Result or Product of this Process

Round Rectangle
bgcolor#e6f2ff
width100%

The 04.00 01 Bidding process produces:

  • An Approved Bidder List
  • The Bid Package containing Bid Documents
  • A released bid
  • Tabulation of bidder submissions
  • An approved award recommendation
  • An Awarded Bidder who has been notified of the Award
  • Bidders notified that they have not been selected for the Award

Process Details

Composition Setup
 

is used for Bid List Approval, Release to Bid and Bid Award Recommendation including these specific steps.

  • Obtain an approved list of bidders
  • Prepare and gain approval of the bid package documents including the proposed sample contract provided by the Contract Admin
  • Secure approval to release the bid
  • Recommend an award supported by the bid tabulation in the Bidding module.
  • Gain approval to use a pre-priced agreement to award certain types of work to selected vendors.
  • Create the Selection of Source form and have it reviewed and approved by the Vendor Manager
  • Following approval, award the bid.
  • Ensure that the awarded bidder is properly set up in e-Builder and SAP

Note that the Bidding process is used to inform internal actors about the bid and gain approval to proceed through the bidding stages, from Bid List approval to award. The Bid module is used to construct and publish the bid to the Bidders portal and to initiate your Contract and Purchase order request.

Process Details

Deck of Cards
idBid
Card
labelSummary

The Bidding process and the Bidding module are both used to complete a bid and issue an award.

Card
labelProcess Map

Image Added

Card
labelStep Descriptions

To make the Step descriptions for Bidding easier to read they have been separated into the three parts (tabs). 

Deck of Cards
idSDBid
historyfalse
Card
labelBid List Approval

Toggle Cloak
Start

Cloak
  • The Bidding process is usually initiated by the Project Manager.
  • Depending on the project the initiator completes the required sections of the page.
    • Contract Management
    • Pre-Priced Agreement for Office/CR/Lab
    • Sole Source
    • Potential Bidders - When adding potential bidders you should add contact information for each bidder prior to submitting for Vendor Manager review. If that information is not provided the process will be returned to your court for the Initiator Revise step
  • When finished, take the Submit action.
  • The next step is Furniture or AV Bid?

Toggle Cloak
Furniture?

Cloak
  • Based on the process initiator's answer to the "Is this a furniture or AV bid?" question the process is routed.
  • If True (Yes) the next step is Bid Doc Preparation
  • If False (No) the next step is AV?

Toggle Cloak
AV?

Cloak
  • Based on the process initiator's answer to the "Is this a furniture or AV bid?" question the process is routed
Deck of Cards
idBid
Card
labelSummary

The Project Manager uses the bidding process and the bidding module to:

  • Compose a list of potential bidders and receive approval on the bidder list
  • Prepare the bid documents and assemble the bid package
  • Release the bid package through the e-Builder Bidder Portal
  • Answer and respond to questions about the bid from the bidders
  • Tabulate and analyze the submitted bids
  • Make an award recommendation
  • Gain approval of the award recommendation
  • Award the bid and notify the winning bidder
  • Notify bidders not selected

Awarding the bid in e-Builder kicks off the commitment/purchase order process

Card
labelProcess Map

Image Removed

Card
labelStep Descriptions

Step descriptions for Bidding have been separated into the three discrete parts below. While Bidding is one process, the supporting documentation is made easier to read by making this division..

Deck of Cards
idSDBid
historyfalse
Card
labelBid List Approval

Toggle Cloak
1. Start

Cloak
  • The Bidding process is usually started by the Project Manager however the OCP Planner, SPT Lead, SPT Commissioning Lead or VPF Strategic Sourcing may also start the process.
  • The initiator fills out the Contract Management, Potential Bidders, and Sole Source sections of the process form. When finished, click the Submit button.
  • The next step is A133 Been Signed?

Toggle Cloak
2. Furniture or AV Bid? (Decisional Step)

Cloak
  • The data field "Is this a furniture or AV bid" is evaluated.
  • If True (Yes) the next step is PM Prepares Bid Documents.
  • If False (No) the next step is Vendor Manager Review.

Toggle Cloak
3. A133 Been Signed? (Decisional Step)

Cloak
  • The data field "Has the A133 Been Signed?" is evaluated.
  • If True (Yes) the next step is PM Prepares Bid Documents.
  • If False (No) the next step is Vendor Manager Review.

