...
The path to launch is long an arduous. To be ready for a smooth, on-time, successful launch a number of gates and milestones must be reached on the road to launch. The launch flow is documented here. To see what the team did for the launch of Hermes 2, see Hermes 2 Launch Preparations.
Table of Contents | ||
---|---|---|
|
...
Major mission package components were fit check with the pathfinder FRR and the fit check Hermes III Payload Bulkhead.
| |
The vehicle is simming to 79,800 ft, with a pad weight of 162 lbs. It is expected to be 12' 2" |
November 11, 2019 Ground Test
Successfully integrated the Mission Package and fired the piston.
November 27, 2019 GO/NO GO Gate
...
- Flight case hydro-statically tested
- Enough chemicals in the Prop Shop to mix the flight motor
Recovery
- Piston Test Complete
- Ground Test Complete
- Drop Test Complete
- Drogue Pull Test
...
Avionics
- Purchase COTS Altimeters
- Vacuum Test
...
Composites
- Fin Can Test Jig Complete
- Nose Cone Tip Jig Complete
...
Internal Structures
- Tumble Test
...