Result or Product of this Process

Round Rectangle
bgcolor#e6f2ff
width100%

The 04.00 01 Bidding process is used to: for Bid List Approval, Release to Bid and Bid Award Recommendation including these specific steps.

  • Obtain an approved bidder list of bidders
  • Assemble Prepare and gain approval of the bid package
  • Release the bid
  • documents including the proposed sample contract provided by the Contract Admin
  • Secure approval to release the bidTabulate bidder submissions
  • Recommend an award
  • Notify awarded bidder
  • Notify bidders not awarded

The process should be used by the Project Manager for the entire process of Bid List Approval, Release to Bid and Bid Award Recommendation.

Process Details

Composition Setup
 
  • supported by the bid tabulation in the Bidding module.
  • Gain approval to use a pre-priced agreement to award certain types of work to selected vendors.
  • Create the Selection of Source form and have it reviewed and approved by the Vendor Manager
  • Following approval, award the bid.
  • Ensure that the awarded bidder is properly set up in e-Builder and SAP

Note that the Bidding process is used to inform internal actors about the bid and gain approval to proceed through the bidding stages, from Bid List approval to award. The Bid module is used to construct and publish the bid to the Bidders portal and to initiate your Contract and Purchase order request.

Process Details

Deck of Cards
idBid
Card
labelSummary

The Bidding process and the Bidding module are both used to complete a bid and issue an award.

Card
labelProcess Map

Image Added

Deck of Cards
idBid
Card
labelSummary

The Initiator, usually the Project Manager, uses the bidding process and the bidding module to:

  • Compose a list of potential bidders and receive approval on the bidder list (There is an option to bypass Bid List Approval)
  • Prepare the bid documents and assemble the bid package.
  • Release the bid package through the e-Builder Bidder Portal.
  • Answer and respond to questions about the bid from the bidders.
  • Tabulate and analyze the submitted bids.
  • Make an award recommendation.
  • Gain approval of the award recommendation.
  • Award the bid and notify the winning bidder.
  • Notify bidders not selected.
Note

Until all cost processes are released we will not kick off the e-Builder commitment/purchase order process after awarding the bid.

Card
labelProcess Map

Image Removed

Card
labelStep Descriptions

To make the Step descriptions for Bidding easier to read they have been separated into the three parts (tabs). 

Deck of Cards
idSDBid
historyfalse
Card
labelBid List Approval

Toggle Cloak
1. Start Process (Complete Initial Bidding Form)

Cloak
  • The Bidding process is usually started initiated by the Project Manager.
  • Depending on the project the initiator completes the required sections of the page.
  • The OCP Planner, SPT Lead, SPT Commissioning Lead or VPF Strategic Sourcing may also start the process.
  • The initiator fills out the Contract Management, Potential Bidders, and if required the Sole Source sections of the process form. When finished, click the Submit button.
    • Contract Management
    • Pre-Priced Agreement for Office/CR/Lab
    • Sole Source
    • Potential Bidders -
    • When adding potential bidders you should add contact information for each bidder prior to submitting for Vendor Manager review.
  • The next step is Furniture or AV Bid?

Bid list approval is always required except in the following cases involving a general contractor. (GC)

  • GC Bid following pre-construction bidding.
  • Subsequent LSW's or Exhibit A's following the first LSW.

Toggle Cloak
2. Furniture or AV Bid? (Conditional)

    • If that information is not provided the process will be returned to your court for the Initiator Revise step
  • When finished, take the Submit action.
  • The next step is Furniture or AV Bid?

Toggle Cloak
Furniture?

Cloak
  • Based on the process initiator's
Cloak
  • Based on the process initiator's answer to the "Is this a furniture or AV bid?" question the process is routed.
  • If True (Yes) the next step is Initiator Prepares Bid Documents.Doc Preparation
  • If False (No) the next step is Skip Bid List ApprovalAV?

Toggle Cloak
3. Skip Bid List Approval (Conditional)AV?

