Result or Product of this Process
This process allows the professional services vendors to request an amendment to their existing approved commitment. The process is used to review and approve the contract amendments provided by the professional services vendors.
This process is started by a professional services vendor for whom separate training will be provided. The information here is for the benefit of internal users who need to work with this process.
1. Start
- The process is started by the Architect Lead who completes the required fields and takes the Submit action.
- The next step is PSA Mail Merge.
2. PSA Mail Merge (System Step)
- The e-Builder system creates a mail merge document using the PSA template and ads it to ...
- The next step is Vendor Signs
3. Vendor Signs
- The vendor reviews the generated mail merge document and has the option to take action to Submit or Revise
- If Submit is chosen the next step is Project Manager Review
- If Revise is chosen the next step is Initiator Revise
4. Project Manager Review
- The Project Manager reviews the process, adds comments if necessary and takes one of the following actions, Submit, Revise or Void
- If Submit is chosen the next step is Financial Analyst Adjusts Funding
- If Revise is chosen the next step is Initiator Revise
- If Void is chosen the next step is Finish,
5. Initiator Revise
- The Project Manager reads the comments and reviews the process fields and updates as necessary, then takes the Resubmit action.
- The next step is Project Manager Review.
6. Additional Funding? (Decisional Step)
- The Additional Funding Required field is evaluated to determine if the value is Yes.
- If the value is Yes (True) then the next step is Spawn Budget Change (03.03).
- If the value is No (False) then the next step is Program Manager Reviews.
7. Program Manager Reviews
- The Program Manager reads the comments, reviews the process fields and has the option to Submit or Revise.
- If Submit is chosen the next step is
- If Revise is chosen the next step is Initiator Revise.
8. Program Type Util? (Decisional Step)
- This is a decisional step that evaluates the Project Type field to determine if this is a Util Program Type.
- If True the next step is Director of Utilities Review.
- If False the next step is Director of Projects Review.
9. Director of Utilities Review
- The Director of Utilities reads the comments and reviews the process fields and has the option to choose between the actions Reviewed and Revise.
- If Reviewed is chosen, the next step is DoF Procurement Review.
- If Revise is chosen the next step is Initiator Revise.
10. Director of Projects Review
- The Director of Projects reads the comments and reviews the process fields and has the option to choose between the actions Reviewed and Revise.
- If Reviewed is chosen, the next step is DoF Procurement Review.
- If Revise is chosen the next step is Initiator Revise.
11. DoF Procurement Review
- The DoF Procurement reads the comments and reviews the process fields and chooses between actions to Submit or Revise.
- If Submit is chosen the next step is Contract > $100M?
- If Revise is chosen the next step is Initiator Revise.
12. Campus Construction? (Decisional Step)
- Multiple process fields are evaluated to determine if this is a Campus Construction project and to determine the next step.
- When True is evaluated the next step is SP&T Program.
- When False is determined the next step is OCP?
13. SP&T Program (Decisional Step)
- Multiple fields are evaluated to determine if this is an SP&T program and to determine the next step.
- When True is evaluated the next step is VPF Strategic Sourcing Review.
- When False is evaluated the next step is Projects Director Review.
14. VPF Strategic Sourcing Review
- The VPF Strategic Sourcing reads the comments, reviews the process fields and has the option to take an action to Submit or Revise.
- If Submit is chosen the next step is Contract < $10M
- If Revise is chosen the next step is Initiator Revise.
15. Projects Director Review
- The Projects Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
- If Submit is chosen the next step is Contract <$10M
- If Revise is chosen the next step is Initiator Revise.
16. Contract <$10M (Decisional Step)
- The date field Project Type is evaluated to determine if it is "Capital Renewal".
- If True the next step is CC Director Executes Contract.
- If False the next step is CC Director Review.
17. CC Director Review
- The CC Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
- If Submit is chosen the next step is Contract < $100M
- If Revise is chosen the next step is Initiator Revise.
18. CC Director Executes
- The CC Director reads the comments and reviews the process and has the option to take an action to Submit or Revise.
- If Submit is chosen the next step is Administrative Assistant Final Review.
- If Revise is chosen the next step is Initiator Revise.