Result or Product of this Process
Round Rectangle |
---|
|
Use this process to request approval for Budget Requests.project budget(s). (Budget = Funded Amount) |
Deck of Cards |
---|
|
Card |
---|
| This process replaces the 3.01 Milestone Project Estimate and Budget request process and the budget template/Excel spreadsheet. All projects will now have a Projects now have an appropriate budget template added when the project is created. Users will run the 03.01a Project Budget RequestApproval process to create the project budget . All work is done within the process, no external document is required. Once the budget is created the process is routed for approval depending on project type. and gain approvals. This process also results in the assignment of a cost object to the project. | Card |
---|
| Note |
---|
This version of the process includes steps, early in the workflow, to ensure that 0's and negative numbers are properly handled to comply with integration requirements. |
Image Removed |
Card |
---|
label | PM Instructions - Creating a BudgetWorkflow |
---|
| Image Added
|
Card |
---|
| 1. Initiation by Project ManagerStart Step Cloak |
---|
- The Start step allows the user, typically the project manager, to enter information about the budget as well as budget line items.
- Also also entered on this screen is information and details for infrastructure funding and alternates.
- On the Submit action the next step is Started by Spawn?.
| eB Admin Process Cloak |
---|
This step is only for use by eB Admins to add to the budget to cover admin costs for CRSP projects Based on how the process is started a conditional is evaluated to determine if the project manager needs to complete their fields. |
2. Started by Spawn (Decisional Step) Cloak |
---|
- The Started by Spawn? conditional determines if the process was spawnedstarted by spawn (instead of started by a user).
- If the conditional is True False the next step is Project Manager Submit EstimateStage 1?.
- If the conditional is True the next step is PM Enters Stage 1
| Stage 1? (Decisional Step) Cloak |
---|
If this Stage 1 is evaluated False the next step is Program Manager/Planning Manager Review. If True the next step is PM Enters Stage 1. | 3. Project Manager EstimateStage 1? (Decisional Step) Cloak |
---|
If this State 1 is True the next step is PM Enters Stage 1. If false the next step is Project Manager Enters Budget. | PM Enters Stage 1 Cloak |
---|
In this step the PM enters the Stage 1 budget. If not needed the PM takes the Void Action which voids the process and moves it to Finish. If a Stage 1 is entered the Submit action is taken. The next step is Program Mgr/Planning Mgr Review | Project Manager Enters Budget Cloak |
---|
- The project manager enters both information about the budget and the Budget Line Items.
- Budget Line Items are are entered by using the Budget Change Items section of the process form. (Because the project manager is editing the template loaded when the project was created)
- When the process
| Cloak |
---|
- The project manager navigates to the Estimate Worksheet, clicks Edit, completes the spreadsheet, and then checks the edited spreadsheet back into e-Builder.
- The project manager attaches the newly edited spreadsheet to the process, completes the form by selecting from the Create Budget Type and Estimate Type dropdown menus and by indicating that the project schedule has been updated if necessary and also indicates if the review includes a funding request.
- Once the form is completed and ready to be reviewed the project manager clicks Submit.
- Next Step: Program Manager Review
- The project manager may also Void the process from this step.
| 4. Program Manager/Planning Manager Review Cloak |
---|
- The P rogram Program Manager and/or Planning Manager reviews the process and adds comments if necessary. The program manager can download the estimate worksheet, make changes and then upload. This will result in a separate document from the one submitted by the PM.budget.
- The Program Manager and/or Planning Manager The program manager has the option of taking either submitting or asking for revisionsthe Submit or Revise action.
- If the program manager clicksSubmita series of decisions is evaluated to determine routing to one of the CC Director and Director of Projects, M&U Director, OCP Director, Campus Services Director or IBO Director. is selected the next step is Campus Construction.
- If Revise is selected If the program manager clicks Revise the next step is Initiator Revise and Resubmit.
| 5. Initiator Revise and Resubmit Cloak |
---|
- The process initiator reads the comments and fills out the required fields and has the option to Resubmit or Void.
- If the initiator chooses Resubmit the next step is Program Manager/Planning Mgr Review
- If the initiator chooses Void the next step is Finish
| Campus Construction? (Decisional Step) Cloak |
---|
If True the next step is Capital Renewal? If False the nest step is M&U? | 6. CC Director and Director of Projects or M&U? (Decisional Step) Cloak |
---|
If True the next step is M&U Director | or OCP Director or Campus Services Director or IBO Director ReviewApproval. If False the next step is OCP?. | M&U Director Approval Cloak |
---|
The M&U Director reviews the budget and has the option to Submit or Revise. |
Cloak |
---|
One of the above reviews the process and takes an action to Submit or to Revise If Submit is chosen the next step is Capital Project? If Revise is taken the nest step is Initiator Revise 2 | OCP? (Decisional Step) Cloak |
---|
If True the next step is OCP Director Approval. If Revise is selected the next step is Initiator Revise 2. | Campus Services (Decisional Step) Cloak |
---|
If True the next step is Campus Services Director Approval. If False the next step is IBO Director Approval. | IBO Director Approval Cloak |
---|
The IBO Director reviews the budget and has the option to Approve or Revise. If Approved is chosen the next step is Capital Project? process passes through several decision steps to determine if it contains a funding request and if it is a capital or academic projectIf the process is determined to be for a capital project the next step is Governance Review.If the process is determined to be for an academic project the next step is CRSP Admin DistributesIf the process is determined not to be for Capital or Academic the next step is R-CRSP Committee Review/Approval.If Revise is chosen the next step is Initiator Revise and Resubmit2. | 7. Funding RequestCapital Renewal Only? (ConditionalDecisional Step) Cloak |
---|
- The funding request step is a conditional that determines if additional funding is needed with the budget request by evaluating the "Does this review include a request for funding" field.
