Section
Column

We are

...

working on the release of RAFT II. This is a major release. This checklist tracks is the current release path of RAFT

...

II to the

...

Initiation

  • Points of contact and release team defined in Roster.
  • Training teams from IS&t and COEUS engaged; Training Plan.
    • Critical Path: Need stable test environment.
  • Usability team engaged; Usability & Accessibility.
  • business-support team engagement, SLA in development: Service Levels Development
  • Stakeholder committee schedule in place, core business users signed up for rolling usability-test plan.

Planning

service operations, primarily from the Business Intelligence development team to Customer Support, Training, and Server & System Administration.

Change Management

  • Enter release date, and other significant dates, on Change Communications Calendar.

    ...

      • Exchange resource name: IS&T: Change Communications
      • When these dates change, communicate to ist-pipeline list.
      • This has not been done in a while, dates have changed a lot.
    • Planned major milestones recorded on wiki home page.
    • Send announcement and change log to ist-pipeline@mit.edu, stakeholder list once release is complete.
    • Update any known open issues (Jira, Request Tracker) affected by release and close.
    • Search http://ist.mit.edu.ezproxyberklee.flo.org and http://kb.mit.edufor any articles that would be invalidated by release and update as needed. Contact istweb@mit.edu if you are not sure how to update this documentation.
    • Contact IS&T Communications for public release announcement.
      • If sending outside of IS&T, send draft release announcement to IS&T communications team at least 2 business days prior to release.
    • Inform ist-pipeline@mit.edu, pipeline of release at least 1 business day prior to release.
    • Consider how to support early adopters or pilot users, phase out current version?
      • Pilot release in May, community release in June. Still no hard transition plan for RAFT I users?

    ...

    • Review need to de-support of previous version(s), communications to current users.
    • Create communication plan, based on stakeholders identified in prior steps.

    ...

    Executing

    ...

    Configuration Management

    • Critical Path: Need stable test environment!
    • Migrating from RAFT I environments to new, clean VMs for RAFT II
      • raft-test in place, needs PHP downgrade?
      • raft-r1, new raft production, does not exist yet.

    ...

      • Await decision on budget for drupal-based online help systems. bi-help-dev installed on temporary system so documenation staff can begin work.
    • Update datacenter SLAs with technical, financial, business contact information.

    Release and Deployment Management

    ...

      • OLA between business-support and Business Intelligence team.

    ...

    • Code management/versioning and continuous integration plan with release engineer. Deploy from Bamboo or directly from SVN.

    Evaluation and Testing

    • See "evaluators" list at right. Responsible parties for internal evaluation. Must sign off. Second architecture review still required by this group.
    • Input and sign-off by Usability Team: Usability & Accessibility Reports.
      • Stakeholder committee schedule in place, core business users signed up for rolling usability-test plan.
    • BI Team to provide smoke-test/system health page for Customer Support?
      • business-help and business-intelligence teams to perform smoke tests for every patch or update during burn-in period (six week from go-live).

    Knowledge Management

    • Training Plan
      • Training mutual venture of SE Training team and COUES Training team.
      • Training curriculum, work with Training to ramp-up Help Desk (business-support).

    ...

    • Online Help: SE Training, Mark Wiklund.
      • are we still doing this?
    • Develop RAFT escalation scripts from Tier 2 (business-support) and Tier 3 (raft-support). Support Escalations Outline

    ...

    Monitor and Control

    • If actual dates do not match previously expected dates, update calendar.
    • business-help and business-intelligence teams to perform smoke tests for every patch or update during burn-in period.
    • If sending outside of IS&T, send draft release announcement to IS&T communications team at least 2 business days prior to release.
    • Inform release-core@mit.edu, pipeline of release at least 1 business day prior to release.
    • Release (Send announcement, deploy final production release, etc.)
    • Second architecture review required, same reviewers, after May pilot release.
    • Revise smoke tests and escalations as needed.

    Closing

    ...

    Column
    Panel
    borderColorblue
    borderWidth1
    titleTransition Teams
    borderStylesolid

    When in doubt, raft-support@mit.edu.

    Release Team
    Technical Lead, Amon Horne
    Release Coordination, Steve Landry
    Systems Operations, Nathan Thaler
    COEUS Integration: Carol Wood

    Evaluation, Internal Acceptance
    Accessibility and Usability: Katherine Wahl
    Database Administration Team: Rob Grenier
    Service Desk: Jessica Donnelly Reed
    Server and Systems Administration: Garry Zacheiss
    Business-user testing team, mitbi-test@mit.edu

    Knowledge Management
    Jessica Donnelly Reed: Service Desk
    Mark Wiklund: Training
    Peggy McGrath: Business Intelligence
    Carole Trainor: COUES Training