Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Comment: Migration of unmigrated content due to installation of a new plugin

Result or Product of this Process

Round Rectangle
bgcolor#e6f2ff
width100%

The 04.01 Bidding process allows the Project Manager to manage the bid for the entire bid process including:

  • Bid List approval
  • Release to bid
  • Bid award recommendation.

Process Details

Composition Setup
 
This process includes Bid

is used for Bid List Approval, Release to Bid and Bid Award Recommendation including these specific steps.

  • Obtain an approved list of bidders
  • Prepare and gain approval of the bid package documents including the proposed sample contract provided by the Contract Admin
  • Secure approval to release the bid
  • Recommend an award supported by the bid tabulation in the Bidding module.
  • Gain approval to use a pre-priced agreement to award certain types of work to selected vendors.
  • Create the Selection of Source form and have it reviewed and approved by the Vendor Manager
  • Following approval, award the bid.
  • Ensure that the awarded bidder is properly set up in e-Builder and SAP

Note that the Bidding process is used to inform internal actors about the bid and gain approval to proceed through the bidding stages, from Bid List approval to award. The Bid module is used to construct and publish the bid to the Bidders portal and to initiate your Contract and Purchase order request.

Deck of Cards
idBid
Card
labelSummary

Process Details

Deck of Cards
idBid
Card
labelSummary

The Bidding process and the Bidding module are both used to complete a bid and issue an award.

Card
labelProcess Map

Image Added

Card
labelStep Descriptions

To make the Step descriptions for Bidding easier to read they have been separated into the three parts (tabs). 

Deck of Cards
idSDBid
historyfalse
Card
labelBid List Approval

Toggle Cloak
Start

Cloak
  • The Bidding process is usually initiated by the Project Manager.
  • Depending on the project the initiator completes the required sections of the page.
    • Contract Management
    • Pre-Priced Agreement for Office/CR/Lab
    • Sole Source
    • Potential Bidders - When adding potential bidders you should add contact information for each bidder prior to submitting for Vendor Manager review. If that information is not provided the process will be returned to your court for the Initiator Revise step
  • When finished, take the Submit action.
  • The next step is Furniture or AV Bid?

Toggle Cloak
Furniture?

Cloak
  • Based on the process initiator's answer to the "Is this a furniture or AV bid?" question the process is routed.
  • If True (Yes) the next step is Bid Doc Preparation
  • If False (No) the next step is AV?

Toggle Cloak
AV?

Cloak
  • Based on the process initiator's answer to the "Is this a furniture or AV bid?" question the process is routed.
  • If True (Yes) the next step is Vendor Mgr Reviews A/V Bid
  • If False (No) the next step is Sole Source?

Toggle Cloak
Vendor Mgr Reviews A/V Bid

Cloak
  • In this step the Vendor Manager reviews the Bid information. The process reaches this step for A/V Bids.
  • If the Submit action is taken the next step is Program Manager Reviews.
  • If the Revise action is taken he next step is Initiator Review.

Toggle Cloak
Vendor Mgr Reviews Prop Bid List

Cloak
  • The Vendor Manager reviews the proposed bid list.
  • If approved the Vendor Manager takes the Submit action. The next step is Prepriced Agmt?
  • If the Revise action is taken he next step is Initiator Review.

Toggle Cloak
Prepriced Agmt?

Cloak
  • The system evaluates this conditional to determine if this is a Pre-priced agreement. Using a pre-priced agreement bypasses the process steps which generate an Approved Bid List.
  • If the use of a pre-priced agreement is approved, the work is awarded to a vendor who has previously bid for for work of a certain scope/complexity in order to be considered for that work in the future.
  • If Pre-priced Agreement is True (Yes) the next step is CA Approved Contract Type.
  • If it is False (No) the next step is Program Manager Review.

Toggle Cloak
Sole Source?

