This process allows the professional services vendors to request an amendment to their existing approved commitment. Following approvals, the process generates a signed amendment document.
Composition Setup
The 06.03 - PSA, MDA or PO Release (PSA) process is used for the following:
Master Design Agreement (MDA) Release
Professional Services Amendment (Contract & Purchase Order Agreement)
Purchase Order Release by Phase (no change to contract)
Deck of Cards
id
Deck of Cards
id
PSA
Card
label
Summary
This process can be started by a the vendor or the project manager.the A/E Lead, Administrative Assistant, CC Planner, Consultant, Contractor, OCP Planner, Project Manager and SPT Lead.
This process is used to submit, review and approve the following: Amendments to Commitments (Contracts) & Purchase Orders issues to Professional Services vendors (A/E, Designers, Consultants), Master Design Agreement Release Change Orders, and Phased Purchase Order Releases (under and executed design contract).
Card
label
Process Map
Image Added
Card
label
Process Map
Image Removed
Card
label
Step Descriptions
Toggle Cloak
1. Start
Cloak
The process is started by the Architect Lead who completes The Process Initiator fills out the required fields and takes the Submit actionchooses to submit.
The next step is PSA Mail Merge.is MDA Release?
Toggle Cloak
2. PSA Mail Merge (System Step)Project Status Check
Cloak
The e-Builder system creates a mail merge document using the PSA template and ads it to ...Project Status CheckConditionalchecks if the Project Status is not an Active one.
If True (Yes) the next step is Project Status is Incorrect
If False (No) the next step is MDA Release?The next step is Vendor Signs
Toggle Cloak
3. Vendor SignsProject Status is Incorrect
Cloak
The vendor reviews the generated mail merge document and has the option to take action to Submit or ReviseInitiator holds the project in this step until the project status is updated to an Active one via a. Once the status is updated the I've run a PMUa action should be taken.
If the I've run a PMUa action is taken If Submit is chosen the next step is Project Manager Review
If Revise is chosen the next step is Initiator Revise
Status Check.
Toggle Cloak
4. Project Manager ReviewMDA Release?
Cloak
The Project Manager reviews the process, adds comments if necessary and takes one of the following actions, Submit, Revise or Void
If Submit is chosen the next step is Financial Analyst Adjusts Funding
If Revise is chosen the next step is Initiator Revise
If Void is chosen the next step is Finish,
Toggle Cloak
5. Initiator Revise
Cloak
The Project Manager reads the comments and reviews the process fields and updates as necessary, then takes the Resubmit action.
The next step is Project Manager Review.
Toggle Cloak
6. Additional Funding? (Decisional Step)
Cloak
The Additional Funding Required field is evaluated to determine if the value is Yes.
If the value is Yes (True) then the next step is Spawn Budget Change (03.03).
If the value is No (False) then the next step is Program Manager Reviews.
Toggle Cloak
7. Program Manager Reviews
Cloak
The Program Manager reads the comments, reviews the process fields and has the option to Submit or Revise.
If Submit is chosen the next step is
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
8. Program Type Util? (Decisional Step)
Cloak
This is a decisional step that evaluates the Project Type field to determine if this is a Util Program Type.
If True the next step is Director of Utilities Review.
If False the next step is Director of Projects Review.
Toggle Cloak
9. Director of Utilities Review
Cloak
The Director of Utilities reads the comments and reviews the process fields and has the option to choose between the actions Reviewed and Revise.
If Reviewed is chosen, the next step is DoF Procurement Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
10. Director of Projects Review
Cloak
The Director of Projects reads the comments and reviews the process fields and has the option to choose between the actions Reviewed and Revise.
If Reviewed is chosen, the next step is DoF Procurement Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
11. DoF Procurement Review
MDA Release? Conditionalchecks if Master Design Agreement (MDA) Change Order was selected for the Type of Change field.
If True (Yes) the next step is PM Enters Release
If False (No) the next step is PO Release?
Toggle Cloak
NTP?
Cloak
The NTP? Conditionalchecks if PS NTP was selected for the Type of Change field.
