Process Start (By Project Manager) Cloak |
---|
- The Project Manager fills out the required fields and
takes the following action:Submit - Status of Process: Submitted
- Makes data field assignments
- Next Step: Return Funds?
| Return Funds? (Decision Step)- clicks Submit.
- The next step is Systems Renwal?
| Systems Renewal Cloak |
---|
- The system determines if this process is for Systems Renewal based on the project manager's response to the question "Requesting Add'l Capital Renewal funds?"
- If it is for Systems Renewal the next step is CC Planner Review
- If it is not for Systems Renewal the next step is Return Funds?
|
CC Planner Review Cloak |
---|
- The CC Planner reviews the process, completes any required fields and chooses one of these actions;
- To CC Planning Manager
- To PM for Revision
- If To CC Planning Manager is chosen the next step is CC Planning Manager Review.
- If To PM is chosen the next step is Initiator Revise.
| CC Planning Manager Review Cloak |
---|
- The Planning Manager reviews and may edit the process When finished the only option is to send the process back to the CC Planner
|
CC Planning Dir Review Cloak |
---|
- The CC Planning Director reviews the request and has the option to Submit if approved or ask the CC Planning Mgr for revisions.
|
Initiator Revises Cloak |
---|
- From the CC planner Review step the CC Planner can request that the project manager revise the request. Once revised, the PM can resubmit the request to the CC planner.
|
Return Funds? Cloak |
---|
Cloak |
---|
Decisional: Return funds to program? True- Status of Process: Unchanged
- Next Step: Program Manager Review A
FalseStatus of Process: UnchangedNext Step: - Return funds is a decision step.
- If funds are being returned to the program the next step is Program Manager Review A
- If funds are not being returned to the program the next step is
| Program Manager Review A Cloak |
---|
- The Program Manager reviews the process
and - , adds comments if necessary
. When finished one of the following actions are taken:- and when finished chooses to Submit or to Revise.
- If Submit is chosen the next step isCC Director Review.
- If Revise is chosen the next step is Initiator Revise and Submit.
| CC Director Review Cloak |
---|
SubmitStatus of Process: UnchangedNext Step: - The CC Director reviews the form and has the option to Submit or Revise.
- If Submit is chosen the next step is
Status of Process: UnchangedAdd Comments: YesRequire Comments: YesData Field Assignments: N/ANext Step: Initiator Revise and Submit- Financial Analyst Adjusts Funding.
Revise- If Revise is chosen the next step is Initiator Revise and Resubmit.
|
Initiator Revise and Submit Cloak |
---|
reads - reads the comments, reviews process fields and updates as necessary
. When finished takes one of the following actions:Resubmit- Status of Process: Unchanged
- Data Field Assignments are made
- Next Step: Return Funds
VoidStatus of Process: VoidAdd Comments: YesComments Required: YesData Field Assignments: N/ANext Step: Finish- and when finished chooses to Resubmit or to Void.
- Resubmit is chosen the next step is Return Funds
- If Void is chosen the next step is Finish
|
Governance Review
Cloak |
---|
- The Budget Planning Manager reviews process fields and updates the funding data as necessary and when finished chooses Submit.
|
Financial Analyst Adjusts Funding Cloak |
---|
- The Financial Analyst reads the comments, adjusts the funding and then
takes the following action:Submit - clicks Submit.
- The next step is True-Up Form/Addl, a mail merge step that creates the True-Up form.
- Once the mail merge is completed the process is Code Complete and goes to the Finish step.
| True Up Form Cloak |
---|
Status of Process: UnchangedData Field Assignments: N/ANext Step: - Automatic Step to generate the True Up form document
- The next step is
| Program Manager Review B Review Cloak |
---|
- The Program Manager reads the comments
and - , reviews the process fields and
takes one of the below actions:SubmitStatus of Process: UnchangedData Field Assignments: N/ANext Step: - chooses to Submit or Revise.
- If Submit is chosen the next step is
Status of Process: UnchangedAdd Comments: YesRequire Comments: YesData Field Assignments: N/ANext Step: Revise- If Revise is chosen the next step is PM Reviews Com Initiator Revise and Resubmit
| CC Project? (Decision Step) Cloak |
---|
This is decisional eStatus of Process: UnchangedNext Step: - e-Builder evaluates the Project Type to determine if the value is "Capital Renewal"
True- If True the next step isProject Director Review
FalseStatus of Process: UnchangedNext Step: - If Falsethe next step is M&U Project?
| M&U Project? (Decision Step) Cloak |
---|
is decisionalStatus of Process: Unchanged Next Step: - . e-Builder evaluates the Project Type to determine if the value is "Utilities".
True- If True the next step is M&U Director Review
FalseStatus of Process: UnchangedNext Step: - If False the next step is OCP Project?
| OCP? (Decision Step) Cloak |
---|
decisionalNext Step: - a decision step. e-Builder evaluates the Project Type to determine if the value is "OCP"
TrueStatus of Process: UnchangedStatus of Process; UnchangedNext Step: - If True the next step is OCP Director Review
False- If False the next step is Director of Housing Review
| Campus Services? Cloak |
---|
- This step is a decision step. e-Builder evaluates the Project Type to determine if the value is "Campus Services"
- If True the next step is Campus Services Director.
