Card |
---|
| Image Removed | Card |
---|
| | | Workflow Task | Actors |
---|
Who can start this process? | CC Planner, CC Planning Manager, eB Admin, Project Manager, - This process is usually initiated by the CC planner or the project manager. Other roles with the ability to being the process are:
, Who can view drafts of this process? | CC Planner, CC Planning Manager, Project Manager | Who can view all process instances? | CC Planning Manager, CRSP Admin, eB Admin, Program Manager | Who can report on this process? | All Users | Who is notified as the process moves between steps? | All Users | Who can view/add private comments to this process? | No Users | - When not started by the CC planner the process routes to the CC planner as the second step.
- After the PD form is completed this process spawns the 03.01 Milestone Project Budget Estimate process.
Card |
---|
| Image Added
|
Card |
---|
| Card |
---|
| Click > to reveal additional content. | Start (Usually by CC Planner) Cloak | Though usually started by the CC Planner, any of the following may start the process: |
---|
- CC Planning Manager
- eB Admin
- Project Manager
- R&M Manager
- Utilities - Program Manager
Once required fields are completed the form is submitted. - If the process was initiated by CC Planner, the next step is Project Manager Review.
- If not initiated by CC Planner, the next step is CC Planner Completes PD Form.
| CC Planner Completes PD Form Cloak |
---|
- CC Planner reviews the process,
complete - completes the required fields and
chooses these - the following actions: Submit, Revise or Void.
Submit Next Step: - If Submit is chosen the next step is Project Manager Review
Revise Next Step: Initiator Review
- .
- If Void is chosen the next step is Finish. The process is set to a Void status.
Void Next Step: Finish |
Project Project Manager Review Cloak |
---|
Submit Next Step: - The Project Manager reviews the process
, completes the required fields and chooses one of the these actions:- with the option to approve and Submit or to Revise.
- To approve and submit the project manager must complete the required fields including section 9.1 on the process form by choosing the date.
- If Submit is chosen the next step is
- Planning Manager and Prog. Manager Review.
Revise Next Step: CC Planner Revise |
Initiator Review Cloak | Process Initiator reviews the process, completes the required fields and clicks Reply. Next Step: CC Planner Completes PD Form- If Revise is chosen the next step is CC Planner Revise.
|
CC Planner Revise Cloak |
---|
- The CC Planner reviews the process, completes the required fields, and clicks Resubmit.
Next Step: - The next step is Project Manager Review.
|
Planning Manager and Prog. Manager Review Cloak |
---|
- Project Manager and Program Manager review the process, complete the required fields and choose
one of these actions:Submit Next Step: - to Submit or Revise.
- If Submit is chosen the next step is Working Committee Review
Revise Next Step: - IfRevise is chosen the next step is CC Planner Revise
| Spawn 3.01a Budget Approval Process Cloak |
---|
- This step initiates a Budget Approval Process.
- The project manager attaches the budget request spreadsheet requesting the Capital Renewal funding.
- Upon the successful spawning of this Budget Approval Process the next step is Project Manager Review.
| Working Committee Review Cloak |
---|
CC Planning Manager reviews the process with the working committee outside of e-Builder, completes the required fields and chooses one of these actions: - Submit
Next Step: Utilities, O&M and SEG Review - Put On Hold
Next Step: Finish
| Utilities, O&M and SEG Review Cloak |
---|
Utilities Director, O&M Director, and SEG Assignor will review the process, add their comments and click Submit. Next Step: CC Director, Ops, and M&U Review | CC Director, Ops, and M&U Review- In this step the The working committee reviews the budget request
- When Submit is chosen the next step is Property Office Review
- If Put on Hold is chosen the next step is Finish.
| Property Office Review Step Cloak |
---|
- In this step the Property Office reviews the information that has been entered to the process. The Property office then indicates whether or not they agree with the funding type. If the Property Office disagrees with the funding type they should select the have made a change to the funding type on the PD option of the Property Office Review field.
- When Submit is chosen the next step is M(ail) M(erge) Property Office.
| Mail Merge (Automation) Property Office Cloak |
---|
- This automation step sends an e-mail to the Property Office showing the information that has been entered into the process.
- When this step completes successfully the next step is R&M, Utilities, FEG, CC Plnng Review.
| R&M, Utilities, FEG, CC Plnng Review Cloak |
---|
- In this step the CC Planner, Utilities Director, R&M Director, and SEG Assignor
| Cloak |
---|
CC Director, M&U Director and IBO Director will - review the process, add their comments and click Submit.
Next Step: CRSP Planning Review- The next step is Create PD Form
| DoF Planning Manager (Governance)CC Directr & VP, CSS Review Cloak |
---|
CC Planning Manager reviews the process, adds comments, prepares the Capital Renewal List for the RCRSP agenda and clicks Submit: Next Step: Spawn Team Assignment | Spawn Team Assignments Cloak |
---|
When a - In this step the information entered is reviewed by by the CC Director, and the VP, CSS Director.
- When the
from the DoF Planning Manager step, the process proceeds to this spawned step. In the spawn step the 2.01 - Team Assignment process starts and is moved to the first step of that workflow. The following action is automatically taken after:Next Step: Finance Office Issues IO Number- the next step is Create PD Form.
| Finance Officer Issues IO NumberCreate PD Form Cloak |
---|
Financial Officer reviews the process, adds the Cost Object Number, and clicks Submit. Next Step: Apply Funding | Apply FundingCC Planning Manager Hold - Record Approvals Cloak |
---|
- In this step, the approved Capital Renewal allocation is recorded.
- When the Create Final PD action is taken the next step is Create Final PD Form.
Financial Analyst reviews the process, applies funding, and clicks Submit: Next Step: Finish | FinishCreate Final PD Form Cloak |
---|
The process is complete. | - In this automation step e-Builder
|
|
|