If True (Yes) the next step is PM Enters Prev Exec NTP
The initiator can upload the previous NTP and submit the step to the CAdmn Rev/Drft/New/Exec PS NTP step who will draft the new PS NTP send it back to the initiator for review and once accepted sent back to the contracts team who will send it out for signatures and then move it along to the program manager review step
The PM can choose to Void the process or, change the PSA Type on this step as well. A void goes to the finish step as voided. Change PSA Type sends the process back to the MDA Release? conditional step. This is helpful if the PM has mistakenly chosen an NTP change type but meant a PO CO, for example. This avoids having to start all over again.
A program manager can review the NTP and submit the process or send it back for revisions to the initiator. If the Prgm Mgr sned it back for a revision to the initiator the project manager is notified.
False (No) the next step is PO Release?
Toggle Cloak
PO Release?
Cloak
The PO Release? Conditional checks if Master Design Agreement (MDA) Change Order was selected for the Type of Change field.
If True (Yes) the next step is PO CO MM
If False (No) the next step is A/E Initiated?
Toggle Cloak
A/E Initiated?
Cloak
The A/E Initiated? Conditional checks if the role of the Process Initiator was A/E Lead or Consultant.
If True (Yes) the next step is PSA Mail Merge
If False (No) the next step is PSA MM (for A/E man
Toggle Cloak
PM Enters Release
Cloak
The Project Manager adds the appropriate release from the 05.02.05 MDA Release(s) folder of project 11112, and fills out any required fields
Cloak
The DoF Procurement reads the comments and reviews the process fields and chooses between actions to Submit or Revise.
If Submit is chosen the next step is Contract > $100M?Program Manager Review MDA
If Revise is chosen the next step is Initiator Revise MDA
If Void is chosen the next step is Finish and the process is set to a Void status.
Toggle Cloak
12. Campus Construction? (Decisional Step)
Cloak
Multiple process fields are evaluated to determine if this is a Campus Construction project and to determine the next step.
When True is evaluated the next step is SP&T Program.
When False is determined the next step is OCP?
Toggle Cloak
13. SP&T Program (Decisional Step)
Cloak
Multiple fields are evaluated to determine if this is an SP&T program and to determine the next step.
When True is evaluated the next step is VPF Strategic Sourcing Review.
When False is evaluated the next step is Projects Director Review.
Toggle Cloak
14. VPF Strategic Sourcing Review
Cloak
The VPF Strategic Sourcing reads the comments, reviews the process fields and has the option to take an action to Submit or Revise.
If Submit is chosen the next step is Contract < $10M
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
15. Projects Director Review
Program Manager Review MDA
Cloak
The Program Manager reviews the Master Design Agreement Release details
If Submit is chosen the next step is Vendor Signature
If Revise is chosen the next step is Initiator Revise MDA
Toggle Cloak
Contracts Group
Cloak
The Contract Admin reviews the Master Design Agreement Release details, makes any changes and if necessary re-uploads the document in the PSA/MDA for Signature field.
If Submit is chosen the next step is Program Manager Review MDA
If Revise is chosen the next step is Initiator Revise MDA
If Void is chosen the next step is Finish and the process is set to a Void status.
Toggle Cloak
Initiator Revise MDA
Cloak
The Initiator Revise MDA step allows the Process Initiator to make changes and resubmit the process.
If Resubmit is chosen the next step is MDA Release
If Void is chosen the next step is Finish and the process is set to a Void status.
Toggle Cloak
Initiator Reviews Release
Cloak
The Initiator Reviews Release step allows the Process Initiator to make changes and resubmit the process.
If Submit is chosen the next step is Contracts Sends Release to Vendor
Toggle Cloak
Contracts Sends Release to Vendor
Cloak
The Contracts Sends Release to Vendor step allows the Contracts Admin to make send the release to the vendor.
If Submit is chosen the next step is Vendor Signature.
If
Cloak
The Projects Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
If Submit is chosen the next step is Contract <$10M
If Revise is chosen the next step is Initiator ReviseReviews Release.
Toggle Cloak
16. Contract <$10M (Decisional Step)Utilities PO?
Cloak
The Utilities PO? Conditional step allows the determines if the Program Type is Utilities
Cloak
The date field Project Type is evaluated to determine if it is "Capital Renewal".
If True(Yes) the next step is CC Director Executes Contract.Est Fin cont>$1M
If False(No) the next step is CC Director Review.Campus Construction?