Cloak
  • Based on the process initiator's answer to the "Skip Bid List ApprovalIs this a furniture or AV bid?" question the process is routed.
  • If True (Yes) the process advances past the Bid List Approval part of the process and goes directly to Initiator Prepares Bid Documents.next step is Vendor Mgr Reviews A/V Bid
  • If False (No) the next step is Vendor Manager Reviews Bid List. Sole Source?

Toggle Cloak
4. Vendor Manager Mgr Reviews A/V Bid List

Cloak
  • The In this step the Vendor Manager reviews the proposed bidder list, completes any required fields, and has the option to take an Action to Submit or Revise. (See shaded area below for specific tasks and instructions)Bid information. The process reaches this step for A/V Bids.
  • If the Submit action is taken If Submit is chosen the next step is Program Manager ReviewReviews.
  • If the Revise action is chosen the taken he next step is Initiator Revise.
    #e6f2ffReview.

Toggle Cloak
Vendor Mgr Reviews Prop Bid List

Cloak
  • The Vendor Manager sees the type of work and estimated cost and uses that information to evaluate the vendors suggested by the PM.
  • The Vendor Manager checks to make sure:

    1. If a Vendor has been selected from the Company Lookup, the PM should have added Contact Name, Phone #, Email.

    2. If a new company is being added, the PM should have added the Company, Contact Name, Phone #, Email.

  • The Vendor Manager is responsible for reviewing the bidder information and updating the Contacts Module in e-Builder based on the information provided in the Potential Bidder List. 

    1. The VM checks to make sure the company and contact information exist in the Contacts Module and is correct.  If information is missing:

      1. The VM clicks on the “Contacts” tab at the top of the screen.

        1. If the Company already exists, add the Contact:

          1. The VM selects the Company.

          2. Clicks on “Add Contact” and copies the Contact information from the VM step into “Contacts”

          3. Clicks “Save”.

        2. If the Company does not already exist:

          1. The VM clicks “Add Company” and adds the Company

            1. From SAP, if available

            2. If not in SAP, more information will be required from the PM

          2. Add the Contact as per 3.a.i. above.

  • The Vendor Manager should add comments, where appropriate in the Vendor Manager Comments text box, or attach relevant documents to the step.

  • To have the PM revise information, the VM should select “Revise”.  To move it forward to the Program Manager, the VM should “Submit”.

  • To upload Companies and/or Contacts:

    1. Click on Contacts tab at the top.

    2. Click on “Import Contacts” (top right, in red line)

    3. Select the “How is your import file organized?”

    4. Choose the file to upload.

Toggle Cloak
5. Initiator Revise

Cloak
  • The initiator reviews the process, adds comments and makes adjustments as necessary. The Action options for the initiator are To Vendor Manager, To Program Manager or Void.
  • If To Vendor Manager is chosen the next step is Vendor Manager Review.
  • If To Program Manager is chosen the next step is Program Manager Review.
  • If Void is chosen the next step is Finish.

Toggle Cloak
6. Program Manager Review

  • reviews the proposed bid list.
  • If approved the Vendor Manager takes the Submit action. The next step is Prepriced Agmt?
  • If the Revise action is taken he next step is Initiator Review.

Toggle Cloak
Prepriced Agmt?

Cloak
  • The system evaluates this conditional to determine if this is a Pre-priced agreement. Using a pre-priced agreement bypasses the process steps which generate an Approved Bid List.
  • If the use of a pre-priced agreement is approved, the work is awarded to a vendor who has previously bid for for work of a certain scope/complexity in order to be considered for that work in the future.
  • If Pre-priced Agreement is True (Yes) the next step is CA Approved Contract Type.
  • If it is False (No) the next step is Program Manager Review.

Toggle Cloak
Sole Source?

Cloak
  • The system evaluates this conditional to determine if this is a Sole Sourced agreement. Using a Sole Sourced agreement bypasses the process steps which generate an Approved Bid List.
  • If the use of a Sole Source agreement is approved, an explanation must be provided.
  • If this conditional evaluates to True (Yes) the next step is Vendor Reccomendation.
  • If this conditional evaluates to False (No) the next step is Vendor Mgr Reviews Prop Bid List.