Toggle Cloak
4. Vendor Manager Review

Cloak
  • The Vendor Manager completes the required fields and has the option to Submit or Revise.
  • If Submit is chosen the next step is Program Manager Reviews.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
5. Initiator Revise

Cloak
  • The initiator reviews the process adds comments and makes adjustments as necessary. The options for the indicator are To Vendor Manager, To Program Manager or Void.
  • If To Vendor Manager is chosen the next step is Vendor Manager Review.
  • If To Program Manager is chosen the next step is Program Manager Review.
  • If Void is chosen the next step is Finish.

 

Toggle Cloak
6. Program Manager Review

Cloak
  • The Program Manager reads the comments and reviews the process fields. The Program Manager has options to Submit or Revise.
  • If Submit is chosen the next step is Sole Source?
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
7. Sole Source? (Decisional Step)

Cloak
  • The data field "Sole Source?" is evaluated.
  • If True (Yes) the next step is VPF Procurement Reviews Bid Package
  • If False (No) the next step is Campus Construction?.

Toggle Cloak
8. Campus Construction? (Decisional Step)

Cloak
  • Multiple fields are evaluated to determine if this is a Campus Construction project.
  • If Yes the next step is SP&T Program?
  • If No the next step is OCP?

 

Toggle Cloak
9. SP&T Program? (Decisional Step)

Cloak
  • Multiple fields are evaluated to determine if this is an SP&T Program.
  • If True (Yes) the next step is VPF Strategic Sourcing Review. Vendor Mgr Reviews A/V Bid
  • If False (No) the next step is Projects Director Review. Sole Source?

Toggle Cloak
10. SPT Director ReviewVendor Mgr Reviews A/V Bid

Cloak
  • In this step the Vendor Manager reviews the Bid information. The process reaches this step for A/V Bids.
  • If the Submit action is taken the next step is Program Manager Reviews.
  • If the Revise action is taken he next step is Initiator Review
  • The SPT Director reads the comments and reviews the process fields and has the option to Submit or Revise.
  • If Submit is chosen the next step is CC Director Review.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
11. Projects Director ReviewVendor Mgr Reviews Prop Bid List

Cloak
  • The Projects Director reads the comments and reviews the process fields and has the option to Submit or Revise Vendor Manager reviews the proposed bid list.
  • If Submit is chosen the approved the Vendor Manager takes the Submit action. The next step is CC Director Review. Prepriced Agmt?
  • If the Reviseaction is chosen the taken he next step is Initiator ReviseReview.

Toggle Cloak
12. CC Director ReviewPrepriced Agmt?

Cloak
  • The CC Director reads the comments and reviews the process fields and has the option to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List (The bid list is approved and Mail Merge creates the bid list)
  • system evaluates this conditional to determine if this is a Pre-priced agreement. Using a pre-priced agreement bypasses the process steps which generate an Approved Bid List.
  • If the use of a pre-priced agreement is approved, the work is awarded to a vendor who has previously bid for for work of a certain scope/complexity in order to be considered for that work in the future.
  • If Pre-priced Agreement is True (Yes) the next step is CA Approved Contract Type.
  • If it is False (No) the next step is Program Manager ReviewIf Revise is chosen the next step is Initiator Revise.

Toggle Cloak
13. OCP? (Decisional Step)Sole Source?

Cloak
  • The system evaluates this conditional to determine if this is a Sole Sourced agreement. Using a Sole Sourced agreement bypasses the process steps which generate an Approved Bid List.
  • If the use of a Sole Source agreement is approved, an explanation must be provided.
  • If this conditional evaluates to
  • Multiple fields are evaluated to determine if this is an OCP Program.
  • If True (Yes) the next step is OCP Director Review Vendor Reccomendation.
  • If this conditional evaluates to False (No) the next step is M&U? Vendor Mgr Reviews Prop Bid List.

Toggle Cloak
14. OCP Director ReviewInitiator Revise

Cloak
  • Initiator Revise is used to request that the initiator correct an error or add more information to a prior step.
  • The Initiator reviews the process and the comments made by the reviewer and makes adjustments as required. The Action options for the initiator are To Vendor Manager, To Program Manager or Void.
  • If To Vendor Manager
Cloak

The OCP Director reads the comments and reviews the process fields. The OCP Director has options to Submit or Revise.