Toggle Cloak
17. CC Director Review Vendor Signature
Cloak
The CC Director reads the comments and reviews the process fields and has the option to take an action to Submit or ReviseConsultant, A/E Lead and/or the Project Manager takes the appropriate action to sign the document.
If Submit is chosen the next step is Contract < $100MProgram Manager Review MDA
If Revise is chosen the next step is Initiator Revise .MDA
Toggle Cloak
18. CC Director ExecutesPO CO MM
Cloak
The CC Director reads the comments and reviews the process and has the option to take an action to Submit or Revise.
If Submit is chosen the next step is Administrative Assistant Final Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
19. Contract <$100M (Decisional Step)
Cloak
The Cost Commitment/Contract Value is evaluated to see if it is < $100,000,000.
If True the next step is Deputy EVP Executes Contract.
If False the next step is Deputy EVP Review.
Toggle Cloak
20. Deputy EVP Executes Contract
Cloak
The Deputy EVP Office reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
If Submit is chosen the next step is Administrative Assistant Final Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
21. Deputy EVP Review
PO CO MM step is a mail merge automation step that completes the Phased Purchase Order Release mail merge document.
The next step is Contracts Reviews PO CO MM
Toggle Cloak
Contracts Reviews the PO CO MM
Cloak
The Contracts Reviews the PO CO MM step allows the Contracts team to review the PO CO for accuracy
If Submit the next step is Init PO Threshold step
If Revise the next step is initiator Revises PO Release step
Toggle Cloak
Init PM Threshold
Cloak
The Init PM Threshold Conditionalchecks if the Change Amount of the PSA reaches the threshold that requires a Contract.
If True (Yes) the next step is PM Attaches Contract/Reviews POCO MM
If False (No) the next step is PM Reviews POCO MM
Toggle Cloak
PM Attaches Contract/ Reviews POCO MM
Cloak
The Project Manager should attach the contract for the work of the PO that the PSA is modifying at this step
Cloak
The Deputy EVP Office will read the comments and review the process fields and has the option to take an action to Submit or Revise.
If Submit is chosen the next step is EVPT Office Executes.PS for CC Director
If ReviseRedo PO CO MM is chosen the next step is Initiator Revise.PO CO MM
Toggle Cloak
22. EVPT Office ExecutesPM Reviews POCO MM
Cloak
The OCP Director reads the comments and reviews the process fields and has the option to take an action to Submit or ReviseProject Manager reviews the POCO MM.
If Submit is chosen the next step is Administrative Assistant Final Review.PS for CC Director
If ReviseRedo PO CO MM is chosen the next step is Initiator Revise.PO CO MM
Toggle Cloak
23. OCP? (Decisional Step)
Cloak
Multiple fields are evaluated to determine if this is an OCP Program.
If True the next step is Contract <$500K.
If False the next step is M&U?
Toggle Cloak
24. Contract <$500K (Decisional Step)
Cloak
The cost commitment/current contract value field is evaluated to determine if it is <$500,000.
If True the next step is OCP Director Review.
If False the next step is OCP Director Executes.
Toggle Cloak
25. OCP Director Review
Cloak
The OCP Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
If Submit is chosen the next step is Contract Value <$100M.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
26. OCP Director Executes
OGC Counsel Reviews
Cloak
In this step the OGC Counsel reviews the information that has been entered to the process.
If Reviewed is chosen the next step is PM Review PSA - Manual Sig Req
If Revise is chosen the next step is Contracts Review PSA MM send from PM
Toggle Cloak
Contracts Review PSA MM send from PM
Cloak
In this step the Contracts Group reviews the information that has been entered to the process.
If Submit is chosen the next step is PM Review PSA - Manual Sig Req
If Revise is chosen the next step is PM Review MM
If Send to OGC is chosen the next step is OGC Council Review
Toggle Cloak
PM Review MM
Cloak
The Project Manager reviews the PSA Mail Merge.
If Submit is chosen the next step is Contracts Review PSA MM send from PM
If Redo MM is chosen the PSA MM is the next step
If Send to PO CO MM is chosen the next step is PO CO MM
If Void is chosen the process goes to finish and is set to a status of Voided
if NTP, POCO or MDA is chosen the process goes back to the Project Status step which allows for the PM to have changed the PSA Type and route it to the correct stream in the workflow process
Toggle Cloak
PS for CC Director
Cloak
This automation step notifies the CC Director of the PO Release.