Cloak
  • The system evaluates this conditional to determine if this is a Sole Sourced agreement. Using a Sole Sourced agreement bypasses the process steps which generate an Approved Bid List.
  • If the use of a Sole Source agreement is approved, an explanation must be provided.
  • If this conditional evaluates to True (Yes) the next step is Vendor Reccomendation.
  • If this conditional evaluates to False (No) the next step is Vendor Mgr Reviews Prop Bid List.

Toggle Cloak
Initiator Revise

Cloak
  • Initiator Revise is used to request that the initiator correct an error or add more information to a prior step.
  • The Initiator reviews the process and the comments made by the reviewer and makes adjustments as required. The Action options for the initiator are To Vendor Manager, To Program Manager or Void.
  • If To Vendor Manager is chosen the next step is Vendor Mgr Reviews Prop Bid List.
  • If To Program Manager is chosen the next step is Program Manager Review.
  • If Void is chosen the next step is Finish.

Toggle Cloak
Program Manager Reviews

Cloak
  • The Program Manager reads the comments and reviews the process fields and has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is Campus Construction?
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
Campus Construction?

Cloak
  • e-Builder uses information previously entered about the project to determine if this is a Campus Construction project.
  • If Yes the next step is SP&T Program?
  • If No the next step is OCP?

Toggle Cloak
SP&T Program?

Cloak
  • e-Builder uses information previously entered about the project to determine if this is an SP&T Program
Card
labelProcess Map

 

Card
labelStep Descriptions

Step descriptions for Bidding have been separated into the three discrete parts below. While Bidding is one process, the supporting documentation is made easier to read by making this division.

This is a draft. Once the process is finalized I will add step numbers. I also plan to add links to Bidding Module documentation and instruction where necessary.

Deck of Cards
idSDBid
historyfalse
Card
labelBid List Approval

Toggle Cloak
Start

Cloak
  • The Bidding process is started by the Project Manager, OCP Planner, SPT Lead, SPT Commissioning Lead or VPF Strategic Sourcing. Regardless of who initiates the process the final step is Submit.
  • The next step is A133 Been Signed?

Toggle Cloak
Furniture or AV Bid? (Decisional Step)

Cloak
  • The data field "Is this a furniture or AV bid" is evaluated.
  • If True (Yes) the next step is PM Prepares Bid Documents.
  • If False (No) the next step is Vendor Manager Review.

Toggle Cloak
A133 Been Signed? (Decisional Step)

Cloak
  • The data field "Has the A133 Been Signed?" is evaluated.
  • If True (Yes) the next step is PM Prepares Bid Documents SPT Director Review.
  • If False (No) the next step is Vendor Manager CC Director Review.

Toggle Cloak
Vendor Manager SPT Director Review

Cloak
  • The Vendor Manager completes the required SPT Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
  • If Submit is chosen the next step is Program Manager Reviews CC Director Review.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
Initiator ReviseCC Director Review

Cloak
  • The initiator CC Director reads the comments and reviews the process adds comments and makes adjustments as necessary. The options for the indicator are To Vendor Manager, To Program Manager or Void.
  • If To Vendor Manager is chosen the next step is Vendor Manager Review.
  • fields and has the option to take an action to Submit or Revise.
  • If Submit If To Program Manager is chosen the next step is Program Manager Review. Approved Bid List
  • If Void Revise is chosen the next step is Finish Initiator Revise.
 

Toggle Cloak
Program Manager ReviewOCP?

Cloak
  • The Program Manager reads the comments and reviews the process fields. The Program Manager has options to Submit or Revise.
  • If Submit is chosen the next step is Sole Source?
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
Sole Source? (Decisional Step)

  • e-Builder evaluates information previously entered about the project to determine if this is an OCP Program.
  • If True (Yes) the next step is OCP Director Review.
  • If False (No) the next step is M&U?

Toggle Cloak
OCP Director Review

Cloak
  • The OCP Director reads the comments and reviews the process fields. The OCP Director has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List
  • If Revise is chosen the next step is Initiator Revise
Cloak
  • The data field "Sole Source?" is evaluated.
  • If True (Yes) the next step is VPF Procurement Reviews Bid Package
  • If False (No) the next step is Campus Construction?.