If Submit
  • is chosen the next step is
Approved Bid List (The bid list is approved and Mail Merge creates the bid list)
  • Vendor Mgr Reviews Prop Bid List.
  • If To Program Manager is chosen the next step is Program Manager Review.
  • If Void
If Revise
  • is chosen the next step is
Initiator Revise
  • Finish.

Toggle Cloak
15. M&U? (Decisional Step)

Cloak
  • Multiple fields are evaluated to determine if this is an M&U program?
  • If Yes the next step is Utilities Program?
  • If No the next step is Campus Services?

Toggle Cloak
16. Utilities Program? (Decisional Step)

Program Manager Reviews

Cloak
  • The Program Manager reads the comments and reviews the process fields and has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is Campus Construction?
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
Campus Construction?

Cloak
  • e-Builder uses information previously entered about the project
Cloak
  • Multiple fields are evaluated to determine if this is a Utilities Program Campus Construction project.
  • If True (Yes) the next step is Utilities Director Review. SP&T Program?
  • If False (No) the next step is SEG Program OCP?

Toggle Cloak
17. Utilities Director ReviewSP&T Program?

Cloak
  • e-Builder uses information previously entered about the project to determine if this is an SP&T Program.
  • If True (Yes)
  • The Utilities Director reads the comments and reviews the process fields. The Utilities Director has the option to Submit or Revise.
  • If Submit is chosen the next step is M&U SPT Director Review.
  • If Revise is chosen False (No) the next step is Initiator Revise CC Director Review.

Toggle Cloak
18. SEG Program? (Decisional Step)SPT Director Review

Cloak
  • The SPT Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
  • If Submit is chosen
  • Multiple fields are evaluated to determine if this is an SEG Program.
  • If True (Yes) the next step is SEG CC Director Review.
  • If False (No) Revise is chosen the next step is O&M Director Review? Initiator Revise.

Toggle Cloak
19. SEG CC Director Review

Cloak
  • The SEG CC Director reads the comments and reviews the process fields. The SEG Director has the option to Submit or Revise.
  • If Submit is chosen the next step is M&U Director Review.
  • If Revise is chosen the next step is Initiator Revise.
  • the process fields and has the option to take an action to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
OCP?

Cloak
  • e-Builder evaluates information previously entered about the project to determine if this is an OCP Program.
  • If True (Yes) the next step is OCP Director Review.
  • If False (No) the next step is M&U?

Toggle Cloak
OCP
Toggle Cloak
20. O&M Director Review

Cloak
  • The O&M OCP Director reads the comments and reviews the process fields. The O&M OCP Director has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is M&U Director Review. Approved Bid List
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
21. M&U Director Review?

Cloak
  • e-Builder evaluates information previously entered about the project to determine if this is an M&U program?
  • If Yes the next step is Utilities Program?
  • If No the next step is Campus Services?
  • The M&U Director reads the comments and reviews the process fields. The M&U Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List (Mail Merge).
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
22. Campus Services? (Decisional Step)Utilities Program?

Cloak
  • e-Builder evaluates information previously entered about the project to
Cloak
  • Multiple fields are evaluated to determine if this is an Campus Services a Utilities Program.
  • If True (Yes) the next step is CS Utilities Director Review.
  • If False (No) the next step is IBO Director Review SEG Program?

Toggle Cloak
23. CS Director Utilities Director Review

Cloak
  • The CS Utilities Director reads the comments and reviews the process fields. The CS Utilities Director has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is M&U Director Review.
  • If Revise is chosen the next step is Approved Bid List (Mail Merge). (The bid list is approved and Mail Merge creates the bid list.)If Revise is chosen the next step is Initiator Revise.is Initiator Revise.

Toggle Cloak
SEG Program?

Cloak
  • e-Builder evaluates information previously entered about the project  to determine if this is an SEG Program.
  • If True (Yes) the next step is SEG Director Review.
  • If False (No) the next step is O&M Director Review?

Toggle Cloak
24. IBO SEG Director Review

Cloak
  • The IBO SEG Director reads the comments and reviews the process fields. The IBO SEG Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List (Mail Merge). (The bid list is approved and Mail Merge creates the bid list.) M&U Director Review.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
25. Initiator ReviseO&M Director Review

Cloak
Cloak
  • The VPF/Treasury The initiator revises the process and adds comments if necessary. The initiator Submits when finished with revisions.
  • The next step is Sole Source?