The next step is Program Manager reviews PO
Toggle Cloak
PM Attaches Contract
Cloak
The Project Manager attaches a copy of the vendor executed contract, and fills out the PM Description of Change (Internal Only) field if necessary.
The next step is Program Manager Reviews PO
Toggle Cloak
Program Manager Reviews PO
Cloak
The Program Manager reviews the Phased Purchase Order Release details.
If Reviewed is chosen the next step is OCP?
If Revise is chosen the next step is Initiator Revise PO Release
Toggle Cloak
OCP?
Cloak
The OCP? Conditional checks if the Program Type of the project is OCP
If True (Yes) the next step is OCP Director Approval
If False (No) the next step is CC Director Approval
Toggle Cloak
CC Director Approval
Cloak
The CC Director takes the appropriate action to approve the document.
If Submit is chosen the next step is SAP Hold Step
If Revise is chosen the next step is Initiator Revise PO Release
Toggle Cloak
OCP Director Approval
Cloak
The OCP Director takes the appropriate action to approve the document.
If Submit is chosen the next step is SAP Hold Step
If Revise is chosen the next step is Initiator Revise PO Release
Toggle Cloak
Initiator Revise PO Release
Cloak
The Initiator RevisePO Release step allows the Process Initiator to make changes and resubmit the process.
If Resubmit is chosen the next step is MDA Release
If Void is chosen the next step is Finish and the process is set to a Void status.
Toggle Cloak
PSA Mail Merge
Cloak
The PSA Mail Merge step is a mail merge automation step that completes the Standard PSA mail merge document.
The next step is Project Manager Review
Toggle Cloak
PSA MM (for A/E man
Cloak
The PSA MM (for A/E man step is a mail merge automation step that completes the Standard PSA mail merge document to be sent to the A/E Lead or Consultant for a manual signature.
The next step is PM Attaches Contract
Toggle Cloak
Project Manager Review
Cloak
The Project Manager reviews the PSA Details and fills out all required fields.
If Submit is chosen the next step is Contracts Group Review PSA
If Revise is chosen the next step is Initiator Revise PSA
Toggle Cloak
Contracts Group Review PSA
Cloak
The Contract Admin and Contract Admin Manager review the PSA Details and determine whether or not it meets the requirements for OGC Counsel Review.
If Reviewed is chosen the next step is Vendor Signs
If Send to OGC is chosen the next step is OGC Counsel Review
If Revise is chosen the next step is Initiator Revise PSA
Toggle Cloak
OGC Counsel Review
Cloak
The DOF General Counsel reviews the PSA Details.
If Reviewed is chosen the next step is Vendor Signs
If Revise is chosen the next step is Contracts Group Review PSA
Toggle Cloak
Vendor Signs
Cloak
The Process Initiator takes the appropriate action to sign the document.
If Submit is chosen the next step is Additional Funding?
If Revise is chosen the next step is Initiator Revise PSA
Toggle Cloak
PM Review PSA - Manual Req
Cloak
The Project Manager fills out all required fields and sends the PSA Document to the Vendor for a manual signature.
If Submit is chosen the next step is Hold for Signed PSA
If Revise is chosen the next step is Initiator Revise PSA
If Void is chosen the next step is Finish and the process is set to a Void status.
Toggle Cloak
Hold for Signed PSA
Cloak
The Project Manager and Contract Admin until they receive back the vendor manually signed PSA document and upload it to the process.
The next step is Additional Funding?
Toggle Cloak
Additional Funding?
Cloak
The Additional Funding? Conditional checks if Yes was selected for the Additional Project Funding? field.
If True (Yes) the next step is Spawn Budget Change (03.03)
If False (No) the next step is Program Manager Review
Toggle Cloak
Spawn Budget Change (03.03)
Cloak
This step spawns a 03.03 - Contingency Request / True-Up Form / Additional Funding Request (BCHNG) process.
The next step is CRSP Admin Mgr. Hold
Toggle Cloak
CRSP Admin Mgr. Hold
Cloak
The CRSP Admin holds the process in this step until additional funding has been applied to the project in both e-Builder and SAP.
The next step is Program Manager Review
Toggle Cloak
Program Manager Review
Cloak
The Program Manager reviews the vendor signed document in the PSA/MDA for Signature field.