- If True (Yes) the next step is Capital Project? (F)
- If False (No) the next step is Capital Project?
|
8. Capital Project? (F) (Conditional) If True the next step is CC Director Approval. If False the next step is Hold for Team Estimate Review Mtg | Hold for Team Estimate Review Mtg Cloak |
---|
This is a hold step until the the Team Estimate Review meeting is held. After the meeting the budget can be submitted for CC Director Approval or sent for revision. (Initiator Revise 2) | CC Director Approval Cloak |
---|
The CC Director reviews and takes either the Submit or Initiator Revise action. If Submit the next step is Capital Project? If Revise the next step is Initiator Revise and Resubmit | Cloak |
---|
The capital project (F) conditional determines if the Program type equals Capital Group based on the Project Custom Field "Program Type" entry being Capital Group. If True the next step is Governance ReviewIf False the next step is Provost Review. | 9. Capital Project? (Conditional) Cloak |
---|
- The Capital Project? Conditional determines if the program type equals Capital Group based on the Project Custom Field "Program Type".
- If True Yes the next step is Cost Object AssignedCapital Project Approval.
- If False the next step is CRSP Admin Distributes
| 10. CRSP Admin Distributes Cloak |
---|
- The CRSP Admin reviews the process and distributes to Associate Provost, DLC & School and has the option of sending to RCRSP or Put on Hold.
- If RCRSP is chosen the next step is R-CRSP Committee Review / Approval
- If Put on Hold is chosen the next step is Project on Hold
| 11. R-CRSP Committee Review Approval- DLC Distribution/RCRSP Approval
| Capital Project Approval Cloak |
---|
- There are three actions from this step.
- If Approve is chosen the next step is Cost Object Assigned
| Cloak |
---|
- The CRSP Admin reviews the process, completes the required fields and has the option to Approve, Revise or Reject
- If Approve is selected the next step is Financial Officeer Office Obtain Cost Objects.
- If Revise is selected chosen the next step is CRSP Admin DistributesInitiator Revise and Resubmit.
- If Reject Put on Hold is selected chosen the next step is Finish. Project on Hold
| 12. Governance ReviewDLC Distribution/RCRSP Approval Cloak |
---|
The CC Planning Manager and or CRSP Admin reviews the process, completes the required fields and has the option to Approve, Put On Hold, or Revise. take one of the following actions from this step: If Approve is selected chosen the next step is Cost Object Assigned? If Put On Hold Reject is selected chosen the next step is Project On HoldIf Revise is selected the next step is Initiator Revise and Resubmit Initiator Revise 2. | 13. Project On Hold Cloak |
---|
- The e-B CRSP Admin reviews the process, completes the required fields and clicks Submit
- The next step is Governance Review Capital Project Approval
| 14. Cost Object Assigned? (Decisional Step) Cloak |
---|
- This step determines if a cost object is assigned to the process
- If True (no) the next step is Financial Officer Obtain Cost Object
- If False (yes) the next step is Financial Analyst Imports Data
| 15. Financial Officer Obtain Cost Object Cloak |
---|
- The Financial Officer obtains the cost object number, updates the process and takes the Receive Received action.
- The next step is Finish Financial Office Updates PICs and takes the Submit action.
| 16. Financial Analyst Imports DataFinancial Officer Updates PICS Cloak |
---|
The Financial Analyst imports data, applies funding (as needed) and clicks SubmitOfficer updates PICS and takes the Submit action. The next step is Finish. |
Finish 17. Finish |
|
...
Card |
---|
label | PM Instructions - Using the Budget Template |
---|
| Create your budget by: - Fill out all required fields.
- Click on the Add All Line Items button. This loads the budget template. Only the first few lines of the template are shown in the example below. The full template when loaded is 168 lines.
- In the Change Amount column, click on the Pencil icon and edit the amount for each line you wish to use in the template.
Image Added
|
Card |
---|
| An RCA form can be printed. To print the form: - Open the 3.01 Budget Approval Process.
- Click the Print button. The Mail Merge Templates menu appears.
- Click the Merge Templates radio button.
- Choose RCA Form from the drop down menu.
- Click Print on the Mail Merge Templates menu.
- A document is created and may be opened. The exact way in which the document is displayed and opened is browser dependent.
Frequently Asked Questions and Solutions - How can I add notes to the budget detail lines?
Answer: The Notes column for each Budget Detail line can be populated using Word. Add notes for any budget line you wish to annotate. You may attach an edited version of the Word document with notes to the process for future reference. - Why is there an error message in the square footage line?
Answer: The square footage was not entered into e-Builder, or was entered in the incorrect field. - How can I remove the 0 lines in the printed form.
Answer: The budget detail is printed in a Word table. You may delete the 0 line rows from the table in Word. - The Scope Description and Design Pricing basis are blank.
Answer: If those lines are blank edit them in Word. - My form has a DRAFT watermark on it? Can I remove it?
Answer: The DRAFT watermark will be printed when the process is saved as a draft. Move the process through the workflow steps and the Draft watermark will not be appear..
|
Card |
---|
label | Financial Officer Instructions |
---|
| The Financial Officer performs three actions in this process: - Obtain a Cost Object and add it to e-Builder.
- Manually copy budget information from the PBAP process to PICS.
- Take the Submit action that establishes or updates the budget in e-Builder.
|
|