Wiki markup without migration |
---|
h1. Start {toggle-cloak:id=Start}
{cloak:id=My Cloak|visible=true}
Started by the CC Planner, CC Planning Manager, eB Admin, Project Manager, R&M Manager, UTLITIES-Program Manager. They will fill out the required field and take the following action:
Submit
Status of Process: Submitted
Causes Field Validation: Yes
If initiated by CC Planner, process routes to Project Manager Review
If not initiated by CC Planner, process routes to CC Planner Completes PD Form
.
{cloak} |
Started by the CC Planner, CC Planning Manager, eB Admin, Project Manager, R&M Manager, UTLITIES-Program Manager. They will fill out the required field and take the following action: Submit Status of Process: Submitted Causes Field Validation: Yes If initiated by CC Planner, process routes to Project Manager Review- If not initiated by CC Planner,
| process routes to - the next step is CC Planner Completes PD Form.
| CC Planner Completes PD Form Cloak |
---|
- CC Planner reviews the process
| and complete - , completes the required fields
| . One - and selects one of the following actions
| will be taken:- : Submit, Revise or Void.
- If Submit is chosen the next step is Project Manager Review.
- If Void is chosen the next step is Finish. The process is set to a Void status.
|
Project Manager Review Submit Status of Process: Leave Status Unchanged Causes Field Validation: Yes Next Step: Project Manager Review
Revise Status of Process: Leave Status Unchanged Causes Field Validation: Yes Add Comments: Yes, Required Next Step: Initiator Review
Void Status of Process: Void Causes Field Validation: No Add Comments: Yes, Required Next Step: Finish
- Project Manager Review
- Project Manager reviews the process and completes the required fields. They will take one of the following actions:
Submit Status of Process: Leave Status Unchanged Causes Field Validation: Yes Next Step: Cloak |
---|
- The Project Manager reviews the process with the option to approve and Submit or to Revise.
- To approve and submit the project manager must complete the required fields including section 9.1 on the process form by choosing the date.
- If Submit is chosen the next step is
|
- Planning Manager and Prog. Manager Review.
|
Revise Status of Process: Leave Status Unchanged Causes Field Validation: Yes Add Comments: Yes, Required Next Step: CC Planner Revise
- Initiator Review
- Process Initiator reviews the process and completes the required fields. They will take the following action:
Reply Status of Process: Leave Status Unchanged Causes Field Validation: Yes Next Step: CC Planner Completes PD Form
CC Planner Revise- If Revise is chosen the next step is CC Planner Revise.
|
CC Planner Revise Cloak |
---|
- The CC Planner reviews the process
| and Status of Process: Leave Status Unchanged Causes Field Validation: Yes Next Step: - , completes the required fields
| . They will take the following action:Resubmit - , and clicks Resubmit.
- The next step is
|
Planning Manager and Prog. Manager Review Cloak |
---|
- Project Manager and Program Manager review the process
| and Next Step: - , complete the required fields
| . They will take one of the following actions:Submit Status of Process: Leave Status Unchanged Causes Field Validation: Yes Number of Actors Required to Complete: All - and choose to Submit or Revise.
- If Submit is chosen the next step is
|
- Working Committee Review
- IfRevise
|
Status of Process: Leave Status Unchanged Causes Field Validation: Yes Add Comments: Yes, Required Next Step: CC Planner Revise
- Working Committee Review
- CC Planning Manager will review the process with working committee outside of e-Builder then complete the required fields. They will take one of the following actions:
Submit Status of Process: Leave Status Unchanged Causes Field Validation: Yes Number of Actors Required to Complete: All Next Step: Utilities , O&M, and SEG Review
Put on Hold Status of Process: On Hold Causes Field Validation: Yes Add Comments: No Next Step: Finish
- Utilities , O&M, and SEG Review
- Utilities Director, O&M Director, and SEG Assignor will review the process, add their comments and take the following action:
Submit Status of Process: Leave Status Unchanged Causes Field Validation: No Add Comment: No Number of Actors Required to Complete: All Next Step: CC Director, Ops, and M&U Review
CC Director, Ops, and M&U Review- is chosen the next step is CC Planner Revise
| Spawn 3.01a Budget Approval Process Cloak |
---|
- This step initiates a Budget Approval Process.
- The project manager attaches the budget request spreadsheet requesting the Capital Renewal funding.
- Upon the successful spawning of this Budget Approval Process the next step is Project Manager Review.
| Working Committee Review Cloak |
---|
- In this step the The working committee reviews the budget request
- When Submit is chosen the next step is Property Office Review
- If Put on Hold is chosen the next step is Finish.
| Property Office Review Step Cloak |
---|
- In this step the Property Office reviews the information that has been entered to the process. The Property office then indicates whether or not they agree with the funding type. If the Property Office disagrees with the funding type they should select the have made a change to the funding type on the PD option of the Property Office Review field.
- When Submit is chosen the next step is M(ail) M(erge) Property Office.
| Mail Merge (Automation) Property Office Cloak |
---|
- This automation step sends an e-mail to the Property Office showing the information that has been entered into the process.
- When this step completes successfully the next step is R&M, Utilities, FEG, CC Plnng Review.
| R&M, Utilities, FEG, CC Plnng Review Cloak |
---|
- In this step the CC Planner, Utilities Director, R&M Director, and SEG Assignor
| CC Director, M&U Director, and IBO Director will - review the process, add their comments and
| take the following action:- click Submit.
- The next step is Create PD Form
| CC Directr & VP, CSS ReviewSubmit Status of Process: Leave Status Unchanged Causes Field Validation: No Add Comment: No Number of Actors Required to Complete: All Next Step: CRSP Screening Review
- DoF Planning Manager (Governance)
- CC Planning Manager will review the process, add their comments, prepare the Capital Renewal List for the RCRSP agenda, and take the following action:
Submit Status of Process: Leave Status Unchanged Causes Field Validation: No Add Comment: No Next Step: Spawn Team Assignment
Spawn Team Assignments Cloak |
---|
- In this step the information entered is reviewed by by the CC Director, and the VP, CSS Director.
|
- When the Submit action is taken
| from DoF Planning Manager step, the process will proceed to this spawn step. In the spawn step the 02.01 – Team Assignment process will be started and moved to the first step of that workflow. The following action will be automatically be taken after:Spawn Complete Spawn Process: 02.01 – Team Assignment Spawn Process Initiator: Automatically Spawned Attach Process: Yes Copy Attached Files: Yes Next Step: Finance Office Issues IO Number
- Finance Officer Issues IO Number
- Financial Officer will review the process, add the Cost Object Number, and take the following action:
Submit Status of Process: Leave Status Unchanged Causes Field Validation: Yes Add Comment: No Next Step: Apply Funding
- Apply Funding
- Financial Analyst will review the process, apply funding, and take the following action:
Submit Status of Process: Approved Causes Field Validation: Yes Add Comment: No Next Step: Finish
- Finish
|