{dynamictasklist:thingsToDo}
This is a link to attachment: [Excel.xls|^Cutover_Plan_V1.xls]
| BUILD | R3 | (/) | 1 | Move transports from SF5 to PS1 Config.(See Transports Tab) | R3 Admin | R3 Admin | 8/25/2007 |
| BUILD | LOGISTIC | (/) | 2 | Load Material Master | Ian B | | 8/27/2007 |
| BUILD | LOGISTIC | (/) | 3 | Load Inventory | Ian B | | 8/27/2007 |
| BUILD | CAO | | 4 | Create Secondary Cost Element " Visitor Parking \-\- Not MTDC #600607" | Gill | | 8/28/2007 |
| BUILD | CAO | | 5 | Create Secondary Cost Element 600760 type 43 "Visitor Parking \-\- Not MTDC" | Gill | | 8/28/2007 |
| BUILD | CAO | | 6 | Add cost element 600760 to Cost Element Groups for ZSTM Reporting | Gill | | 8/28/2007 |
| BUILD | CAO | | 7 | Add cost element 600607 to Cost Element Groups for ZSTM Reporting | Gill | | 8/28/2007 |
| BUILD | SAIS | | 8 | Check planning for FY08 and ensure it is part of PROD. Setup | Bob. C. | | 8/20/2007 |
| BUILD | CAO | | 9 | Create Activity Type PMPRK2 with allocation cost element 600760 | M. Benson | | 8/29/2007 |
| BUILD | CAO | | 10 | Create Planned Price for combination of CC1693800 and Act Type PMPRK2 | M. Benson | | 8/29/2007 |
| BUILD | CAO | | 11 | Create Work Center's Kresge, Main, Mass, Hayward, East w/ costing for 1693800 and Acitivity Type PMPRK2 | M. Benson | | 8/29/2007 |
| | | | 11a | Setup Job for Batch Settlement | Lisa | | Delayed |
| BUILD | LOGISTIC | | 12 | Maintain ZVPLOTWORK with SLOC and Work Centers | Ian B. | | Delayed |
| BUILD | LOGISTIC | | 13 | Maintain Number Range for Order Type Park in Production | John B. | | 8/25/2007 |
| | | | | Create Message for SAPweb downtime of parking application | Bill M. | | |
| | | | 13a | Request Dev. Transports to PS1 | Ian B. | | |
| BUILD | IDD | | 14 | Request web project move to PS1 | Bill M. | | |
| BUILD | IDD | | 15 | Request to move Help files to PS1 | Bill M. | | |
| | | | 15a | Change Gateway Page | Bill M. | | |
| BUILD | R3 | | 16 | Authorizations for the Roles | George P. | | |
| Test | Parking | | 17 | Create Live Test data via web transactions in production | Robynn | | |
| Test | Community | | 18 | Create Live Test data via SAPweb to be refunded after settlement | Pam S. | | |
| Test | SAIS | | 19 | Let settlement program settle outstanding orders on Sunday night | Batch User | | |
| Test | SAIS | | 20 | Review settlement on Monday morning to ensure accuracy in results | Ian B. | | |}{dynamictasklist} |