Toggle Cloak
Initiator Revise

Cloak
  • Initiator Revise is used to request that the initiator correct an error or add more information to a prior step.
  • The Initiator reviews the process and the comments made by the reviewer and makes adjustments as required. The Action options for the initiator are To Vendor Manager, To Program Manager or Void.
  • If To Vendor Manager is chosen the next step is Vendor Mgr Reviews Prop Bid List.
  • If To Program Manager is chosen the next step is Program Manager Review.
  • If Void is chosen the next step is Finish.

Toggle Cloak
Program Manager Reviews

Cloak
  • The Program Manager reads the comments and reviews the process fields and has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is Campus Construction?
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
Campus Construction?

Cloak
  • e-Builder uses information previously entered about the project to determine if this is a Campus Construction project.
  • If Yes the next step is SP&T Program?
  • If No the next step is OCP?

Toggle Cloak
SP&T Program?

Cloak
  • e-Builder uses information previously entered about the project to determine if this is an SP&T Program.
  • If True (Yes) the next step is SPT Director Review.
  • If False (No) the next step is CC Director Review.

Toggle Cloak
SPT Director Review

Cloak
  • The SPT Director reads the comments and reviews the process fields and has the option to take an action
Cloak
  • The Program Manager reads the comments and reviews the process fields and has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is Campus Construction? CC Director Review.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
7. Campus Construction? (Conditional)

Cloak
  • e-Builder uses information previously entered about the project to determine if this is a Campus Construction project.
  • If Yes the next step is SP&T Program?
  • If No the next step is OCP?

CC Director Review

Cloak
  • The CC Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
OCP?
Toggle Cloak
8. SP&T Program? (Conditional)

Cloak
  • e-Builder uses evaluates information previously entered about the project to determine if this is an SP&T OCP Program.
  • If True (Yes) the next step is SPT OCP Director Review.
  • If False (No) the next step is CC Director Review. M&U?

Toggle Cloak
9. SPT OCP Director Review

Cloak
  • The SPT OCP Director reads the comments and reviews the process fields and . The OCP Director has the option to take an action to an Action to Submit or Revise.
  • If Submit is chosen the next step is CC Director Review. Approved Bid List
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
10. CC Director ReviewM&U?

Cloak
  • e-Builder evaluates information previously entered about the project to determine if this is an M&U program?
  • If Yes the next step is Utilities Program?
  • If No the next step is Campus Services?
  • The CC Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
11. OCP? (Conditional)Utilities Program?

Cloak
  • e-Builder evaluates information previously entered about the project to determine if this is an OCP a Utilities Program.
  • If True (Yes) the next step is OCP Utilities Director Review.
  • If False (No) the next step is M&USEG Program?

Toggle Cloak
12. OCP Utilities Director Review

Cloak
  • The OCP Utilities Director reads the comments and reviews the process fields. The OCP Utilities Director has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List
  • an Action to Submit or Revise.
  • If Submit If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
13. M&U? (Conditional)

  • M&U Director Review.
  • If Revise is chosen the next step is Initiator Revise.
Cloak
  • e-Builder evaluates information previously entered about the project to determine if this is an M&U program?
  • If Yes the next step is Utilities Program?
  • If No the next step is Campus Services?

Toggle Cloak
14. Utilities SEG Program? (Conditional)

Cloak
  • e-Builder evaluates information previously entered about the project to project  to determine if this is a Utilities an SEG Program.
  • If True (Yes) the next step is Utilities SEG Director Review.
  • If False (No) the next step is SEG Program O&M Director Review?

Toggle Cloak
15. Utilities SEG Director Review

Cloak
  • The Utilities SEG Director reads the comments and reviews the process fields. The Utilities SEG Director has the option to take an Action to  Submit or Revise.
  • If Submit is chosen the next step is M&U Director Review.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
16. SEG Program? (Conditional)

Cloak
  • e-Builder evaluates information previously entered about the project  to determine if this is an SEG Program.
  • If True (Yes) the next step is SEG Director Review.
  • If False (No) the next step is O&M Director Review?

