Result or Product of this Process

Round Rectangle
bgcolor#e6f2ff
width100%

The 04.00 01 Bidding process produces:

  • An Approved Bidder List
  • The Bid Package containing Bid Documents
  • A released bid
  • Tabulation of bidder submissions
  • An approved award recommendation
  • An Awarded Bidder who has been notified of the Award
  • Bidders notified that they have not been selected for the Award

The process should be used by the Project Manager for the entire process of Bid List Approval, Release to Bid and Bid Award Recommendation.

Process Details

Composition Setup
 

is used for Bid List Approval, Release to Bid and Bid Award Recommendation including these specific steps.

  • Obtain an approved list of bidders
  • Prepare and gain approval of the bid package documents including the proposed sample contract provided by the Contract Admin
  • Secure approval to release the bid
  • Recommend an award supported by the bid tabulation in the Bidding module.
  • Gain approval to use a pre-priced agreement to award certain types of work to selected vendors.
  • Create the Selection of Source form and have it reviewed and approved by the Vendor Manager
  • Following approval, award the bid.
  • Ensure that the awarded bidder is properly set up in e-Builder and SAP

Note that the Bidding process is used to inform internal actors about the bid and gain approval to proceed through the bidding stages, from Bid List approval to award. The Bid module is used to construct and publish the bid to the Bidders portal and to initiate your Contract and Purchase order request.

Process Details

Deck of Cards
idBid
Card
labelSummary

The Bidding process and the Bidding module are both used to complete a bid and issue an award

Deck of Cards
idBid
Until all cost processes are released we will not kick off the commitment/purchase order process after awarding the bid

.

Card
labelSummary

The Project Manager uses the bidding process and the bidding module to:

  • Compose a list of potential bidders and receive approval on the bidder list (There is an option to bypass Bid List Approval)
  • Prepare the bid documents and assemble the bid package.
  • Release the bid package through the e-Builder Bidder Portal.
  • Answer and respond to questions about the bid from the bidders.
  • Tabulate and analyze the submitted bids.
  • Make an award recommendation.
  • Gain approval of the award recommendation.
  • Award the bid and notify the winning bidder.
  • Notify bidders not selected.
Note
Card
labelProcess Map

This workflow displays in two images.

 

Image Removed

 

Image RemovedImage Added

Card
labelStep Descriptions

To make the Step descriptions for Bidding easier to read they have been separated into the three discrete parts below. While Bidding is one process, the supporting documentation is made easier to read by making this division..(tabs). 

Deck of Cards
idSDBid
historyfalse
Release to Bid
Card
labelBid List Approval

Toggle Cloak
1. Start Process (Complete Initial Bidding Form)

Cloak
  • The Bidding process is usually started initiated by the Project Manager.
  • The OCP Planner, SPT Lead, SPT Commissioning Lead or VPF Strategic Sourcing may also start the process.
  • The initiator fills out the Contract Management, Potential Bidders, and if required the Sole Source sections of the process form. When finished, click the Submit button.
  • The next step is Skip Bid List Approval?

Bid list approval is always required except in the following cases involving a general contractor. (GC)

  • GC Bid following pre-construction bidding.
  • Subsequent LSW's or Exhibit A's following the first LSW.

Toggle Cloak
2. Furniture or AV Bid? (Decisional Step)

  • Depending on the project the initiator completes the required sections of the page.
    • Contract Management
    • Pre-Priced Agreement for Office/CR/Lab
    • Sole Source
    • Potential Bidders - When adding potential bidders you should add contact information for each bidder prior to submitting for Vendor Manager review. If that information is not provided the process will be returned to your court for the Initiator Revise step
  • When finished, take the Submit action.
  • The next step is Furniture or AV Bid?

Toggle Cloak
Furniture?

Cloak
  • Based on the process initiator's answer to the "Is this a furniture or AV bid?" question the process is routed.
  • If True (Yes) the next step is Bid Doc Preparation
  • If False (No) the next step is AV?

Toggle Cloak
AV?