If Submit is chosen the next step is Campus Construction?
If Revise is chosen the next step is Initiator Revise PSA
Toggle Cloak
Initiator Revise PSA
Cloak
The Initiator RevisePSA step allows the Process Initiator to make changes and resubmit the process.
If Resubmit is chosen the next step is MDA Release
If Void is chosen the next step is Finish and the process is set to a Void status.
Toggle Cloak
Campus Construction?
Cloak
The Campus Construction? Conditional checks if the Program Type of the project is Academic, Campus Services, Capital Group, Special, System Performance & Turn-over, or Systems Renewal
If True (Yes) the next step is SP&T Program?
If False (No) the next step is OCP?
Toggle Cloak
OCP?
Cloak
The OCP? Conditional checks if the Program Type of the project is OCP
If True (Yes) the next step is EstFinCon> $500K
If False (No) the next step is CSM?
Toggle Cloak
CSM?
Cloak
The CSM? Conditional checks if the Program Type of the project is CSG or R&M
If True (Yes) the next step is EstFinCon> $5m?
If False (No) the next step is Utilities Program?
Toggle Cloak
Utilities Program?
Cloak
The Utilities Program? Conditional checks if the Program Type of the project is CUP - OPS or Utilities
If True (Yes) the next step is Est Fin Cont>$1M
If False (No) the next step is FEG Program
Toggle Cloak
FEG Program?
Cloak
The FEG Program? Conditional checks if the Program Type of the project is Energy or SEG
If True (Yes) the next step is FEG Director Review
If False (No) the next step is EstFinCon >$1M
Toggle Cloak
EstFinCon > $1M
Cloak
The EstFinCon > $1M Conditional checks if >$1,000,000<=$5,000,000, >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
If True (Yes) the next step is EstFinCon>$10M
If False (No) the next step is Dir. Finance Execute
Toggle Cloak
SP&T Program?
Cloak
The SP&T Program? Conditional checks if the Program Type of the project is System Performance & Turn-over
If True (Yes) the next step is SPT Director Review
If False (No) the next step is EstFinCon >$10m
Toggle Cloak
EstFinCon> $500K
Cloak
The EstFinCon> $500K Conditional checks if >$500,000<=$1,000,000,>$1,000,000<=$5,000,000, >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
If True (Yes) the next step is OCP Director Review
If False (No) the next step is OCP Director Execute
Toggle Cloak
EstFinCon>$5m?
Cloak
The EstFinCon>$5m? Conditional checks if >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
If True (Yes) the next step is CSM Director Review
If False (No) the next step is CSM Director Execute
Toggle Cloak
Est Fin cont> $1M
Cloak
The Est Fin cont> $1M Conditional checks if >$1,000,000<=$5,000,000, >$5,000,000<=$10,000,000, >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
If True (Yes) the next step is Utilities Director Review
If False (No) the next step is Utilities Director Execute
Toggle Cloak
SPT Director Review
Cloak
The SPT Directorreviews the Process Details and the appropriate file in the Change Order Document Details section
Cloak
The OCP Director reads the comments and reviews the process fields and has the option to take an action to Submit or to Revise.
If Submit is chosen the next step is Administrative Assistant Final Review.EstFinCon>$10M
If Revise is chosen the next step is Initiator Revise .2
Toggle Cloak
27. M&U?OCP Director Review
Cloak
The OCP Directorreviews the Process Details and the appropriate file in the Change Order Document Details section.
If Submit is chosen
Cloak
Multiple fields are evaluated to determine if this is an M&U Program.
If Truethe next step is Utilities Program?EstFinCon>$10M
If FalseRevise is chosen the next step is Campus Services?Initiator Revise 2
Toggle Cloak
28. Utilities Program? (Decisional Step)CSM Director Review
Cloak
The M&U Directorreviews the Process Details and the appropriate file in the Change Order Document Details section.
If Submit is chosen
Cloak
Multiple fields are evaluated to determine if this is a Utilities program.
If Truethe next step is Contract <$100KEstFinCon>$10M
If FalseRevise is chosen the next step is SEG Program?Initiator Revise 2
Toggle Cloak
29. Contract <100K (Decisional Step)FEG Director Review
Cloak
The SEG Directorreviews the Process Details and the appropriate file in the Change Order Document Details section.
