Enter information for each commitment item. - Item Number - a sequential number denoting each line.
- Budget Line Item - Associate each entry with a Budget Line Item.
- Current Budget - Displays the current budget.
- Description - editable field for a description.
- Retainage Percent - enter the retainage percent when applicable.
- Amount - the amount of the the commitment line
- Allowance Item - Check if it is an allowance item.
- Custom Fields - used to enter the cost object.
Pay particulate attention to the Retainage percentage as that determines how retainage is calculated when invoices are submitted. A Retainage of five percent should be expressed as 5.00 (as in the example) ![](/confluence/download/attachments/117319849/image2019-7-15%2014%3A18%3A41.png?version=1&modificationDate=1563214721000&api=v2)
The following list of items, though part of the budget template, cannot be used to generate a commitment. You cannot place internal charges on a PO. If you are issuing a PO to cover vendor expenses use the reimbursable line item for that vendor type. For example, for A/E expenses use B-30-125 A/E Reimbursables. Do Not Use list is below: A15-005 | A15-005 DoF Project Administration | A15-010 | A15-010 OCP Project Administration | A15-015 | A15-015 Utilities Project Administration | A15-020 | A15-020 SEG Project Administration | A15-025 | A15-025 EHS Project Administration | A15-035 | A15-035 Service and Support-Staff | A15-045 | A15-045 Employee Benefit Charges (EB) - General | A20-050 | A20-050 Travel Expenses | C50-685 | C50-685 Other MIT Internal Charges | C55-730 | C55-730 Steam | C55-745 | C55-745 Chilled Water | F95-835 | F95-835 EVPT Contingency | F96-840 | F96-840 DoF Contingency |
|