have been separated into the three discrete parts below. While Bidding is one process, the supporting documentation is made easier to read by making this division..

    1. Start

    2. Furniture or AV Bid? (Decisional Step)

    3. A133 Been Signed? (Decisional Step)

    4. Vendor Manager Review

    5. Initiator Revise

    6. Program Manager Review

    7. Sole Source? (Decisional Step)

    8. Campus Construction? (Decisional Step)

    9. SP&T Program? (Decisional Step)

    10. SPT Director Review

    11. Projects Director Review

    12. CC Director Review

    13. OCP? (Decisional Step)

    14. OCP Director Review

    15. M&U? (Decisional Step)

    16. Utilities Program? (Decisional Step)

    17. Utilities Director Review

    18. SEG Program? (Decisional Step)

    19. SEG Director Review

    20. O&M Director Review

    21. M&U Director Review

    22. Campus Services? (Decisional Step)

    23. CS Director Review

    24. IBO Director Review

    25. Initiator Revise

    26. VPF Procurement Reviews Bid Package

    27. Approved Bid List (Automatic Step)

    28. Initiator Prepares Bid Documents

    29. Has A133 Been Signed? (Decisional Step)

    30. DoF Procurement Assembles Bid Package

    31. Program Manager Reviews Package

    32. Projects Director Reviews Package

    33. Initiator Releases Bid

    34. Initiator Recommend Vendor

    35. Selection of Source (Automatic Step)

    36. DoF Procurement Reviews Selection

    37. Program Manager Review

    38. Initiator Revise

    39. Campus Construction (Decisional Step)

    40. SP&T Program? (Decisional Step)

    41. SPT Director Review

    42. Projects Director Review

    43. M&U (Decisional Step)

    44. Utilities Program (Decisional Step)

    45. Utilities Director Review

    46. SEG Program

    47. SEG Director Review

    48. O&M Director Review

    49. DoF Procurement Review

    50. A133 Been Signed? (Decisional Step}

    51. >10M (Decisional Step)

    52. One Bid? (Decisional Step)

    53. Lowest Bid? (Decisional Step)

    54. VPF Procurement Review

    55. Campus Construction (Decisional Step)

    56. CC Director Review

    57. OCP? (Decisional Step)

    58. OCP Director Review

    59. M&U? (Decisional Step)

    60. M&U Director Review

    61. Campus Services? (Decisional Field)

    62. CS Director Review

    63. IBO Director Review

    64. Initiator Award Bid

    65. Finish

     

     

     