Toggle Cloak
17. SEG Director Review

O&M Director Review

Cloak
  • The O&M Director reads the comments and reviews the process fields. The O&M Director has the option to Submit or Revise.
  • If Submit is chosen the next step is M&U Director Review.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
M&U Director Review

Cloak
  • The M&U
Cloak
  • The SEG Director reads the comments and reviews the process fields. The SEG The M&U Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
Campus Services?

Cloak
  • e-Builder evaluates information previously entered about the project to determine if this is an Campus Services Program.
  • If Submit is chosen True (Yes) the next step is M&U CS Director Review.
  • If Revise is chosen False (No) the next step is Initiator Revise. IBO Director Review

Toggle Cloak
18. O&M Director CS Director Review

Cloak
  • The O&M CS Director reads the comments and reviews the process fields. The O&M CS Director has the option to Submit or Revise.
  • If Submit is chosen the next step is M&U Director Review. Approved Bid List
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
19. M&U IBO Director Review

Cloak
  • The M&U The IBO Director reads the comments and reviews the process fields. The M&U The IBO Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
20. Campus Services? (Conditional)Initiator Revise

Cloak
  • e-Builder evaluates information previously entered about the project to determine if this is an Campus Services Program.
  • If True (Yes) the next step is CS Director Review.
  • If False (No) the next step is IBO Director Review

Toggle Cloak
21. CS Director Review

Cloak
  • The CS Director reads the comments and reviews the process fields. The CS Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
22. IBO Director Review

Cloak
  • The IBO Director reads the comments and reviews the process fields. The IBO Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
23. Initiator Revise

Cloak
  • The initiator revises the process and adds comments if necessary. The initiator Submits when finished with revisions.
  • The next step is Sole Source?

Toggle Cloak
24. Approved Bid List (Automation)

Cloak
  • This step generates the Approved Bid List document from a template
  • The bid list document is placed into the Documents\05 Procurement\0505 Bid Lists (I) folder
  • The next step is Initiator Prepares Bid Documents.
  • The initiator revises the process and adds comments if necessary. The initiator Submits when finished with revisions.
  • If the Submit action is taken the next step is Sole Source?
  • If Void is chosen the next step is Finish.

Toggle Cloak
Approved Bid List

Cloak
  • This step generates the Approved Bid List document from a template
  • The bid list document is placed into the Documents\05 Procurement\0505 Bid Lists (I) folder
  • The next step is CA Apprv Contract Type.
Card
labelDocuments, Contract Approval, Release Bid

Toggle Cloak
CA Apprv Contract Type

Cloak
  • The Contract Admin either approves or changes the contract type or approves the Pre-priced agreement and adds the contract number for that agreement to the process.
  • The Contract Admin takes the Approved action to approve. The next step is Approved Pre-Price.
  • The Contract Admin takes the Changed action when changing the contract type, and adds comments to indicate to the PM that the contract has been changed and the reasons for the change.
  • The next step is Bid Doc Preparation.

Toggle Cloak
Approved Pre-Price Agreement

Cloak
  • This is a conditional step. If True (a Pre-priced agreement) the next step is the Merge/Code step that creates the Selection of Source form document.
  • If False the next step is Bid Document Preparation.

Toggle Cloak
PrePriced SoS

Cloak
  • e-Builder generates the Selection of Source for Pre-priced agreements.
  • The next step is Vendor Manager Review of SoS.

Toggle Cloak
Bid Document Preparation

Cloak
  • The process initiator, usually the Project Manager, prepares/uploads the bid documents and completes the required fields. The Submit action is taken when finished.
  • The next step is Contract Admin Assembles Bid Package

Toggle Cloak
Contract Admin Assembles Bid Package

Cloak
  • The Contract Admin assembles the bid package and when finished takes the Submit action.
  • As part of this process the Contract Admin adds a contract sample and assigns a contract number.

  • The next step is Hold for Bids/Proposals Received.