- If False the next step is Dir of Fin & Adm Review
| Dir of Fin & Adm Review Cloak |
---|
Project - Director of Finance and Administration reads the comments and review the process fields and
takes the below action:Submit Status of Process: UnchangedData Field Assignments: N/A- has the option to Submit, Revise, or Send to CC Director.
- If Submit is chosen the next step is VP, CSS Executes.
- If Revise is chosen the next step is Initiator Revise and Resubmit.
- If Send to CC Director is chosen the next step is CC Director Review.
Next Step: CC Director Review |
CC Director ReviewVP, CSS Executes Cloak |
---|
CC - IBO Director reads the comments and
reviews - review the process fields and
takes the below action:Submit Status of Process: UnchangedData Field Assignments: N/A- has the option to Submit, Revise, or Send to CC Director.
- If Submit is chosen the next step is DoF Dept Funding?
- If Revise is chosen the next step is Initiator Revise and Resubmit
- If Send to CC Director is chosen the next step is CC Director Review.
Next Step: Department Funding? | M&U CC Director Review Cloak |
---|
M&U - CC Director reads the comments and
reviews - review the process fields and
takes the below action:Submit - Status of Process: Unchanged
- Data Field Assignments: N/A
- Next Step: Department Funding?
- has the option to Submit or Revise.
- If Submit is chosen the next step is CC Director Review.
- If Send to Dir of Fin and Adm is chosen the next step is Dir of Fin & Adm Review.
- If Send to Utilities Director is chosen the next step is Utilities Director Review.
- If Send to O&M Director is chosen the next step is O&M Director Review.
- If Send to FEG Director is chosen the next step is SEG Director Review.
- If Send to M&U Director is chosen the next step is M&U Director Review.
- If Send to OCP Director is chosen the next step is OCP Director Review.
- If Send to Campus Services Director is chosen the next step is Campus Services Director.
| M&U OCP Director Review Cloak |
---|
OCP the - comments and reviews the process fields and
takes the below action:Submit Status of Process: Leave Status UnchangedCauses Field Validation: YesData Field Assignments: N/ANext Step: - clicks Submit.
- The next step is
| OCP Director of Housing Review Cloak |
---|
of Housing- reads the the comments and reviews the process fields and
takes the below action:Submit Status of Process: UnchangedData Field Assignments: N/ANext Step: - clicks Submit.
- The next step is
| DoF Department Funding? (Decision Step) Cloak |
---|
decisional - decision step. e-Builder evaluates the value of the Department Funding field.
True- Status of Process: Unchanged
- Next Step: Financial Analyst Adds Funding
FalseStatus of Process: UnchangedNext Step: DoF Contingency?- If Yes the next step is Governance Review_2
- If False the next step is DoF Contingency?
| Governance Review_2 Cloak |
---|
- Governance Review reads the comments and reviews the process fields and clicks Approve.
- The next step is True Up Form / Addi
- If the To PM -> Revise action is taken the next step is Initiator Revise & Resubmit.
| DoF Contingency (Decision Step) Cloak |
---|
decisional Status of Process: UnchangedNext Step: - decision step. e-Builder evaluates the value of the Funding Source field.
True- If True the next step is Financial Analyst Adds Funding
FalesStatus of Process: UnchangedNext Step: - If False the next step is EVPT Contingency?
| EVPT Contingency (Decision Step) Cloak |
---|
decisional Status of Process: UnchangedNext Step: - decision step. e-Builder evaluates the value of the Funding Source field.
True- If True the next step is Deputy EVPT Review
FalseStatus of Process: UnchangedNext Step: CRSP/R-CRSP Committee Review- If False the next step is Governance Review_1
| Deputy EVPT Review Cloak |
---|
- The EVPT Office reads the comments and reviews the process fields and
takes the following action:Submit Status of Process: UnchangedData Field Assignments: N/ANext Step: - then clicks Submit.
- The next step is
- Financial Analyst Adds Funding
| CRSP/R-CRSP/Committee ReviewGovernance Review_1 Cloak |
---|
The CRSP Admin - Governance Review reads the comments and reviews the process fields and
takes the following action:Approve Status of Process: UnchangedData Field Assignments: N/ANext Step: - clicks Approve.
- The next step is
| True Up Form (Automatic Step to Generate Document) Cloak |
---|
- Automatic step to generate the true up form document
Mail Merge Template: Default TemplateArchive Mail Merge: YesDestination Folder: Documents \ 19 eB Process Documents \ 03Store in File Field: Budget DocumentSend to Process Initiator: NoEmail Format: HTMLNext Step: 02 Project Budget (Cost)- Financial Analyst Adds Funding
|
Financial Analyst Adds Funding Cloak |
---|
- The financial analyst adds the funding to the project and will compete the required process fields
and take the below action:Funds Applied - Status of Process: Approved
- Data Field Assignments: N/A
- Notify: Process Initiator
- Next Step: Finish
- clicks to add funds.
- The next step is Finish
| Finish Cloak | This is the terminal step for this process. |
---|
|
|