Cloak
  • Based on the process initiator's answer
Cloak
  • Based on the entry to the "Is this a furniture or AV bid?" question in the process this field is evaluated to determine routing for the processis routed.
  • If True (Yes) the next step is Initiator Prepares Bid Documents. Vendor Mgr Reviews A/V Bid
  • If False (No) the next step is Skip Bid List ApprovalSole Source?

Toggle Cloak
3. Skip Bid List Approval (Decisional Step)Vendor Mgr Reviews A/V Bid

Cloak
  • In this step the Vendor Manager reviews the Bid information. The process reaches this step for A/V Bids.
  • If the Submit action is taken the next step is Program Manager Reviews.
  • If the Revise action is taken he next step is Initiator Review
  • The data field "Skip Bid List Approval?" conditional is evaluated.
  • If True (Yes) the process advances past the Bid List Approval part of the process and goes directly to Initiator Prepares Bid Documents. (Step #28 in this document)
  • If False (No) the next step is Bid List Approval.

Toggle Cloak
4. Vendor Mgr Reviews Prop Bid List Approval

Cloak
  • The Vendor Manager completes reviews the proposed bidders list, completes any required fields and has the option to Submit or Revisebid list.
  • If Submit is chosen the approved the Vendor Manager takes the Submit action. The next step is Program Manager Review. Prepriced Agmt?
  • If the Reviseaction is chosen the taken he next step is Initiator ReviseReview.

Toggle Cloak
5. Initiator RevisePrepriced Agmt?

Cloak
  • The initiator reviews the process, adds comments and makes adjustments as necessary. The Action options for the initiator are To Vendor Manager, To Program Manager or Void.
  • If To Vendor Manager is chosen the next step is Vendor Manager Review.
  • If To Program Manager is chosen the next step is Program Manager Review.
  • If Void is chosen the next step is Finish.

 

Toggle Cloak
6. Program Manager Review

Cloak
  • The Program Manager reads the comments and reviews the process fields and has Action options to Submit or Revise.
  • If Submit is chosen the next step is Campus Construction?
  • If Revise is chosen the next step is Initiator Revise.

 

Toggle Cloak
7. Campus Construction? (Decisional Step)

Cloak
  • e-Builder uses information previously entered to determine if this is a Campus Construction project.
  • If Yes the next step is SP&T Program?
  • If No the next step is OCP?

 

Toggle Cloak
8. SP&T Program? (Decisional Step)

Cloak
  • e-Builder uses information previously entered to determine if this is an SP&T Program.
  • If True (Yes) the next step is SPT Director Review.
  • If False (No) the next step is CC Director Review.

Toggle Cloak
9. SPT Director Review

  • system evaluates this conditional to determine if this is a Pre-priced agreement. Using a pre-priced agreement bypasses the process steps which generate an Approved Bid List.
  • If the use of a pre-priced agreement is approved, the work is awarded to a vendor who has previously bid for for work of a certain scope/complexity in order to be considered for that work in the future.
  • If Pre-priced Agreement is True (Yes) the next step is CA Approved Contract Type.
  • If it is False (No) the next step is Program Manager Review.

Toggle Cloak
Sole Source?

Cloak
  • The system evaluates this conditional to determine if this is a Sole Sourced agreement. Using a Sole Sourced agreement bypasses the process steps which generate an Approved Bid List.
  • If the use of a Sole Source agreement is approved, an explanation must be provided.
  • If this conditional evaluates to True (Yes) the next step is Vendor Reccomendation.
  • If this conditional evaluates to False (No) the next step is Vendor Mgr Reviews Prop Bid List.

Toggle Cloak
Initiator Revise

Cloak
  • Initiator Revise is used to request that the initiator correct an error or add more information to a prior step.
  • The Initiator reviews the process and the comments made by the reviewer and makes adjustments as required. The Action options for the initiator are To Vendor Manager, To Program Manager or Void.
  • If To Vendor Manager is chosen the next step is Vendor Mgr Reviews Prop Bid List.
  • If To Program Manager is chosen the next step is Program Manager Review.
  • If Void is chosen the next step is Finish.

Toggle Cloak
Program Manager Reviews

Cloak
  • The Program Manager reads the comments and reviews the process fields and has the option to take an Action
Cloak
  • The SPT Director reads the comments and reviews the process fields and has the option to Submit or Revise.
  • If Submit is chosen the next step is CC Director Review. Campus Construction?
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
10. CC Director ReviewCampus Construction?