Toggle Cloak
Hold for Bids/Proposals Received

Cloak

The bid should be released in the Bid module when the process reaches this step.

  • Hold the process in this step from bid release until all bids are received and the bid tab has been opened and analyzed. This may be held for one to several weeks while the bid is open.
  • Once the bids have been analyzed and a vendor recommendation is ready the Project Manager takes the Submit action.
  • The next step is Vendor Recommendation.
Bid Award Recommendation
Card
labelBid Award Recommendation

Toggle Cloak
Vendor Recommendation

Cloak
  • The Project Manager, having received all the bids and supporting documents, performs the analysis and selects a vendor.
  • The process step form is completed and the Submit action is taken.
  • The next step is Selection of Source.

Toggle Cloak
Selection of Source

Cloak
  • This is an automatic step to generate the Selection of Source document. The Selection of Source template is applied.
  • The next step is Vendor Manager Review of SoS.

Toggle Cloak
Vendor Manager Review of SoS

Cloak
  • The Vendor Manager reviews the selection and has the option to take the Action to Submit or Revise
Card
labelRelease to Bid

Toggle Cloak
25. Initiator Prepares Bid Documents

Cloak
  • The process initiator, usually the Project Manager, prepares/uploads the bid documents and completes the required fields. The Submit Action is taken when finished.
  • The next step is GC Previously Approved?

Toggle Cloak
26. GC Previously Approved? (Decisional Step)

Cloak
  • e-Builder determines, based on information previously entered, if the GC has already been approved.
  • If True (Yes) the next step is Program Manager Reviews Package.
  • If False (No) the next step is Assemble Bid Package.

Toggle Cloak
27. Assemble Bid Package

Cloak
  • The Contract Admin reads the comments and reviews the process fields. The Contract Admin has the option to take an Action to Submit or Revise
  • If Submit is chosen the next step is Program Manager Reviews Package
  • If Revise is chosen the next step is Initiator Prepares Bid Documents

Toggle Cloak
28. Program Manager Reviews Package

Cloak
  • The Program Manager reads the comments and reviews the process fields. The program manager has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is Initiator Releases Bid. Program Manager Review
  • If Revise is chosen the next step is Initiator Prepares Bid Documents.

Toggle Cloak
29. Initiator Releases Bid

Cloak
  • The initiator (usually the Project Manager) works within the Bidding module to complete the steps that enable the Bidding portal for the bid package.
  • Once the bid has been released the Initiator completes the required process fields, takes the Submit Action.
  • The next step is Initiator Recommend Vendor.
Card
  • Vendor Recommendation.

Toggle Cloak
Program Manager Review

Cloak
  • The Program Manager reads the comments and reviews the process fields. The program manager has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is Campus Construction.
  • If Revise is chosen the next step is Initiator Revise Recommendation.
label

Toggle Cloak
30. Initiator Recommend VendorRevise Recommendation

Cloak
  • The initiator receives all the bid documents, reviews them, and selects a vendor for recommendation. All project managers on the project receive a notification when this step is reached. They will fill out the required fields and Submit. Initiator reviews the process and adds comments and makes adjustments as necessary. The initiator has the option to Submit or Void.
  • If Submit is chosen the The next step is Selection of Source.

Toggle Cloak
31. Selection of Source (Automatic Step)

Cloak
  • This is an automatic step to generate the Selection of Source document. The Selection of Source template is applied.
  • The next step is Vendor Manager Review of SoSIf Void is chosen the next step is Finish.

Toggle Cloak
32. Vendor Manager Review of SoS
Campus Construction?

Cloak
  • e-Builder uses information previously entered to to determine "ownership" of the program.
  • If True (Yes)
Cloak
  • The Vendor Manager reviews the selection and has the option to take the Action to Submit or Revise
  • If Submit is chosen the next step is SP&T Program Manager Review.
  • If Revise is chosen False (No) the next step is Initiator Recommend Vendor M&U.

Toggle Cloak
33. Program Manager ReviewSP&T Program?