Toggle Cloak
Campus Construction? (Decisional Step)M&U?

Cloak
  • e-Builder evaluates information previously entered about the project to
Cloak
  • Multiple fields are evaluated to determine if this is a Campus Construction project.an M&U program?
  • If Yes the next step is SP&T Utilities Program?
  • If No the next step is OCPCampus Services?
 

Toggle Cloak
SP&T Utilities Program? (Decisional Step)

Cloak
  • Multiple fields are evaluated to e-Builder evaluates information previously entered about the project to determine if this is an SP&T a Utilities Program.
  • If True (Yes) the next step is VPF Strategic Sourcing Utilities Director Review.
  • If False (No) the next step is Projects Director Review. SEG Program?

Toggle Cloak
SPT Utilities Director Review

Cloak
  • The SPT Utilities Director reads the comments and reviews the process fields and . The Utilities Director has the option to take an Action to Submit or Revise.
  • If Submit is chosen the next step is CC M&U Director Review.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
Projects Director ReviewSEG Program?

Cloak
  • e-Builder evaluates information previously entered about the project  to determine if this is an SEG Program.
  • If True (Yes)
Cloak
  • The Projects Director reads the comments and reviews the process fields and has the option to Submit or Revise.
  • If Submit is chosen the next step is CC SEG Director Review.
  • If Revise is chosen False (No) the next step is Initiator Revise. O&M Director Review?

Toggle Cloak
CC SEG Director Review

Cloak
  • The CC SEG Director reads the comments and reviews the process fields and . The SEG Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List (The bid list is approved and Mail Merge creates the bid list) is chosen the next step is M&U Director Review.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
OCP? (Decisional Step)O&M Director Review

Cloak
  • The O&M Director reads the comments and reviews the process fields. The O&M Director has the option to Submit or Revise.
  • If Submit is chosen
  • Multiple fields are evaluated to determine if this is an OCP Program.
  • If True (Yes) the next step is OCP M&U Director Review.
  • If False (No) Revise is chosen the next step is M&U? Initiator Revise.

Toggle Cloak
OCP M&U Director Review

Cloak
The OCP
  • The M&U Director reads the comments and reviews the process fields.
The OCP
  • The M&U Director has
options
  • the option to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid
List (The bid list is approved and Mail Merge creates the bid list)
  • List
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
M&U? (Decisional Step)Campus Services?

Cloak
  • e-Builder evaluates information previously entered about the project
Cloak
  • Multiple fields are evaluated to determine if this is an M&U program? Campus Services Program.
  • If True (Yes) the next step is Utilities Program? CS Director Review.
  • If False (No) the next step is Campus Services? IBO Director Review

Toggle Cloak
Utilities Program? (Decisional Step)CS Director Review

Cloak
  • The CS Director reads the comments and reviews the process fields. The CS Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List
  • If Revise is chosen the next step is Initiator Revise.
  • Multiple fields are evaluated to determine if this is a Utilities Program.
  • If True (Yes) the next step is Utilities Director Review.
  • If False (No) the next step is SEG Program?

Toggle Cloak
Utilities IBO Director Review

Cloak
  • The Utilities IBO Director reads the comments and reviews the process fields. The Utilities IBO Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
Initiator Revise

Cloak
  • The initiator revises the process and adds comments if necessary. The initiator Submits when finished with revisions.
  • If the Submit action is taken the next step is Sole Source?
  • If Void is chosen the next step is M&U Director Review.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
SEG Program? (Decisional Step)

Cloak
  • Multiple fields are evaluated to determine if this is an SEG Program.
  • If True (Yes) the next step is SEG Director Review.
  • If False (No) the next step is O&M Director Review?