Cloak
  • The CC Director reads the comments and reviews the process fields and has the option to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List (The bid list is approved and Mail Merge creates the bid list)
  • If Revise is chosen the next step is Initiator Revise.
  • e-Builder uses information previously entered about the project to determine if this is a Campus Construction project.
  • If Yes the next step is SP&T Program?
  • If No the next step is OCP?

Toggle Cloak
SP&T Program?
Toggle Cloak
11. OCP? (Decisional Step)

Cloak
  • e-Builder evaluates uses information previously entered to about the project to determine if this is an OCP SP&T Program.
  • If True (Yes) the next step is OCP SPT Director Review.
  • If False (No) the next step is M&U? CC Director Review.

Toggle Cloak
12. OCP SPT Director Review

Cloak
  • The OCP SPT Director reads the comments and reviews the process fields . The OCP Director has options and has the option to take an action to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List (The bid list is approved and Mail Merge creates the bid list) CC Director Review.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
13. M&U? (Decisional Step)CC Director Review

Cloak
  • The CC Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List
  • If Revise is chosen the next step is Initiator Revise.
Cloak
  • e-Builder evaluates information previously entered to determine if this is an M&U program?
  • If Yes the next step is Utilities Program?
  • If No the next step is Campus Services?

Toggle Cloak
14. Utilities Program? (Decisional Step)OCP?

Cloak
  • e-Builder evaluates information previously entered to about the project to determine if this is a Utilities an OCP Program.
  • If True (Yes) the next step is Utilities OCP Director Review.
  • If False (No) the next step is SEG Program M&U?

Toggle Cloak
15. Utilities OCP Director Review

Cloak
  • The Utilities OCP Director reads the comments and reviews the process fields. The Utilities OCP Director has the option to to take an Action to Submit or Revise.
  • If Submit is chosen the next step is M&U Director Review. Approved Bid List
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
M&U?

Cloak
  • e-Builder evaluates information previously entered about the project to determine if this is an M&U program?
  • If Yes the next step is Utilities Program?
  • If No the next step is Campus Services?

Toggle Cloak
16. SEG Utilities Program? (Decisional Step)

Cloak
  • e-Builder evaluates information previously entered to about the project to determine if this is an SEG a Utilities Program.
  • If True (Yes) the next step is SEG Utilities Director Review.
  • If False (No) the next step is O&M Director Review SEG Program?

Toggle Cloak
17. SEG Utilities Director Review

Cloak
  • The SEG Utilities Director reads the comments and reviews the process fields. The SEG Utilities Director has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is M&U Director Review.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
18. O&M Director ReviewSEG Program?

Cloak
  • e-Builder evaluates information previously entered about the project  to determine if this is an SEG Program.
  • If True (Yes) the next step is SEG
Cloak
  • The O&M Director reads the comments and reviews the process fields. The O&M Director has the option to Submit or Revise.
  • If Submit is chosen the next step is M&U Director Review.
  • If Revise is chosen False (No) the next step is Initiator Revise. O&M Director Review?

Toggle Cloak
19. M&U SEG Director Review

Cloak
  • The M&U The SEG Director reads the comments and reviews the process fields. The M&U The SEG Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List (Mail Merge) M&U Director Review.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
20. Campus Services? (Decisional Step)O&M Director Review

Cloak
  • The O&M Director reads the comments and reviews the process fields. The O&M Director has the option to Submit or Revise.
  • If Submit is chosen the next step is M&U
Cloak
  • e-Builder evaluates information previously entered to determine if this is an Campus Services Program.
  • If True (Yes) the next step is CS Director Review.
  • If False (No) Revise is chosen the next step is IBO Director Review? Initiator Revise.

Toggle Cloak
21. CS Director M&U Director Review

Cloak
  • The CS The M&U Director reads the comments and reviews the process fields. The CS The M&U Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List (Mail Merge). (The bid list is approved and Mail Merge creates the bid list.)List
  • If Revise is chosen the next step is Initiator Revise.

toggle-cloak
Campus Services?