Cloak
  • The Program Manager reads the comments and reviews the process fields. The program manager has the option to take an Action to Submit or Revise."Contract managed by a different program" field is evaluated.
  • If True (Yes) If Submit is chosen the next step is Campus Construction SPT Director Review.
  • If Revise is chosen False (No) the next step is Initiator Revise.is Vendor Manager Review of SoS

Toggle Cloak
34. Initiator ReviseSPT Director Review

Cloak
  • The Initiator SPT Director reads the comments and reviews the process and adds comments and makes adjustments as necessaryfields. The initiator SPT Director has the option to Submit or Void Revise.
  • If Submit is chosen the next step is Selection Vendor Manager Review of SourceSoS.
  • If Void Revise is chosen the next step is Finish Initiator Revise.

Toggle Cloak
35. Campus Construction (Decisional Step)M&U2?

Cloak
  • e-Builder uses information previously entered to to determine "ownership" of the program.
  • If True (Yes) the next step is SP&T Utilities Program.?
  • If False (No) the next step is M&U. Campus Services?

Toggle Cloak
36. SP&T Utilities Program? (Decisional Step)

Cloak
  • The "Contract managed by a different program" field is evaluatede-Builder uses information previously entered to determine "ownership" of the program.
  • If True (Yes) the next step is SPT Utilities Director Review.
  • If False (No) the next step is Vendor Manager Review of SoSSEG Program?.

Toggle Cloak
37. SPT Utilities Director Review Rec

Cloak
  • The SPT Director utilities director reads the comments and reviews the process fields. The SPT Director utilities director has the option to Submit or Revise.
    If Submit is chosen the next step is Vendor Manager Review of SoS.If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
38. M&U (Decisional Step)

  • M&U Director Review Rec.
  • If Revise is chosen the next step is Initiator Revise Recommendation
Cloak
  • e-Builder uses information previously entered to determine "ownership" of the program.
  • If True (Yes) the next step is Utilities Program?
  • If False the next step is Vendor Manager Review of SoS.

Toggle Cloak
39. Utilities Program (Decisional Step)SEG Program?

Cloak
  • e-Builder uses information previously entered to determine "ownership" of the programif this is an SEG Program.
  • If True (Yes) the next nest step is Utilities SEG Director Review .Rec
  • If False (No) the next step is SEG Program?. O&M Director Review Rec

Toggle Cloak
40. Utilities SEG Director Review Rec

Cloak
  • The utilities director SEG Director reads the comments and reviews the process fields. The utilities director SEG Director has the option option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is Vendor Manager Review of SoS.
  • If Revise is chosen the next step is Initiator ReviewRevise Recommendation.

Toggle Cloak
41. SEG ProgramO&M Director Review Rec

Cloak
  • The O&M Director reads the comments and reviews the process fields. DoF Procurement has the option to Submit or Revise.
  • If Submit is chosen the next step is Vendor Manager Review of SoS.
  • If Revise is chosen the next step is Initiator Revise Recommendation
Cloak
  • e-Builder uses information previously entered to determine if this is an SEG Program.
  • If True (Yes) the nest step is SEG Director Review
  • If False (No) the next step is O&M Director Review.

Toggle Cloak
42. SEG CC Director Review

Cloak
  • The SEG CC Director reads the comments and reviews the process fields. The SEG CC Director has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is Vendor Manager Review of SoS Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise Recommendation.

Toggle Cloak
43. O&M Director ReviewOCP?

Cloak
  • Multiple fields are evaluated to determine if this is an OCP Program.
  • If True (Yes) the next step is OCP Director Review.
  • If False (No) the next step is M&U?
Cloak

 

  • The O&M Director reads the comments and reviews the process fields. DoF Procurement has the option to Submit or Revise.
  • If Submit is chosen the next step is Vendor Manager Review of SoS.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
44. Vendor Manager Review of SoSOCP Director Review

Cloak
  • Vendor Manager The OCP Director reads the comments and reviews the process fields. Vendor Manager OCP Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Campus Construction.If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
45. Campus Construction (Decisional Step)

  • Awards Bid.
  • If Revise is chosen
Cloak
  • Multiple fields are evaluated to determine if this is a Campus Construction program.
  • If True (Yes) the next step is CC Director Review.
  • If False (No) the next step is OCP? Initiator Revise Recommendation.