Toggle Cloak
SEG Director Review

Cloak
  • The SEG Director reads the comments and reviews the process fields. The SEG Director has the option to Submit or Revise.
  • If Submit is chosen the next step is M&U Director Review.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
O&M Director Review

Cloak
  • The O&M Director reads the comments and reviews the process fields. The O&M Director has the option to Submit or Revise.
  • If Submit is chosen the next step is M&U Director Review.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
Campus Services? (Decisional Step)

Cloak
  • Multiple fields are evaluated to determine if this is an Campus Services Program.
  • If True (Yes) the next step is CS Director Review.
  • If False (No) the next step is IBO Director Review?

Toggle Cloak
CS Director Review

Cloak

 

  • The CS Director reads the comments and reviews the process fields. The CS Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List (Mail Merge). (The bid list is approved and Mail Merge creates the bid list.)
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
IBO Director Review

Cloak
  • The IBO Director reads the comments and reviews the process fields. The IBO Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Approved Bid List (Mail Merge). (The bid list is approved and Mail Merge creates the bid list.)
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
Initiator Revise

Cloak
  • The initiator revises the process and adds comments if necessary. The initiator Submits when finished with revisions.
  • The next step is Sole Source?

Toggle Cloak
VPF Procurement Reviews Bid Package

Cloak
  • The VPF/Treasury reads the comments and reviews the process fields. The following are the possible actions.
  • If Submit is chosen the next step is Campus Construction.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
Approved Bid List (Automatic Step)

Cloak
  • Automatic step generates the Approved Bid List document.
  • The next step is Initiator Prepares Bid Documents.
Card
labelRelease to Bid
  • is Finish.

Toggle Cloak
Approved Bid List

Cloak
  • This step generates the Approved Bid List document from a template
  • The bid list document is placed into the Documents\05 Procurement\0505 Bid Lists (I) folder
  • The next step is CA Apprv Contract Type.
Card
labelDocuments, Contract Approval, Release Bid

Toggle Cloak
CA Apprv Contract Type

Cloak
  • The Contract Admin either approves or changes the contract type or approves the Pre-priced agreement and adds the contract number for that agreement to the process.
  • The Contract Admin takes the Approved action to approve. The next step is Approved Pre-Price.
  • The Contract Admin takes the Changed action when changing the contract type, and adds comments to indicate to the PM that the contract has been changed and the reasons for the change.
  • The next step is Bid Doc Preparation.

Toggle Cloak
Approved Pre-Price Agreement

Cloak
  • This is a conditional step. If True (a Pre-priced agreement) the next step is the Merge/Code step that creates the Selection of Source form document.
  • If False the next step is Bid Document Preparation.

Toggle Cloak
PrePriced SoS

Cloak
  • e-Builder generates the Selection of Source for Pre-priced agreements.
  • The next step is Vendor Manager Review of SoS.

Toggle Cloak
Bid Document Preparation

Cloak
  • The process initiator, usually the Project Manager, prepares/uploads the bid documents and completes the required fields. The Submit action is taken when finished.
  • The next step is Contract Admin Assembles Bid Package

Toggle Cloak
Contract Admin Assembles Bid Package

Cloak
  • The Contract Admin assembles the bid package and when finished takes the Submit action.
  • As part of this process the Contract Admin adds a contract sample and assigns a contract number.

  • The next step is Hold for Bids/Proposals Received.

Toggle Cloak
Hold for Bids/Proposals Received

Cloak

The bid should be released in the Bid module when the process reaches this step.

  • Hold the process in this step from bid release until all bids are received and the bid tab has been opened and analyzed. This may be held for one to several weeks while the bid is open.
  • Once the bids have been analyzed and a vendor recommendation is ready the Project Manager takes the Submit action.
  • The next step is Vendor Recommendation.
Card
labelBid Award Recommendation

Toggle Cloak
Vendor Recommendation

Cloak
  • The Project Manager, having received all the bids and supporting documents, performs the analysis and selects a vendor.
  • The process step form is completed and the Submit action is taken.
  • The next step is Selection of Source.