Cloak
  • e-Builder evaluates information previously entered about the project to determine if this is an Campus Services Program.
  • If True (Yes) the next step is CS Director Review.
  • If False (No) the next step is IBO Director Review

Toggle Cloak
CS Director 22. IBO Director Review

Cloak
  • The IBO CS Director reads the comments and reviews the process fields. The IBO CS Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List (Mail Merge). (The bid list is approved and Mail Merge creates the bid list.)
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
23. Initiator ReviseIBO Director Review

Cloak
  • The initiator revises IBO Director reads the comments and reviews the process and adds comments if necessary. The initiator Submits when finished with revisions.
  • The next step is Sole Source?

Toggle Cloak
24. Approved Bid List (Automatic Step)

Cloak
  • Automatic step generates the Approved Bid List document.
  • The next step is Initiator Prepares Bid Documents.
Card
  • fields. The IBO Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List.
  • If Revise is chosen the next step is Initiator Revise.
label

Toggle Cloak
25. Initiator Prepares Bid DocumentsRevise

Cloak
  • The initiator , usually the Project Manager, prepares the bid documents and completes the required fields. The Submit Action is taken when finished.revises the process and adds comments if necessary. The initiator Submits when finished with revisions.
  • If the Submit action is taken the next step is Sole Source?
  • If Void is chosen the next step is Finish.The next step is GC Previously Approved?

Toggle Cloak
26. GC Previously Approved? (Decisional Step)Approved Bid List

Cloak
  • e-Builder determines, based on information previously entered, if the GC has already been approved.
  • If True (Yes) the next step is Program Manager Reviews Package.
  • If False (No) the next step is Assemble Bid Package.
  • This step generates the Approved Bid List document from a template
  • The bid list document is placed into the Documents\05 Procurement\0505 Bid Lists (I) folder
  • The next step is CA Apprv Contract Type.
Card
labelDocuments, Contract Approval, Release Bid

Toggle Cloak
CA Apprv Contract Type
Toggle Cloak
27. Assemble Bid Package

Cloak
  • The Contract Adminreads the comments and reviews the process fields. The Contract Admin has the option to take an Action to Submit or Revise
  • If Submit is chosen the next step is Program Manager Reviews Package
  • If Revise is chosen the next step is Initiator Prepares Bid Documents

Toggle Cloak
28. Program Manager Reviews Package

Cloak
  • The Program Manager reads the comments and reviews the process fields. The program manager has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is Initiator Releases Bid.
  • If Revise is chosen the next step is Initiator Prepares Bid Documents.

Toggle Cloak
29. Initiator Releases Bi

Cloak
  • The initiator (usually the Project Manager) works within the Bidding module to complete the steps that enable the Bidding portal for the bid package.
  • Once the bid has been released the Initiator completes the required process fields, takes the Submit Action.
  • The next step is Initiator Recommend Vendor.
  • either approves or changes the contract type or approves the Pre-priced agreement and adds the contract number for that agreement to the process.
  • The Contract Admin takes the Approved action to approve. The next step is Approved Pre-Price.
  • The Contract Admin takes the Changed action when changing the contract type, and adds comments to indicate to the PM that the contract has been changed and the reasons for the change.
  • The next step is Bid Doc Preparation.

Toggle Cloak
Approved Pre-Price Agreement

Cloak
  • This is a conditional step. If True (a Pre-priced agreement) the next step is the Merge/Code step that creates the Selection of Source form document.
  • If False the next step is Bid Document Preparation.

Toggle Cloak
PrePriced SoS

Cloak
  • e-Builder generates the Selection of Source for Pre-priced agreements.
  • The next step is Vendor Manager Review of SoS.

Toggle Cloak
Bid Document Preparation

Cloak
  • The process initiator, usually the Project Manager, prepares/uploads the bid documents and completes the required fields. The Submit action is taken when finished.
  • The next step is Contract Admin Assembles Bid Package

Toggle Cloak
Contract Admin Assembles Bid Package

Cloak
  • The Contract Admin assembles the bid package and when finished takes the Submit action.
  • As part of this process the Contract Admin adds a contract sample and assigns a contract number.

  • The next step is Hold for Bids/Proposals Received.