Toggle Cloak
26. VPF Procurement Reviews Bid Package

  • O&M Director reads the comments and reviews the process fields. The following are the possible actionsO&M Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Campus Construction M&U Director Review.
  • If Revise is chosen the next step is Initiator Revise.

toggle-cloak
27. Approved Bid List (Automatic Step)

Cloak
  • Automatic step generates the Approved Bid List document.
  • The next step is Initiator Prepares Bid Documents.
Card
labelRelease to Bid

Cloak
M&U Director Review

Cloak
  • The M&U Director reads the comments and reviews the process fields. The M&U Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
Campus Services?

Cloak
  • e-Builder evaluates information previously entered about the project to determine if this is an Campus Services Program.
  • If True (Yes) the next step is CS Director Review.
  • If False (No) the next step is IBO Director Review

Toggle Cloak
CS Director Review

Cloak
  • The CS Director reads the comments and reviews the process fields. The CS Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
IBO Director Review

Cloak
  • The IBO Director

Toggle Cloak
28. Initiator Prepares Bid Documents

Cloak
  • The initiator prepares the bid documents, completes the required fields and Submits when finished.
  • The next step is DOF Procurement Assembles Bid Package.

Toggle Cloak
29. Has A133 Been Signed? (Decisional Step)

Cloak
  • The data field "Has the A133 been signed?" is evaluated.
  • If True (Yes) the next step is Program Manager Reviews Package.
  • If False (No) the next step is DoF Procurement Assembles Bid Package.

Toggle Cloak
30. DoF Procurement Assembles Bid Package

Cloak
  • The DOF Procurement reads the comments and reviews the process fields DoF Procurement may . The IBO Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Projects Director Reviews Package Approved Bid List.
  • If Revise is chosen the next step is PM Prepares Bid Documents Initiator Revise.

Toggle Cloak
31. Program Manager Reviews PackageInitiator Revise

Cloak
  • The program manager reads the comments and reviews the process fields. The program manager has the option to Submit or Reviseinitiator revises the process and adds comments if necessary. The initiator Submits when finished with revisions.
  • If the Submit action is chosen taken the next step is DoF Procurement Assembles Bid Package. Sole Source?
  • If Revise Void is chosen the next step is PM Prepares Bid Documents Finish.

Toggle Cloak
32. Projects Director Reviews PackageApproved Bid List

Cloak
  • The Projects Director reads the comments and reviews the process fields The Projects Director may Submit of Revise.
  • If Submit is chosen the next step is Release to Bid (Mail Merge).
  • If Revise is chosen the next step is PM Prepares Bid Documents.

Toggle Cloak
33. Initiator Releases Bid (The initiator works in the Bidding Module prior to Submitting this step)

Cloak
  • The initiator completes the required process fields, Submits and uses the e-Builder Bidding module to send the bids to the approved bid list.
  • The next step is Initiator Recommends Vendor.
  • This step generates the Approved Bid List document from a template
  • The bid list document is placed into the Documents\05 Procurement\0505 Bid Lists (I) folder
  • The next step is CA Apprv Contract Type.
Card
labelDocuments, Contract Approval, Release Bid

Toggle Cloak
CA Apprv Contract Type

Cloak
  • The Contract Admin either approves or changes the contract type or approves the Pre-priced agreement and adds the contract number for that agreement to the process.
  • The Contract Admin takes the Approved action to approve. The next step is Approved Pre-Price.
  • The Contract Admin takes the Changed action when changing the contract type, and adds comments to indicate to the PM that the contract has been changed and the reasons for the change.
  • The next step is Bid Doc Preparation.

Toggle Cloak
Approved Pre-Price Agreement

Cloak
  • This is a conditional step. If True (a Pre-priced agreement) the next step is the Merge/Code step that creates the Selection of Source form document.
  • If False the next step is Bid Document Preparation.

Toggle Cloak
PrePriced SoS

Cloak
  • e-Builder generates the Selection of Source for Pre-priced agreements.
  • The next step is Vendor Manager Review of SoS.

Toggle Cloak
Bid Document Preparation

Cloak
  • The process initiator, usually the Project Manager, prepares/uploads the bid documents and completes the required fields. The Submit action is taken when finished.
  • The next step is Contract Admin Assembles Bid Package

Toggle Cloak
Contract Admin Assembles Bid Package

Cloak
  • The Contract Admin assembles the bid package and when finished takes the Submit action.
  • As part of this process the Contract Admin adds a contract sample and assigns a contract number.

  • The next step is Hold for Bids/Proposals Received.