If Submit is chosen Cost Commitment.Current Contact Value is evaluated to determine if the value is < $100,000.If Truethe next step is Utilities Director Executes.EstFinCon>$10M
If FalseRevise is chosen the next step is Utilities Director Review.Initiator Revise 2
Toggle Cloak
30. Utilities Director ExecutesReview
Cloak
The Utilities Directorreads reviews the comments Process Detailsand reviews the process fields and has the option to take an action to Submit or Revisethe appropriate file in the Change Order Document Details section.
If Submit is chosen the next step is Administrative Assistant Final Review.EstFinCon>$10M
If Revise is chosen the next step is Initiator Revise .2
Toggle Cloak
31. Utilities Director ReviewDir. Finance Execute
Cloak
By taking the Approved action at this step the Director of Finance and Administration is Approving the process.
If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
If Revise is chosen the next step is Initiator Revise 2
If Send CC Director is
The Utilities Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
If Submit is chosen the next step is Contract <5m.
If Revise is chosen the next step isInitiator Revise CC Director Review.
Toggle Cloak
32. Contract <$5MEstFinCon>$10m
Cloak
The Cost Commitment.Current Contact Value is evaluated to determine if the value is < $500,000EstFinCon>$10m Conditional checks if >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
If True(Yes) the next step is M&U Director Executes.CC Director Review
If False(No) the next step is M&U Director Review.CC Director Execute
Toggle Cloak
33. M&U Director ExecutesCC Director Review
Cloak
The M&U CC Directorreads reviews the comments Process Detailsand reviews the process fields and has the option to take an action to Submit or Revisethe appropriate file in the Change Order Document Details section.
If Submit is chosen the next step is Administrative Assistant Final Review.EstFinCon>10<=100mil
If Revise is chosen the next step is Initiator Revise .2
Toggle Cloak
34. M&U Director Review
Cloak
The M&U Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
If Submit is chosen the next step is Contract Value <$100M.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
35. SEG Program? (Decisional Step)
Cloak
Multiple fields are evaluated to determine if this is an SEG Program.
If True the next step is Contract <$100K
If False the next step is Contract<$100K
Toggle Cloak
36. Contract <$100K (Decisional Field)
Cloak
The CostCommitment.CurrentContractValue field is evaluated to determine if it is <$100K
If True the next step is SEG Director Executes.
If False the next step is SEG Director Review.
Toggle Cloak
37. SEG Director Executes
Cloak
The SEG Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
If Submit is chosen the next step is Administrative Assistant Final Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
38. SEG Director Reviews
Cloak
The SEG Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
If Submit is chosen the next step is Contract <$5M (step 30)
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
39. Contract <$100K (Decisional Step)
CC Director Execute
Cloak
By taking the Approved action at this step the CC Director is Approving the process.
If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
If Revise is chosen the next step is Initiator Revise 2
Toggle Cloak
OCP Director Execute
Cloak
By taking the Approved action at this step the OCP Director is Approving the process.
If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
If Revise is chosen the next step is Initiator Revise 2
Toggle Cloak
CSM Director Execute
Cloak
By taking the Approved action at this step the M&U Director is Approving the process.
If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
If Revise is chosen the next step is Initiator Revise 2
Toggle Cloak
Utilitites Director Execute
Cloak
By taking the Approved action at this step the Utilities Director is Approving the process.
If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
If Revise is chosen the next step is Initiator Revise 2
Toggle Cloak
EstFinCon>$10M
Cloak
The EstFinCon>$10M Conditional checks if >$10,000,000<=$100,000,000, or >$100,000,000 was selected for the Estimated Final Contract Amount field.
If True (Yes) the next step is Dir of Fin & Adm Review 2.
If False (No) the next step is Dir of Fin & Adm Review 1.
Toggle Cloak
Dir of Fin & Adm Review 1
Cloak
The Director of Finance and Administration reviews the Process Details and the appropriate file in the Change Order Document Details section.
If Submit is chosen the next step is VP, CSS Execute.
If Revise is chosen the next step is Initiator Revise 2.
If Send CC Director is chosen the next step is CC
Cloak
The CostCommitment.CurrentContractValue field is evaluated to determine if it is <$100,000.
If True the next step is O&M Director Executes.