Toggle Cloak
Hold for Bids/Proposals Received

Cloak

The bid should be released in the Bid module when the process reaches this step.

  • Hold the process in this step from bid release until all bids are received and the bid tab has been opened and analyzed. This may be held for one to several weeks while the bid is open.
  • Once the bids have been analyzed and a vendor recommendation is ready the Project Manager takes the Submit action.
  • The next step is Vendor Recommendation.
Card
labelBid Award Recommendation

Toggle Cloak
Vendor Recommendation

Cloak
  • The Project Manager, having received all the bids and supporting documents, performs the analysis and selects a vendor.
  • The process step form is completed and the Submit action is taken.
  • The next step is Selection of Source.

Toggle Cloak
Selection of Source

Cloak
  • This is an automatic step to generate the Selection of Source document. The Selection of Source template is applied.
  • The next step is Vendor Manager Review of SoS.

Toggle Cloak
Vendor Manager Review of SoS

Cloak
  • The Vendor Manager reviews the selection and has the option to take the Action to Submit or Revise
  • If Submit is chosen the next step is Program Manager Review
  • If Revise is chosen the next step is Vendor Recommendation.

Toggle Cloak
Program Manager Review

Cloak
  • The Program Manager
Card
labelBid Award Recommendation

Toggle Cloak
30. Initiator Recommend Vendor

Cloak
  • The initiator receives all the bid documents, reviews them, and selects a vendor for recommendation. All project managers on the project receive a notification when this step is reached. They will fill out the required fields and Submit.
  • The next step is Selection of Source.

Toggle Cloak
31. Selection of Source (Automatic Step)

Cloak
  • This is an automatic step to generate the Selection of Source document. The Selection of Source template is applied.
  • The next step is DoF Procurement Reviews Selection.

Toggle Cloak
32. Vendor Manager Review of SoS

Cloak
  • Vendor Manager reviews the selection and has the option to take the Action to Submit or Revise
  • If Submit is chosen the next step is Program Manager Review
  • If Revise is chosen the next step is Initiator Recommend Vendor

Toggle Cloak
33. Program Manager Review

Cloak
  • The Program Manager reads the comments and reviews the process fields. The program manager has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is Campus Construction.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
34. Initiator Revise

Cloak
  • The Initiator reviews the process and adds comments and makes adjustments as necessary. The initiator has the option to Submit or Void.
  • If Submit is chosen the next step is Selection of Source.
  • If Void is chosen the next step is Finish.

Toggle Cloak
35. Campus Construction (Decisional Step)

Cloak
  • e-Builder uses information previously entered to to determine "ownership" of the program.
  • If True (Yes) the next step is SP&T Program.
  • If False (No) the next step is M&U.

Toggle Cloak
36. SP&T Program? (Decisional Step)

Cloak
  • The "Contract managed by a different program" field is evaluated.
  • If True (Yes) the next step is SPT Director Review.
  • If False (No) the next step is DoF Procurement Review.

Toggle Cloak
37. SPT Director Review

Cloak
Cloak
  • e-Builder uses information previously entered to determine "ownership" of the program.
  • If True (Yes) the next step is Utilities Program?
  • If False the next step is DoF Procurement Review.
 
  • The SPT Director reads the comments and reviews the process fields. The SPT Director program manager has the option option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is DoF Procurement Review Campus Construction.
  • If Revise is chosen the next step is Initiator Revise .

Toggle Cloak
38. M&U (Decisional Step)

  • Recommendation.

Toggle Cloak
39. Utilities Program (Decisional Step)Initiator Revise Recommendation

Cloak
  • The Initiator reviews the process and adds comments and makes adjustments as necessary. The initiator has the option to Submit or Void.
  • If Submit is chosen the next step is Selection of Source.
  • If Void is chosen the next step is Finish
Cloak
  • e-Builder uses information previously entered to determine "ownership" of the program.
  • If True (Yes) the next step is Utilities Director Review.
  • If False (No) the next step is SEG Program?.

Toggle Cloak
40. Utilities Director ReviewCampus Construction?