Toggle Cloak
Selection of Source

Cloak
  • This is an automatic step to generate the Selection of Source document. The Selection of Source template is applied.
  • The next step is Vendor Manager Review of SoS.

Toggle Cloak
Vendor Manager Review of SoS

Cloak
  • The Vendor Manager reviews the selection and has the option to take the Action to Submit or Revise
  • If Submit is chosen the next step is Program Manager Review
  • If Revise is chosen the next step is Vendor Recommendation.

Toggle Cloak
Program Manager Review

Cloak
  • The Program Manager reads the comments and reviews the process fields. The program manager has the option to take an Action to Submit or Revise.

Toggle Cloak
Initiator Prepares Bid Documents

Cloak
  • The initiator prepares the bid documents, completes the required fields and Submits when finished.
  • The next step is DOF Procurement Assembles Bid Package.

Toggle Cloak
Has A133 Been Signed? (Decisional Step)

Cloak
  • The data field "Has the A133 been signed?" is evaluated.
  • If True (Yes) the next step is Program Manager Reviews Package.
  • If False (No) the next step is DoF Procurement Assembles Bid Package.

Toggle Cloak
DoF Procurement Assembles Bid Package

Cloak
  • The DOF Procurement reads the comments and reviews the process fields DoF Procurement may Submit or Revise
  • If Submit is chosen the next step is Projects Director Reviews Package Campus Construction.
  • If Revise is chosen the next step is PM Prepares Bid Documents Initiator Revise Recommendation.

Toggle Cloak
Program Manager Reviews PackageInitiator Revise Recommendation

Cloak
  • The program manager reads the comments and reviews the process fields. The program manager Initiator reviews the process and adds comments and makes adjustments as necessary. The initiator has the option to Submit or Revise Void.
  • If Submit is chosen the next step is DoF Procurement Assembles Bid Package Selection of Source.
  • If Revise Void is chosen the next step is PM Prepares Bid Documents Finish.

Toggle Cloak
Projects Director Reviews PackageCampus Construction?

Cloak
  • e-Builder uses information previously entered to to determine "ownership" of the program.
  • If True (Yes) the next step is SP&T Program.
  • If False (No) the next step is M&U
Cloak
  • The Projects Director reads the comments and reviews the process fields The Projects Director may Submit of Revise.
  • If Submit is chosen the next step is Release to Bid (Mail Merge).
  • If Revise is chosen the next step is PM Prepares Bid Documents.

Toggle Cloak
Initiator Releases BidSP&T Program?

Cloak
  • The initiator completes the required process fields, Submits and uses the e-Builder Bidding module to send the bids to the approved bid list.
  • The next step is Initiator Recommends Vendor.
Card
labelBid Award Recommendation
  • "Contract managed by a different program" field is evaluated.
  • If True (Yes) the next step is SPT Director Review.
  • If False (No) the next step is Vendor Manager Review of SoS

Toggle Cloak
SPT Director Review

Cloak
  • The SPT Director reads the comments and reviews the process fields. The SPT Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Vendor Manager Review of SoS.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
M&U2?

Cloak
  • e-Builder uses information previously entered to determine "ownership" of the program.
  • If True (Yes) the next step is Utilities Program?
  • If False (No) the next step is Campus Services?

Toggle Cloak
Utilities Program?

Cloak
  • e-Builder uses information previously entered to determine "ownership" of the program.
  • If True (Yes) the next step is Utilities Director Review.
  • If False (No) the next step is SEG Program?.

Toggle Cloak
Utilities Director Review Rec

Cloak
  • The utilities director reads the comments and reviews the process fields. The utilities director has the option to Submit or Revise

Toggle Cloak
Initiator Recommend Vendor

Cloak
  • The initiator receives all the bid documents, reviews them, and selects a vendor for recommendation. All project managers on the project receive a notification when this step is reached. They will fill out the required fields and Submit.
  • The next step is Selection of Source.