Toggle Cloak
46. CC M&U Director Review Rec

Cloak
  • The CC M&U Director reads the comments and reviews the process fields . CC Director and has the option to Submit or Revise.
  • If Submit is chosen the next step is Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise Recommendation.

Toggle Cloak
47. OCP? (Decisional Step)Campus Services?

Cloak
  • Multiple fields are evaluated to determine if this is an OCP Program.Campus Services program?
  • If True (Yes) the next step is OCP CS Director Review.
  • If False (No) the next step is M&U? IBO Director Review.

Toggle Cloak
48. OCP CS Director Review

Cloak
  • The OCP The Campus Services Director reads the comments and reviews the process fields. OCP The CC Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
49
  • .
M&U? (Decisional Step)
Cloak
  • Multiple fields are evaluated to determine if this is an M&U program
  • If True (Yes) the next step is M&U Director Review
  • If False (No) the next step is Campus Services?

Toggle Cloak
50. M&U IBO Director Review

Cloak
  • The M&U IBO Director reads the comments and reviews the process fields and . The IBO Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
Initiator Award Bid

Cloak
  • The Initiator reviews the process and awards the bid using the e-Builder Bidding module. The final action when the bid is awarded is to return to the process and take the Submit Action.
  • The next step is Vendor Manager Checks Company Info.If Revise is chosen the next step is Initiator Revise

Toggle Cloak
51. Campus Services? (Decisional Field)Pre-Priced 3?

Cloak
  • Multiple fields are evaluated to determine if this is an Campus Services program?This conditional determines if this process contains a Pre-priced agreement.
  • If True (Yes) the next step is CS Director Review the process moves to Finish.
  • If False (No) the next step is IBO Director Review. the process moves to Vendor Manager Checks Company Info

Toggle Cloak
52. CS Director Review

Cloak
  • The Campus Services Director reads the comments and reviews the process fields. The CC Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
53. IBO Director Review

Cloak

The IBO Director reads the comments and reviews the process fields. The IBO Director has the option to Submit or Revise.

  • If Submit is chosen the next step is Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
54. Initiator Award Bid

Cloak
  • The Initiator reviews the process and awards the bid using the e-Builder Bidding module. The final action when the bid is awarded is to return to the process and take the Submit Action.
  • The next step is Finish.

64. Finish

Card
idPFI
labelProcess Form Instructions

Vendor Mgr Checks Company Info

Cloak
  • The Vendor Managerchecks and fills out form fields to ensure that:
    • The awarded bidder exists in SAP
    • The company information is correct and current in the Contacts module.
    • If the company is not in SAP that the New Company process has been started.
  • When finished the Vendor Manager takes the Submit action.
  • The next step is Vendor Exists in SAP?

Toggle Cloak
Vendor Exists in SAP?

Cloak
  • This step routes the process to the Finish step if the Vendor exists in SAP.
  • If the Vendor does not exist in SAP the next step is AA Adds New Company.

Toggle Cloak
AA Adds New Company

Cloak
  • If the company does not exist in SAP the AA completes the 01.01 Add New Company/Contact process and holds the process in this step until that has been completed.
  • When completed the AA takes the Vendor Added action.
  • The next step is Vendor Manager Checks Company Info.

Toggle Cloak
Hold for SAP Vendor #

Cloak
  • In this step the Administrative Assistant waits until the Vendor has been assigned a SAP Vendor Number from VPF.
  • If the Submit action is taken the next step is Finish.
  • If the Revise action is taken the next step is AA Adds New Company.

Toggle Cloak
Finish

Cloak

Contract Management

Image Removed

Potential Bidders

Use the Lookup link to display a menu that allows potential bidders to be added.

Image Removed

Sole Source

Indicate if this is a Sole Source procurement. If it is Sole Source, provide a reason.

Image Removed