Cloak
  • e-Builder uses information previously entered to to determine "ownership" of the program.
  • If True (Yes) the next step is SP&T Program.
  • If False (No) the next step is M&U
  • The utilities director reads the comments and reviews the process fields. The utilities director has the option to Submit or Revise.
  • If Submit is chosen the next step is DoF Procurement Review.
  • If Revise is chosen the next step is Initiator Review.

Toggle Cloak
41. SEG ProgramSP&T Program?

Cloak
  • The "Contract managed by a different program" field is evaluated
Cloak
  • e-Builder uses information previously entered to determine if this is an SEG Program.
  • If True (Yes) the nest next step is SEG SPT Director Review.
  • If False (No) the next step is O&M Director Review. Vendor Manager Review of SoS

Toggle Cloak
42. SEG SPT Director Review

Cloak
  • TheSEG SPT Director reads the comments and reviews the process fields. The SEG SPT Director has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is DoF Procurement Review.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
43. O&M Director Review

Cloak

 

  • The O&M Director reads the comments and reviews the process fields. DoF Procurement has the option to Submit or Revise.
  • If Submit is chosen the next step is DoF Procurement Review.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
44. Vendor Manager Review of SoS

  • Submit or Revise.
  • If Submit is chosen the next step is Vendor Manager Review of SoS.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
M&U2?

Cloak
  • e-Builder uses information previously entered to determine "ownership" of the program.
  • If True (Yes) the next step is Utilities Program?
  • If False (No) the next step is Campus Services?

Toggle Cloak
Utilities Program?

Cloak
  • e-Builder uses information previously entered to determine "ownership" of the program.
  • If True (Yes) the next step is Utilities Director Review.
  • If False (No) the next step is SEG Program?.

Toggle Cloak
Utilities Director Review Rec

Cloak
  • The utilities director
Cloak

 

  • Vendor Manager reads the comments and reviews the process fields. Vendor Manager The utilities director has the option to Submit or Revise.
    If Submit is chosen the next step is Campus Constructionis M&U Director Review Rec.
  • If Revise is chosen the next step is Initiator Revise Recommendation.
 

Toggle Cloak
SEG Program?

Cloak
  • The data field "One Bid" is evaluatede-Builder uses information previously entered to determine if this is an SEG Program.
  • If True (Yes) the next nest step is VPF Procurement SEG Director Review .Rec
  • If False (No) the next step is Lowest Bid?

Toggle Cloak
49. Lowest Bid? (Decisional Step)

Cloak

 

  • The data field Reason Vendor Selected is evaluated to determine If the reason selected is "2.5 Multiple Bidders Selected - Only One Bidder Responded".
  • If True the next step is VPF Procurement Review.
  • If False the next step is Lowest Bid?

Toggle Cloak
50. Lowest Bid? (Decisional Step)

Cloak
  • The data field Reason Vendor Selected is evaluated to determine if the reason selected is "2.2 Adequate price competition (at least 2 quotes): Lowest Bidder Selected. No further explanation required.".
  • If True (Yes) the next step is Campus Construction.
  • If False (No) the next step is VPF Procurement Review.

Toggle Cloak
53. VPF Procurement Review

  • O&M Director Review Rec

Toggle Cloak
SEG Director Review Rec

Cloak
  • The SEG Director reads the comments and reviews the process fields. The SEG Director has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is Vendor Manager Review of SoS.
  • If Revise is chosen the next step is Initiator Revise Recommendation.

Toggle Cloak
O&M Director Review Rec

Cloak
  • The O&M Director reads the comments and reviews the process fields. DoF Procurement has the option to Submit or Revise.
  • If Submit is chosen the next step is Vendor Manager Review of SoS.
  • If Revise is chosen the next step is Initiator Revise Recommendation.

Toggle Cloak
CC Director Review

Cloak
  • The CC Director
Cloak
  • The VPF/Treasury reads the comments and reviews the process fields. The VPF/Treasury CC Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Campus Construction Initiator Awards Bid.
  • If Revise is chosen Revise is chosen the next step is Initiator Revise Recommendation.

Toggle Cloak
OCP?

Cloak
  • Multiple fields are evaluated to determine if this is an OCP Program.
  • If True (Yes) the next step is OCP Director Review.
  • If False (No) the next step is DoF Procurement Review M&U?.