Toggle Cloak
Selection of Source (Automatic Step)

Cloak
  • This is an automatic step to generate the Selection of Source document. The Selection of Source template is applied.
  • The next step is Program Manager Review.

Toggle Cloak
Program Manager Review

Cloak
  • The program manager reads the comments and reviews the process fields. The program manager has the option to Submit or Revise.
  • If Submit is chosen the next step is Campus Construction.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
Initiator Revise

Cloak
  • The initiator reviews the process and adds comments and makes adjustments as necessary. The initiator has the option to Submit or Void.
    If Submit is chosen the next step is Selection of Sourceis M&U Director Review Rec.
  • If Void Revise is chosen the next step is Finish Initiator Revise Recommendation.

Toggle Cloak
Campus Construction (Decisional Step)SEG Program?

Cloak
  • Multiple fields are evaluated to determine "ownership of the program"e-Builder uses information previously entered to determine if this is an SEG Program.
  • If True (Yes) the next nest step is SP&T Program. SEG Director Review Rec
  • If False (No) the next step is M&U.
 
  • O&M Director Review Rec

Toggle Cloak
SP&T Program? (Decisional Step)SEG Director Review Rec

Cloak
  • The SEG Director reads the comments and reviews the process fields. The SEG Director has the option to take an Action to Submit or Revise.
  • If Submit is chosen
  • The "Contract managed by a different program" field is evaluated.
  • If True (Yes) the next step is VPF Strategic Sourcing Review Vendor Manager Review of SoS.
  • If False (No) Revise is chosen the next step is Project Director Review Initiator Revise Recommendation.

Toggle Cloak
SPT O&M Director Review Rec

Cloak
  • The SPT O&M Director reads the comments and reviews the process fields. The SPT Director DoF Procurement has the option to Submit or Revise.
  • If Submit is chosen the next step is DoF Procurement Vendor Manager Review of SoS.
  • If Revise is chosen the next step is Initiator Revise Recommendation.

Toggle Cloak
Projects CC Director Review

Cloak
  • The projects director CC Director reads the comments and reviews the process fields. The Projects CC Director has the option to Submit or Revise.
  • If Submit is chosen the next step is DoF Procurement Review Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise Recommendation.
 

Toggle Cloak
M&U (Decisional Step)OCP?

Cloak
  • Multiple fields are evaluated to determine ownership of the programif this is an OCP Program.
  • If True (Yes) the next step is Utilities Program? OCP Director Review.
  • If False (No) the next step is DoF Procurement Review.
 
  • M&U?.

Toggle Cloak
Utilities Program (Decisional Step)OCP Director Review

Cloak
  • The OCP Director reads the comments and reviews the process fields. OCP Director has the option to Submit or Revise.
  • If Submit is chosen the next step is Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise Recommendation
  • Multiple fields are evaluated to determine "ownership of the program".
  • If True (Yes) the next step is Utilities Director Review.
  • If False (No) the next step is SEG Program?.

Toggle Cloak
Utilities M&U Director Review Rec

Cloak
  • The utilities director M&U Director reads the comments and reviews the process fields . The utilities director and has the option to Submit or Revise.
  • If Submit is chosen the next step is DoF Procurement Review. Initiator Awards Bid
  • If Revise is chosen the next step is Initiator Review.

Toggle Cloak
SEG Program

Cloak
  • Multiple fields are evaluated to determine if this is an SEG Program.
  • If True (Yes) the nest step is SEG Director ReviewIf False (No) the next step is O&M Director Review Initiator Revise Recommendation.

Toggle Cloak
SEG Director ReviewCampus Services?

Cloak
  • Multiple fields are evaluated to determine if this is an Campus Services program?
  • If True (Yes)
  • The SEG Director reads the comments and reviews the process fields. The SEG Director has the option to Submit or Revise.
  • If Submit is chosen the next step is DoF Procurement CS Director Review.
  • If Revise is chosen False (No) the next step is Initiator Revise IBO Director Review.

