This process allows the Project Manager to change the project budget if funds are needed for non-PO Cost or for PO Only (no contract).
This process is started by the project manager

1. Process Start (Project Manager)
- The Project Manager fills out the required fields and clicks Submit.
- The next step is Return Funds?
2. Return Funds? (Decision Step)
- Return funds is a decision step.
- If funds are being returned to the program the next step is Program Manager Review A
- If funds are not being returned to the program the next step is Program Manager Review B
3. Program Manager Review A
- The Program Manager reviews the process, adds comments if necessary and when finished chooses to Submit or to Revise.
- If Submit is chosen the next step is Financial Analyst Adjusts Funding
- If Revise is chosen the next step is Initiator Revise and Submit.
4. Initiator Revise and Submit
- The Project Manager reads the comments, reviews process fields and updates as necessary and when finished chooses to Resubmit or to Void.
- Resubmit is chosen the next step is Return Funds
- If Void is chosen the next step is Finish
5. Financial Analyst Adjusts Funding
- The Financial Analyst reads the comments, adjusts the funding and then clicks Submit.
- The next step is Finish
6. True Up Form
- Automatic Step to generate the True Up form document
- The next step is Finish
7. Program Manager Review B
- The Program Manager reads the comments, reviews the process fields and chooses to Submit or Revise.
- If Submit is chosen the next step is CC Project?
- If Revise is chosen the next step is PM Reviews Com Initiator Revise and Resubmit
8. CC Project? (Decision Step)
- This is a decision step. e-Builder evaluates the Project Type to determine if the value is "Capital Renewal"
- If True the next step is Project Director Review
- If False the next step is M&U Project?
9. M&U Project? (Decision Step)
- This is a decision step. e-Builder evaluates the Project Type to determine if the value is "Utilities".
- If True the next step is M&U Director Review
- If False the next step is OCP Project?
10. OCP? (Decision Step)
- This step is a decision step. e-Builder evaluates the Project Type to determine if the value is "OCP"
- If True the next step is OCP Director Review
- If False the next step is Director of Housing Review
11. Projects Director Review
- The Projects Director reads the comments and review the process fields and has the option to Submit or Revise.
- If Submit is chosen the next step is CC Director Review
- If Revise is chosen the next step is Initiator Revise and Resubmit
12. CC Director Review
- The CC Director reads the comments and reviews the process fields and clicks Submit.
- The next step is Department Funding?
13. M&U Director Review
- The M&U Director reads the comments and reviews the process fields and clicks Submit.
- The next step is Department Funding?
14. OCP Director Review
- The OCP Director reads the the comments and reviews the process fields and clicks Submit.
- The next step is Department Funding?
15. Director of Housing Review
- The Director of Housing reads the the comments and reviews the process fields and clicks Submit.
- The next step is Department Funding?
16. Department Funding? (Decision Step)
- This is a decision step. e-Builder evaluates the value of the Department Funding field.
- If True the next step is Financial Analyst Adds Funding
- If False the next step is DoF Contingency?
17. DoF Contingency (Decision Step)
- This is a decision step. e-Builder evaluates the value of the Funding Source field.
- If True the next step is Financial Analyst Adds Funding
- If False the next step is EVPT Contingency?
18 EVPT Contingency (Decision Step)
This is a decisional step. e-Builder evaluates the value of the Funding Source field.
- True
- Status of Process: Unchanged
- Next Step: Deputy EVPT Review
- False
- Status of Process: Unchanged
- Next Step: CRSP/R-CRSP Committee Review
Deputy EVPT Review
The EVPT Office reads the comments and reviews the process fields and takes the following action:
Submit
- Status of Process: Unchanged
- Data Field Assignments: N/A
- Next Step: Financial Analyst Adds Funding
Governance Review
The CRSP Admin reads the comments and reviews the process fields and takes the following action:
Approve
- Status of Process: Unchanged
- Next Step: True Up Form / Addi
True Up Form (Automatic Step to Generate Document)
Automatic step to generate the true up form document
- Mail Merge Template: Default Template
- Archive Mail Merge: Yes
- Destination Folder: Documents \ 19 eB Process Documents \ 03.02 Project Budget (Cost)
- Store in File Field: Budget Document
- Send to Process Initiator: No
- Email Format: HTML
- Next Step: Financial Analyst Adds Funding
Financial Analyst Adds Funding
The financial analyst adds the funding to the project and will compete the required process fields and take the below action:
Funds Applied
- Status of Process: Approved
- Data Field Assignments: N/A
- Notify: Process Initiator
- Next Step: Finish
Finish