Toggle Cloak
Hold for Bids/Proposals Received

Cloak

The bid should be released in the Bid module when the process reaches this step.

  • Hold the process in this step from bid release until all bids are received and the bid tab has been opened and analyzed. This may be held for one to several weeks while the bid is open.
  • Once the bids have been analyzed and a vendor recommendation is ready the Project Manager takes the Submit action.
  • The next step is Vendor Recommendation.
Card
labelBid Award Recommendation

Toggle Cloak
Vendor Recommendation

Cloak
  • The Project Manager, having received all the bids and supporting documents, performs the analysis and selects a vendor.
  • The process step form is completed and the Submit action is taken.
  • The next step is Selection of Source.

Toggle Cloak
Selection of Source

Cloak
  • This is an automatic step to generate the Selection of Source document. The Selection of Source template is applied.
  • The next step is Vendor Manager Review of SoS.

Toggle Cloak
Vendor Manager Review of SoS

Cloak
  • The Vendor Manager reviews the selection and has the option to take the Action to Submit or Revise
  • If Submit is chosen the next step is Program Manager Review
  • If Revise is chosen the next step is Vendor Recommendation.

Toggle Cloak
Program Manager Review

Cloak
  • The Program Manager reads the comments and reviews the process fields. The program manager has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is Campus Construction.
  • If Revise is chosen the next step is Initiator Revise Recommendation.

Toggle Cloak
Initiator Revise Recommendation

Cloak
  • The Initiator reviews the process and adds comments and makes adjustments as necessary. The initiator has the option to Submit or Void
Card
labelBid Award Recommendation

Toggle Cloak
34. Initiator Recommend Vendor

Cloak
  • The initiator receives all the bid documents, reviews them, and selects a vendor for recommendation. All project managers on the project receive a notification when this step is reached. They will fill out the required fields and Submit.
  • The next step is Selection of Source.

Toggle Cloak
35. Selection of Source (Automatic Step)

Cloak
  • This is an automatic step to generate the Selection of Source document. The Selection of Source template is applied.
  • The next step is Program Manager Review.

Toggle Cloak
36. DoF Procurement Reviews Selection

Cloak
  • DoF Procurement reviews the selection and has the option to Submit or Revise
  • If Submit is chosen the next step is Program Manager Review
  • If Revise is chosen the next step is Initiator Recommend Vendor

Toggle Cloak
37. Program Manager Review

Cloak
  • The program manager reads the comments and reviews the process fields. The program manager has the option to Submit or Revise.
  • If Submit is chosen the next step is Campus Construction.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
38. Initiator Revise

Cloak
  • The initiator reviews the process and adds comments and makes adjustments as necessary. The initiator has the option to Submit or Void.
  • If Submit is chosen the next step is Selection of Source.
  • If Void is chosen the next step is Finish.

Toggle Cloak
39. Campus Construction (Decisional Step)

Cloak
  • Multiple fields are evaluated to determine "ownership of the program".
  • If True (Yes) the next step is SP&T Program.
  • If False (No) the next step is M&U.

Toggle Cloak
40. SP&T Program? (Decisional Step)

Cloak
  • The "Contract managed by a different program" field is evaluated.
  • If True (Yes) the next step is VPF Strategic Sourcing Review.
  • If False (No) the next step is Project Director Review.

Toggle Cloak
41. SPT Director Review

Cloak
  • The SPT Director reads the comments and reviews the process fields. The SPT Director has the option to Submit or Revise.
  • If Submit is chosen the next step is DoF Procurement Review.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
42. Projects Director Review

Cloak
  • The projects director reads the comments and reviews the process fields. The Projects Director has the option to Submit or Revise.
  • If Submit is chosen the next step is DoF Procurement Review.
  • If Revise is chosen the next step is Initiator Revise.

 

Toggle Cloak
43. M&U (Decisional Step)

Cloak
  • Multiple fields are evaluated to determine ownership of the program.
  • If True (Yes) the next step is Utilities Program?
  • If False the next step is DoF Procurement Review.

 

Toggle Cloak
44. Utilities Program (Decisional Step)

Cloak
  • Multiple fields are evaluated to determine "ownership of the program".
  • If True (Yes) the next step is Utilities Director Review.
  • If False (No) the next step is SEG Program?.