Toggle Cloak
54. Campus Construction (Decisional Step)OCP Director Review

Cloak
  • The OCP Director reads the comments and reviews the process fields. OCP Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise Recommendation.
  • Multiple fields are evaluated to determine if this is a Campus Construction program.
  • If True (Yes) the next step is CC Director Review.
  • If False (No) the next step is OCP?

Toggle Cloak
55. CC M&U Director Review Rec

Cloak
  • The CC M&U Director reads the comments and reviews the process fields . CC Director and has the option to Submit or Revise.
  • If Submit is chosen the next step is Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise Recommendation.

Toggle Cloak
56. OCP? (Decisional Step)Campus Services?

Cloak
  • Multiple fields are evaluated to determine if this is an OCP Program.Campus Services program?
  • If True (Yes) the next step is OCP CS Director Review.
  • If False (No) the next step is M&U? IBO Director Review.

Toggle Cloak
57. OCP CS Director Review

Cloak
  • The OCP The Campus Services Director reads the comments and reviews the process fields. OCP The CC Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
58
  • .
M&U? (Decisional Step)
Cloak
  • Multiple fields are evaluated to determine if this is an M&U program
  • If True (Yes) the next step is M&U Director Review
  • If False (No) the next step is Campus Services?

Toggle Cloak
59. M&U IBO Director Review

Cloak
  • The M&U IBO Director reads the comments and reviews the process fields and . The IBO Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
Initiator Award Bid

Cloak
  • The Initiator reviews the process and awards the bid using the e-Builder Bidding module. The final action when the bid is awarded is to return to the process and take the Submit Action.
  • The next step is Vendor Manager Checks Company Info.If Revise is chosen the next step is Initiator Revise

Toggle Cloak
60. Campus Services? (Decisional Field)Pre-Priced 3?

Cloak
  • Multiple fields are evaluated to determine if this is an Campus Services program?This conditional determines if this process contains a Pre-priced agreement.
  • If True (Yes) the next step is CS Director Review the process moves to Finish.
  • If False (No) the next step is IBO Director Review. the process moves to Vendor Manager Checks Company Info

toggle-cloak
Vendor Mgr Checks Company Info

Cloak
61. CS Director Review
Cloak
  • The Campus Services Director reads the comments and reviews the process fields. The CC Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
62. IBO Director Review

Cloak

The IBO Director reads the comments and reviews the process fields. The IBO Director has the option to Submit or Revise.

  • If Submit is chosen the next step is Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
63. Initiator Award Bid

Cloak

The initiator reviews the process and awards the bid using the e-Builder Bidding module. The initiator Submits.

The next step is Finish.

 

64. Finish

 

Card
idPFI
labelProcess Form Instructions
  • The Vendor Managerchecks and fills out form fields to ensure that:
    • The awarded bidder exists in SAP
    • The company information is correct and current in the Contacts module.
    • If the company is not in SAP that the New Company process has been started.
  • When finished the Vendor Manager takes the Submit action.
  • The next step is Vendor Exists in SAP?

Toggle Cloak
Vendor Exists in SAP?

Cloak
  • This step routes the process to the Finish step if the Vendor exists in SAP.
  • If the Vendor does not exist in SAP the next step is AA Adds New Company.

Toggle Cloak
AA Adds New Company

Cloak
  • If the company does not exist in SAP the AA completes the 01.01 Add New Company/Contact process and holds the process in this step until that has been completed.
  • When completed the AA takes the Vendor Added action.
  • The next step is Vendor Manager Checks Company Info.

Toggle Cloak
Hold for SAP Vendor #

Cloak
  • In this step the Administrative Assistant waits until the Vendor has been assigned a SAP Vendor Number from VPF.
  • If the Submit action is taken the next step is Finish.
  • If the Revise action is taken the next step is AA Adds New Company.

Toggle Cloak
Finish

Cloak

Contract Management

Image Removed

Potential Bidders

Use the Lookup link to display a menu that allows potential bidders to be added.

Image Removed

Sole Source

Indicate if this is a Sole Source procurement. If it is Sole Source, provide a reason.

Image Removed