If False the next step is O&M Director Review.
Toggle Cloak
40. O&M Director ExecutesDir of Fin & Adm Review 2
Cloak
TheO&M Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
If Submit is chosen the next step is Administrative Assistant Final Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
41. O&M Director Review
Director of Finance and Administration reviews theProcess Details and the appropriate file in the Change Order Document Details section.
If Submit is chosen the next step is VP, CSS Review.
If Revise is chosen the next step is Initiator Revise 2.
If Send CC Director is chosen the next step is CC Director Review.
Toggle Cloak
VP, CSS Review
Cloak
The VP for Campus Services and Stewardshipreviews the Process Details and the appropriate file in the Change Order Document Details section
Cloak
The O&M Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
If Submit is chosen the next step is <undocumented>.EstFinCon>10<=100mil
If Revise is chosen the next step is Contract <$5M.Initiator Revise 2
Toggle Cloak
42. Campus Services? (Decisional Step)
Cloak
The CustomProject.ProgramType field is evaluated to determine if this is a Campus Services Program.
If True the next step is Contract <$5m.
If False the next step is Contract <$10m.
Toggle Cloak
43. Contract <$5M (Decisional Step)
Cloak
The CostCommitment.CurrentContractValue field is evaluated to determine if the value is <$5M.
If True the next step is CS Director Executes.
If False the next step is CS Director Review.
Toggle Cloak
44. CS Director Executes
Cloak
The CS Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
If Submit is chosen the next step is Administrative Assistant Final Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
45. CS Director Review
Cloak
The CS Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
If Submit is chosen the next step is Contract Value <$100M.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
46. Contract <$10M (Decisional Step)
Cloak
The CostCommitment.CurrentContractValue field is evaluated to determine if the contact value is <$10,000,000.
If True the next step is IBO Director Executes.
If False the next step is IBO Director Review.
Toggle Cloak
47. IBO Director Executes
Cloak
The IBO Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
If Submit is chosen the next step is Administrative Assistant Final Review.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
48. IBO Director Review
Cloak
The IBO Director reads the comments and reviews the process fields and has the option to take an action to Submit or Revise.
If Submit is chosen the next step is Contract Value <$100M.
If Revise is chosen the next step is Initiator Revise.
Toggle Cloak
49. Administrative Assistant Final Review
Cloak
The Administrative Assistant enters the change in SAP, completes the required process fields and executes the SAP Entry Completed action.
The next step is Finish.
50. Finish
VP, CSS Execute
Cloak
By taking the Approved action at this step the Deputy EVP is Approving the process.
If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
If Revise is chosen the next step is Initiator Revise 2
Toggle Cloak
EstFinCon>10<=100mil
Cloak
The EstFinCon>10<=100mil Conditional checks if >$10,000,000<=$100,000,000 was selected for the Estimated Final Contract Amount field.
If True (Yes) the next step is VP Finance Execute
If False (No) the next step is EVPT Execute
Toggle Cloak
VP Finance Execute
Cloak
By taking the Approved action at this step the VP for Finance is Approving the process.
If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
If Revise is chosen the next step is Initiator Revise 2
Toggle Cloak
EVPT Execute
Cloak
By taking the Approved action at this step the EVP&T Office is Approving the process.
If Approved is chosen the next step is Amendment Signature followed by the SAP Hold Step.
If Revise is chosen the next step is Initiator Revise 2
Toggle Cloak
Initiator Revise 2
Cloak
The Initiator Revise 2 step allows the Process Initiator to make changes and resubmit the process.
If Resubmit is chosen the next step is MDA Release
If Void is chosen the next step is Finish and the process is set to a Void status.
Toggle Cloak
Amendment Signature
Cloak
The Amendment Signature step is a e-Signature File Download automation step that completes the Docusign envelope.
The next step is SAP Hold Step
Toggle Cloak
SAP Hold Step
Cloak
Hold step for SAP Processing.
Once processed the next step is the PO MM step.
Toggle Cloak
PO MM
Cloak
The PO MM step is a mail merge automation step that completes the PSA PO CO MMmail merge document.
The next step is Project Manager Review
Toggle Cloak
AA/Contracts Sends Exec-PSA to Vendor
Cloak
The Administrative Assistant and Contract Admin should review the documents attached to the process, and send the executed documents to the vendor.