Toggle Cloak
45. Utilities Director Review

Cloak
  • The utilities director reads the comments and reviews the process fields. The utilities director has the option to Submit or Revise.
  • If Submit is chosen the next step is DoF Procurement Review Selection of Source.
  • If Revise Void is chosen the next step is Initiator Review Finish.

Toggle Cloak
46. SEG ProgramCampus Construction?

Cloak
  • Multiple fields are evaluated to determine if this is an SEG Programe-Builder uses information previously entered to to determine "ownership" of the program.
  • If True (Yes) the nest next step is SEG Director Review SP&T Program.
  • If False (No) the next step is OM&M Director ReviewU.

Toggle Cloak
47. SEG Director ReviewSP&T Program?

Cloak
  • The "Contract managed by a different program" field is evaluated.
  • If True (Yes) the next step is SPT Director Review.
  • If False (No) the next step is
Cloak
  • The SEG Director reads the comments and reviews the process fields. The SEG Director has the option to Submit or Revise.
  • If Submit is chosen the next step is DoF Procurement Review.
  • If Revise is chosen the next step is Initiator Revise.Vendor Manager Review of SoS

Toggle Cloak
48. O&M SPT Director Review

 
Cloak
  • The O&M SPT Director reads the comments and reviews the process fields. DoF Procurement The SPT Director has the option to Submit or Revise.
  • If Submit is chosen the next step is DoF Procurement Vendor Manager Review of SoS.
  • If Revise is chosen the next step is Initiator Revise..

Toggle Cloak
M&U2?

Cloak
  • e-Builder uses information previously entered to determine "ownership" of the program.
  • If True (Yes) the next step is Utilities Program?
  • If False (No) the next step is Campus Services?

Toggle Cloak
49. DoF Procurement ReviewUtilities Program?

Cloak
  • e-Builder uses information previously entered to determine "ownership" of the program.
  • If True (Yes) the next step is Utilities Director Review.
  • If False (No) the next step is SEG Program?

 

  • DoF Procurement reads the comments and reviews the process fields. The O&M Director has the option to Submit or Revise.
  • If Submit is chosen the next step is A133 Been Signed?.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
50. A133 Been Signed? (Decisional Step}Utilities Director Review Rec

Cloak
  • The data field "Has the A133 Been Signed" is evaluated.
  • If True (Yes) the next step is Campus Construction.
  • If False (No) the next step is >10M

Toggle Cloak
51. >10M (Decisional Step)

  • The utilities director reads the comments and reviews the process fields. The utilities director has the option to Submit or Revise.
    If Submit is chosen the next step is M&U Director Review Rec.
  • If Revise is chosen the next step is Initiator Revise Recommendation.

Toggle Cloak
SEG Program?

Cloak
  • e-Builder uses information previously entered to determine if this is an SEG Program
Cloak
  • The data field ">10M" is evaluated.
  • If True (Yes) the next nest step is VPF Procurement SEG Director Review .Rec
  • If False (No) the next step is One Bid? O&M Director Review Rec

Toggle Cloak
52. One Bid? (Decisional Step)SEG Director Review Rec

Cloak

 

  • The data field Reason Vendor Selected is evaluated to determine If the reason selected is "2.5 Multiple Bidders Selected - Only One Bidder Responded".
  • If True the next step is VPF Procurement Review.
  • If False the next step is Lowest Bid?

Toggle Cloak
53. Lowest Bid? (Decisional Step)

Cloak
  • The data field Reason Vendor Selected is evaluated to determine if the reason selected is "2.2 Adequate price competition (at least 2 quotes): Lowest Bidder Selected. No further explanation required.".
  • If True the next step is Campus Construction.
  • If False the next step is VPF Procurement Review.

Toggle Cloak
54. VPF Procurement Review

  • The SEG Director reads the comments and reviews the process fields. The SEG Director has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is Vendor Manager Review of SoS.
  • If Revise is chosen the next step is Initiator Revise Recommendation.

Toggle Cloak
O&M Director Review Rec

Cloak
  • The O&M Director reads the comments and reviews the process fields. DoF Procurement has the option to Submit or Revise.
  • If Submit is chosen the next step is Vendor Manager Review of SoS.
  • If Revise is chosen the next step is Initiator Revise Recommendation.

Toggle Cloak
CC Director Review

Cloak
  • The CC Director
Cloak
  • The VPF/Treasury reads the comments and reviews the process fields. The VPF/Treasury CC Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Campus Construction Initiator Awards Bid.
  • If Revise is chosen Revise is chosen the next step is Initiator Revise Recommendation.

