Enter information for each commitment item. - Item Number - a sequential number denoting each line.
- Budget Line Item - Associate each entry with a Budget Line Item.
- Current Budget - Displays the current budget.
- Description - editable field for a description.
- Retainage Percent - enter the retainage percent when applicable.
- Amount - the amount of the the commitment line
- Allowance Item - Check if it is an allowance item.
- Custom Fields - used to enter the cost object.
Pay particulate attention to the Retainage percentage as that determines how retainage is calculated when invoices are submitted. A Retainage of five percent should be expressed as 5.00 (as in the example) Image Added
The following list of items, though part of the budget template, cannot be used to generate a commitment. You cannot place internal charges on a PO. If you are issuing a PO to cover vendor expenses use the reimbursable line item for that vendor type. For example, for A/E expenses use B-30-125 A/E Reimbursables. Do Not Use list is below: A15-005 | A15-005 DoF Project Administration | A15-010 | A15-010 OCP Project Administration | A15-015 | A15-015 Utilities Project Administration | A15-020 | A15-020 SEG Project Administration | A15-025 | A15-025 EHS Project Administration | A15-035 | A15-035 Service and Support-Staff | A15-045 | A15-045 Employee Benefit Charges (EB) - General | A20-050 | A20-050 Travel Expenses | C50-685 | C50-685 Other MIT Internal Charges | C55-730 | C55-730 Steam | C55-745 | C55-745 Chilled Water | F95-835 | F95-835 EVPT Contingency | F96-840 | F96-840 DoF Contingency |