Toggle Cloak
O&M CS Director Review

 
Cloak
  • The O&M Campus Services Director reads the comments and reviews the process fields. DoF Procurement The CC Director has the option to Submit or Revise.
  • If Submit is chosen the next step is DoF Procurement Review Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
DoF Procurement IBO Director Review

Cloak

 

  • DoF Procurement The IBO Director reads the comments and reviews the process fields. The O&M IBO Director has the option to Submit or Revise.
  • If Submit is chosen the next step is A133 Been Signed? Initiator Awards Bid.
  • If Revise is chosen the next step is Initiator Revise.

Toggle Cloak
A133 Been Signed? (Decisional Step}Initiator Award Bid

Cloak
  • The data field "Has the A133 Been Signed" is evaluated.
  • If True (Yes) the next step is Campus Construction.
  • If False (No) the next step is >10M

Toggle Cloak
>10M (Decisional Step)

Cloak
  • The data field ">10M" is evaluated.
  • If True (Yes) the next step is VPF Procurement Review.
  • If False (No) the next step is One Bid?

Toggle Cloak
One Bid? (Decisional Step)

Cloak

 

  • The data field Reason Vendor Selected is evaluated to determine If the reason selected is "2.5 Multiple Bidders Selected - Only One Bidder Responded".
  • If True the next step is VPF Procurement Review.
  • If False the next step is Lowest Bid?

Toggle Cloak
Lowest Bid? (Decisional Step)

Cloak
  • The data field Reason Vendor Selected is evaluated to determine if the reason selected is "2.2 Adequate price competition (at least 2 quotes): Lowest Bidder Selected. No further explanation required.".
  • If True the next step is Campus Construction.
  • If False the next step is VPF Procurement Review.

Toggle Cloak
VPF Procurement Review

Cloak
  • The VPF/Treasury reads the comments and reviews the process fields. The VPF/Treasury has the option to Submit or Revise.
  • If Submit is chosen the next step is Campus Construction.
  • If Revise is chosen the next step is DoF Procurement Review.

Toggle Cloak
Campus Construction (Decisional Step)

Cloak
  • Multiple fields are evaluated to determine if this is a Campus Construction program.
  • If True (Yes) the next step is CC Director Review.
  • If False (No) the next step is OCP?

 

 

 

  • Initiator reviews the process and awards the bid using the e-Builder Bidding module. The final action when the bid is awarded is to return to the process and take the Submit Action.
  • The next step is Vendor Manager Checks Company Info.

Toggle Cloak
Pre-Priced 3?

Cloak
  • This conditional determines if this process contains a Pre-priced agreement.
  • If True the process moves to Finish.
  • If False the process moves to Vendor Manager Checks Company Info

Toggle Cloak
Vendor Mgr Checks Company Info

Cloak
  • The Vendor Managerchecks and fills out form fields to ensure that:
    • The awarded bidder exists in SAP
    • The company information is correct and current in the Contacts module.
    • If the company is not in SAP that the New Company process has been started.
  • When finished the Vendor Manager takes the Submit action.
  • The next step is Vendor Exists in SAP?

Toggle Cloak
Vendor Exists in SAP?

Cloak
  • This step routes the process to the Finish step if the Vendor exists in SAP.
  • If the Vendor does not exist in SAP the next step is AA Adds New Company.

Toggle Cloak
AA Adds New Company

Cloak
  • If the company does not exist in SAP the AA completes the 01.01 Add New Company/Contact process and holds the process in this step until that has been completed.
  • When completed the AA takes the Vendor Added action.
  • The next step is Vendor Manager Checks Company Info.

Toggle Cloak
Hold for SAP Vendor #

Cloak
  • In this step the Administrative Assistant waits until the Vendor has been assigned a SAP Vendor Number from VPF.
  • If the Submit action is taken the next step is Finish.
  • If the Revise action is taken the next step is AA Adds New Company.

Toggle Cloak
Finish

Cloak