Toggle Cloak
OCP?

Cloak
  • Multiple fields are evaluated to determine if this is an OCP Program.
  • If True (Yes) the next step is OCP Director Review.
  • If False (No) the next step is DoF Procurement Review M&U?.

Toggle Cloak
55. Campus Construction (Decisional Step)OCP Director Review

Cloak
  • The OCP Director reads the comments and reviews the process fields. OCP Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise Recommendation.
  • Multiple fields are evaluated to determine if this is a Campus Construction program.
  • If True (Yes) the next step is CC Director Review.
  • If False (No) the next step is OCP?

Toggle Cloak
56. CC M&U Director Review Rec

Cloak
  • The CC M&U Director reads the comments and reviews the process fields . CC Director and has the option to Submit or Revise.
  • If Submit is chosen the next step is Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise Recommendation.

Toggle Cloak
57. OCP? (Decisional Step)Campus Services?

Cloak
  • Multiple fields are evaluated to determine if this is an OCP Program.Campus Services program?
  • If True (Yes) the next step is OCP CS Director Review.
  • If False (No) the next step is M&U? IBO Director Review.

Toggle Cloak
58. OCP CS Director Review

Cloak
  • The OCP The Campus Services Director reads the comments and reviews the process fields. OCP The CC Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
59
  • .
M&U? (Decisional Step)
Cloak
  • Multiple fields are evaluated to determine if this is an M&U program
  • If True (Yes) the next step is M&U Director Review
  • If False (No) the next step is Campus Services?

Toggle Cloak
60. M&U IBO Director Review

Cloak
  • The M&U IBO Director reads the comments and reviews the process fields and . The IBO Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
Initiator Award Bid

Cloak
  • The Initiator reviews the process and awards the bid using the e-Builder Bidding module. The final action when the bid is awarded is to return to the process and take the Submit Action.
  • The next step is Vendor Manager Checks Company Info.If Revise is chosen the next step is Initiator Revise

Toggle Cloak
61. Campus Services? (Decisional Field)Pre-Priced 3?

Cloak
  • Multiple fields are evaluated to determine if this is an Campus Services program?This conditional determines if this process contains a Pre-priced agreement.
  • If True (Yes) the next step is CS Director Review the process moves to Finish.
  • If False (No) the next step is IBO Director Review. the process moves to Vendor Manager Checks Company Info

toggle-cloak
Vendor Mgr Checks Company Info

Cloak
62. CS Director Review
Cloak
  • The Campus Services Director reads the comments and reviews the process fields. The CC Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
63. IBO Director Review

Cloak

The IBO Director reads the comments and reviews the process fields. The IBO Director has the option to Submit or Revise.

  • If Submit is chosen the next step is Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
64. Initiator Award Bid

Cloak

The initiator reviews the process and awards the bid using the e-Builder Bidding module. The initiator Submits.

The next step is Finish.

 

65. Finish

 

Card
idPFI
labelProcess Form Instructions
  • The Vendor Managerchecks and fills out form fields to ensure that:
    • The awarded bidder exists in SAP
    • The company information is correct and current in the Contacts module.
    • If the company is not in SAP that the New Company process has been started.
  • When finished the Vendor Manager takes the Submit action.
  • The next step is Vendor Exists in SAP?

Toggle Cloak
Vendor Exists in SAP?

Cloak
  • This step routes the process to the Finish step if the Vendor exists in SAP.
  • If the Vendor does not exist in SAP the next step is AA Adds New Company.

Toggle Cloak
AA Adds New Company

Cloak
  • If the company does not exist in SAP the AA completes the 01.01 Add New Company/Contact process and holds the process in this step until that has been completed.
  • When completed the AA takes the Vendor Added action.
  • The next step is Vendor Manager Checks Company Info.

Toggle Cloak
Hold for SAP Vendor #

Cloak
  • In this step the Administrative Assistant waits until the Vendor has been assigned a SAP Vendor Number from VPF.
  • If the Submit action is taken the next step is Finish.
  • If the Revise action is taken the next step is AA Adds New Company.

Toggle Cloak
Finish

Cloak

Contract Management

Image Removed

Potential Bidders

Use the Lookup link to display a menu that allows potential bidders to be added.

Image Removed

Sole Source

Indicate if this is a Sole Source procurement. If it is Sole Source, provide a reason.

Image Removed